City of Cut Bank v. Tom Patrick Construction, Inc.

1998 MT 219, 963 P.2d 1283, 290 Mont. 470, 55 State Rptr. 915, 1998 Mont. LEXIS 201
CourtMontana Supreme Court
DecidedSeptember 3, 1998
Docket97-718
StatusPublished
Cited by8 cases

This text of 1998 MT 219 (City of Cut Bank v. Tom Patrick Construction, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cut Bank v. Tom Patrick Construction, Inc., 1998 MT 219, 963 P.2d 1283, 290 Mont. 470, 55 State Rptr. 915, 1998 Mont. LEXIS 201 (Mo. 1998).

Opinions

JUSTICE LEAPHART

delivered the Opinion of the Court.

¶1 City of Cut Bank (Cut Bank) appeals from the decision of the Ninth Judicial District Court, Glacier County, dismissing with prejudice Cut Bank’s complaint based upon the United States Supreme Court’s decision in Doctor’s Associates, Inc. v. Casarotto (1996), 517 U.S. 681, 116 S.Ct. 1652, 134 L.Ed.2d 902 (Casarotto). More specifically, the District Court determined that the transaction between Cut Bank and Tom Patrick Construction (Tom Patrick), which is the basis of the current action, involved interstate commerce and thus must be arbitrated pursuant to the Federal Arbitration Act (FAA). We reverse and remand.

Factual and Procedural Background

¶2 Cut Bank entered into a construction contract with Tom Patrick on November 16,1993. The contract required Tom Patrick to replace a water line in Bum Coulee, construct an access road and stabilize the surrounding coulee and ditch areas. Tom Patrick completed the first two stages — replacing the water line and constructing the access road. Cut Bank, however, contends that the riprap materials used by Tom Patrick in the stabilization stage of the construction were insufficient to complete the project to specifications.

¶3 Cut Bank made several requests that Tom Patrick complete the project in accordance with the contract but eventually hired the services of another contractor to complete the project according to specifications. Completion of the project was more costly than the original contract price. Cut Bank refused to the make final payment due to [472]*472Tom Patrick under the contract and refused to surrender Tom Patrick’s bond and performance bond.

¶4 As a result, Tom Patrick served Cut Bank with a notice of intent to arbitrate the dispute. Cut Bank objected to arbitration proceedings, asserting that no valid contract for arbitration existed because the construction contract did not comply with § 27-5-114(4), MCA (1993), which required that notice that a contract is subj ect to arbitration be typed in underlined capital letters on the front page of the contract. Cut Bank filed a complaint in District Court seeking a stay of arbitration. Tom Patrick dismissed the arbitration proceedings and requested that the District Court stay further proceedings pending the resolution of the challenge to § 27-5-114, MCA, in Casarotto. The District Court granted the stay.

¶5 The United States Supreme Court issued its decision in Casarotto (1996), 517 U.S. 681, 116 S.Ct. 1652, 134 L.Ed.2d 902, determining that §27-5-114(4), MCA, was preempted by the FAA. Thereafter, Tom Patrick moved to dismiss Cut Bank’s complaint for failure to state a cause of action. Cut Bank responded that the FAA was not applicable to the construction contract because the contract did not involve interstate commerce. The District Court, citing Casarotto, dismissed Cut Bank’s complaint with prejudice. Cut Bank appeals to this Court presenting three issues for review. We determine that the issue of whether the complaint alleges an underlying contract involving interstate commerce is dispositive and therefore do not reach the remaining issues.

Standard of Review

¶6 Our standard of review of district court rulings on motions to dismiss under Rule 12(b)(6), M.R.Civ.P, is set forth in Willson v. Taylor (1981), 194 Mont. 123, 634 P.2d 1180:

A complaint should not be dismissed for failure to state a claim unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief. A motion to dismiss under Rule 12(b)(6), M.R.Civ.P., has the effect of admitting all well-pleaded allegations in the complaint. In considering the motion, the complaint is construed in the light most favorable to the plaintiff, and all allegations of fact contained therein are taken as true.

Willson, 194 Mont. at 126, 634 P.2d at 1182 (citations omitted). The District Court’s determination that Cut Bank’s complaint failed to state a claim is a conclusion of law. Our standard of review of the trial [473]*473court’s conclusions of law is whether the tribunal’s interpretation of the law is correct. Steer, Inc. v. Department of Revenue (1990), 245 Mont. 470, 474-75, 803 P.2d 601, 603.

Discussion

¶7 Congress, in enacting the FAA, sought to foreclose state legislative attempts to undercut the enforceability of arbitration agreements. The United States Supreme Court has explained that § 2 of the FAA reflects a strong national policy favoring arbitration agreements. Perry v. Thomas (1987), 482 U.S. 483, 107 S.Ct. 2520, 96 L.Ed.2d 426. As a result of this strong policy, agreements to arbitrate will be upheld under the FAA unless the agreement is not part of a contract evidencing interstate commerce or is revocable “upon such grounds as exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2.

¶8 Recognizing that many contracts provide little warning to parties that a contract is subject to arbitration, the Montana legislature enacted § 27-5-114(4), MCA. That section required that notice that a contract was subject to arbitration be printed in capitalized underlined print on the front of the contract. In so providing, the legislature sought to ensure that parties to a contract were aware, when they signed a contract subject to an arbitration clause, that they were waiving their constitutional right to access the courts. The legislature sought to prevent parties from waiving that right without their full knowledge.

¶9 Specifically, § 27-5-114(4), MCA, stated that “notice that a contract is subject to arbitration pursuant to this chapter shall be typed in underlined capital letters on the first page of the contract; and unless such notice is displayed thereon, the contract may not be subject to arbitration.” This section (since repealed) was in effect in November 1993, at the time that Cut Bank entered into the construction contract with Tom Patrick. The construction contract did not comply with the notice requirement of § 27-5-114(4), MCA. Rather, Section 16.1, located in the Standard General Conditions on page 110 of the Contract Documents, stated that “[a]ll claims, disputes and other matters in question between [Cut Bank] and [Tom Patrick] arising out of or relating to the Contract Documents or the breach thereof... will be decided by arbitration ....’’At the District Court, Cut Bank contended that this provision does not comply with the requirements of § 27-5-114(4), MCA, therefore that the agreement to arbitrate is not enforceable. Tom Patrick, on the other hand, maintained that this ac[474]*474tion is controlled by the United States Supreme Court’s decision in Casarotto.

¶10 The United States Supreme Court, in Casarotto, held that Montana’s first-page notice requirement found at § 27-5-114(4), MCA, conflicted with the FAA and was therefore preempted by the federal law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grigg v. Paul
2023 MT 23N (Montana Supreme Court, 2023)
Abraham v. Hull & Swingley
2020 MT 254N (Montana Supreme Court, 2020)
Anderson v. Recontrust Co.
2017 MT 313 (Montana Supreme Court, 2017)
Cowan v. Cowan
2004 MT 97 (Montana Supreme Court, 2004)
Bar OK Ranch, Co. v. Ehlert
2002 MT 12 (Montana Supreme Court, 2002)
Chapman v. McVicher
1999 MT 293N (Montana Supreme Court, 1999)
City of Cut Bank v. Tom Patrick Construction, Inc.
1998 MT 219 (Montana Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
1998 MT 219, 963 P.2d 1283, 290 Mont. 470, 55 State Rptr. 915, 1998 Mont. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cut-bank-v-tom-patrick-construction-inc-mont-1998.