City of Lincoln v. Norris Public Power District

500 N.W.2d 183, 243 Neb. 458, 1993 Neb. LEXIS 150
CourtNebraska Supreme Court
DecidedMay 21, 1993
DocketS-91-430
StatusPublished
Cited by32 cases

This text of 500 N.W.2d 183 (City of Lincoln v. Norris Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lincoln v. Norris Public Power District, 500 N.W.2d 183, 243 Neb. 458, 1993 Neb. LEXIS 150 (Neb. 1993).

Opinion

Caporale, J.

I. STATEMENT OF CASE

The applicant-appellant, City of Lincoln (doing business as Lincoln Electric System), sought from the Nebraska Power Review Board a modification of the city’s electrical service area so as to permit the city to supply electrical services in an area now served by the protestant-appellee, Norris Public Power District. Prior to hearing, Norris unsuccessfully moved to dismiss the application on the ground that the city had not pled facts entitling it to the relief it sought. The matter then proceeded to hearing. At the close of the city’s evidence, Norris successfully moved for dismissal on the ground that the city had failed to establish facts entitling it to a modification. The dispositive assignments of error asserted by the city may be summarized as claiming that the board (1) misinterpreted the applicable statutes and (2) failed to apply the law of the case. We affirm.

II. CONTENTIONS OF PARTIES

In general, the city alleges that as the result of an annexation, it acquired planning and zoning jurisdiction beyond its corporate limits and into the subject area, where Norris presently supplies electrical services. Claiming that it must plan for and be prepared to meet the increased demand for electrical services created by the continuing urbanization of areas within its planning and zoning jurisdiction, the city asserts that its *460 service area must be modified under the provisions of Neb. Rev. Stat. § 70-1007 (Reissue 1990).

Norris’ position is that not only did the city fail to allege facts entitling it to a modification of its service area, it failed to prove facts entitling it to such.

III. THE RECORD

The record establishes the city’s planning and zoning jurisdiction over the subject area, which consists of approximately 6 square miles falling within Norris’ service area and contains 28 consumers of Norris’ electrical services.

The record further demonstrates that the city has acquired other areas previously served by Norris and integrated them into the city’s system; however, considerable effort, and apparently expense, was required to conform Norris’ installations to the city’s standards.

For example, the city uses a three-phase circuit with cable rated at 15,000 volts capable of carrying 580 to 590 amperes. In contrast, Norris uses smaller cable capable of carrying only 200 amperes. The city typically needs between 3 to 5 years of leadtime in order to design and construct the urban electrical delivery system it uses. Optimally, the city locates its substations on 2- to 2‘A-mile centers, looped so that the various substations back each other up in the event of breakdowns, thus avoiding losses of electrical services to its consumers. When an area has already been developed, the process of obtaining the needed rights-of-way to construct substations becomes difficult and expensive. Moreover, placing larger equipment into an existing neighborhood is disruptive. Therefore, the city prefers to begin serving an area prior to active development.

Although the contestants have been able to agree on day-to-day operational matters, Norris has refused to transfer any territory or customers to the city. It has even refused to engage in any planning with regard to future transfers until annexation has actually taken place. In the city’s view, waiting until annexation or just before to engage in joint planning is too late — “the interface between an urban system and a rural system occurs better in an area of lower density than higher density.” The city would like to establish a “set of mutually *461 agreeable items that would indicate how the parties would plan a transition from one utility to another as the area grows.”

The city also adduced evidence that it has grown both in area and population and will continue to do so into the foreseeable future and that the subject area will be developed and be annexed at some unspecified future time. In comparison to peer utilities, the city “performfs] very well” in terms of outages and does so at competitive rates. Indeed, if the city had been serving the subject area in 1989, the 28 consumers involved would have paid almost 19 percent less for their electricity. However, the city will need to acquire increased electrical capacity, and as a consequence, its average rate is more likely to increase than to decrease.

There is no evidence that Norris is unable to service the consumers in the subject area or that such service involves a wasteful and unwarranted duplication of facilities.

IV. ANALYSIS

With the foregoing background, we proceed to a consideration of each of the city’s two dispositive and summarized assignments of error.

1. Interpretation of Statutes

The first of these assignments of error claims that the board misinterpreted the applicable statutes. In addition to § 70-1007, mentioned in part II above, the statutes which control the resolution of the substantive issues in this case are found at Neb. Rev. Stat. §§ 70-1005, 70-1008, 70-1010(1), and 70-1011 (Reissue 1990).

Section 70-1005 provides:

Any supplier may at any time on or after July 1, 1964, apply to the board to establish its service area. In such case and in all cases where agreements have not been entered into, including cases arising under section 70-1008, the secretary shall give written notice to the parties involved citing them to appear at a time, not less than thirty days thereafter, and at a place specified in the notice for a hearing upon the matter of establishing the service areas concerned in the notice. The provisions of this section shall not apply to service within the corporate limits of any *462 municipality.

Section 70-1007 reads:

After the hearing, the board shall make an order establishing the service areas in the matter covered by the notice. In determining any such matter, the board shall seek to carry out the policy stated in section 70-1001. It shall give such consideration as is appropriate in each case to the following:
(1) The supplier best able to supply the load required;
(2) The most logical future supplier of the area;
(3) The desires of the supplier with respect to loads and service areas it wishes to serve;
(4) The ability to provide service at costs comparable to other suppliers in the service area and the immediate costs to the ultimate consumers involved in the transfer; and
(5) The ability of the supplier to cope with the problems of expanding loads and increased costs.

Neb. Rev. Stat. § 70-1001

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Tek Mfg., Inc. v. Beehner
751 N.W.2d 135 (Nebraska Supreme Court, 2008)
Money v. Flowers
748 N.W.2d 49 (Nebraska Supreme Court, 2008)
Miller v. Commercial Contractors Equipment, Inc.
711 N.W.2d 893 (Nebraska Court of Appeals, 2006)
Weeder v. Central Community College
691 N.W.2d 508 (Nebraska Supreme Court, 2005)
Houston v. Metrovision, Inc.
677 N.W.2d 139 (Nebraska Supreme Court, 2004)
Billingsley v. BFM Liquor Management, Inc.
645 N.W.2d 791 (Nebraska Supreme Court, 2002)
State v. Carter
586 N.W.2d 818 (Nebraska Supreme Court, 1998)
Carpenter v. Cullan
581 N.W.2d 72 (Nebraska Supreme Court, 1998)
Hoiengs v. County of Adams
574 N.W.2d 498 (Nebraska Supreme Court, 1998)
Talle v. Nebraska Department of Social Services
572 N.W.2d 790 (Nebraska Supreme Court, 1998)
Slagle v. J.P. Theisen & Sons, Inc.
560 N.W.2d 758 (Nebraska Supreme Court, 1997)
Kerrigan & Line v. Foote
558 N.W.2d 837 (Nebraska Court of Appeals, 1997)
Scotts Bluff County v. Department of Social Services
550 N.W.2d 13 (Nebraska Supreme Court, 1996)
Boss v. FILLMORE COUNTY SCHOOL DIST.
548 N.W.2d 1 (Nebraska Court of Appeals, 1996)
Boss v. Fillmore County School District No. 19
548 N.W.2d 1 (Nebraska Court of Appeals, 1996)
In Re Adoption of Kassandra B.
540 N.W.2d 554 (Nebraska Supreme Court, 1995)
Keith County v. Department of Social Services
540 N.W.2d 109 (Nebraska Supreme Court, 1995)
Smith v. State, Dept. of Motor Vehicles
535 N.W.2d 694 (Nebraska Supreme Court, 1995)
Anderson v. Nashua Corp.
519 N.W.2d 275 (Nebraska Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
500 N.W.2d 183, 243 Neb. 458, 1993 Neb. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lincoln-v-norris-public-power-district-neb-1993.