City of Centralia, Washington v. Federal Energy Regulatory Commission, and Pacific Power and Light Company, Respondent-Intervenor

799 F.2d 475, 1986 U.S. App. LEXIS 29401
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 4, 1986
Docket85-7082
StatusPublished
Cited by1 cases

This text of 799 F.2d 475 (City of Centralia, Washington v. Federal Energy Regulatory Commission, and Pacific Power and Light Company, Respondent-Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Centralia, Washington v. Federal Energy Regulatory Commission, and Pacific Power and Light Company, Respondent-Intervenor, 799 F.2d 475, 1986 U.S. App. LEXIS 29401 (9th Cir. 1986).

Opinion

REINHARDT, Circuit Judge:

In this challenge to the Federal Energy Regulatory Commission’s disposition of two competing applications to develop a hydroelectric project at a dam, we review the policies developed by the Commission to reconcile its differing mandates under the Federal Power Act and the Public Utility Regulatory Policies Act of 1978, as amended by the Energy Security Act of 1980. We affirm those policies under the two acts and affirm its disposition of the competing applications.

I. BACKGROUND

A. Statutory Framework

Congress enacted the Federal Power Act (FPA) to promote the “ ‘comprehensive development of water power.’ ” Chemehuevi Tribe of Indians v. FPC, 420 U.S. 395, 405, 95 S.Ct. 1066, 1073, 43 L.Ed.2d 279 (1975) (quoting FPC v. Union Electric Co., 381 U.S. 90, 101, 85 S.Ct. 1253, 1259, 14 L.Ed.2d 239 (1965)). In furtherance of that objective and to assure that such development serve the public interest, Congress established a licensing scheme, administered by the Commission, in Subchapter I of the FPA, 16 U.S.C. §§ 791a-823a (1982), for the construction, operation, and maintenance of hydroelectric power projects. Northern Colorado Water Conservancy District v. FERC, 730 F.2d 1509, 1512 (D.C.Cir.1984). The Commission must find that the licensee’s project will be “best adapted to a comprehensive plan for ... the improvement and utilization of waterpower development, and for other beneficial public uses....” 16 U.S.C. § 803(a); see also Udall v. FPC, 387 U.S. 428, 450, 87 S.Ct. 1712, 1724, 18 L.Ed.2d 869 (1967).

The Commission may issue preliminary permits to competing license applicants. 16 U.S.C. § 797(f). A permit maintains the permittee’s priority of application against potential competitors for the project site while the permitee compiles the data required for licensing. 16 U.S.C. § 798. A permit guarantees priority of consideration to the permittee for up to three years. 16 U.S.C. § 798. A permit is not a prerequisite to studying a site or to submitting a license application.

Prompted by the energy crisis of the 1970’s, Congress enacted the Public Utility Regulatory Policies Act of 1978 (PURPA) in order to expedite the development of certain hydroelectric power projects. Idaho Power Co. v. FERC, 766 F.2d 1348, 1350 (9th Cir.1985); H.R.Rep. No. 543, 95th Cong., 2d Sess. 22, 49, 304, reprinted in 1978 U.S.Code Cong. & Ad. News 7659, 7673, 7691, 7716, 7796. PURPA authorizes the Commission to exempt from the licensing procedures of the FPA projects with a generating capacity of up to fifteen megawatts, but only if those projects will utilize solely the hydroelectric potential of existing water conduits not operated primarily for the production of power. 16 U.S.C. § 823a(a), (b).

In the Energy Security Act of 1980, 16 U.S.C. §§ 2705, 2708 (1982), Congress amended PURPA to expand the Commission’s exemption authority to include projects of up to five megawatts that would utilize the hydroelectric potential at an existing dam; however, to receive an exemption under the 1980 amendments, the project’s completion must not require any construction or enlargement of the existing dam’s impoundment structures, 16 U.S.C. § 2708(a)(6). Neither PURPA as originally enacted nor the Energy Security Act *478 amendments requires that an exemption proposal be “best adapted” to the site.

B. Regulatory Framework

1. The Standard for Exemptions

Under its Energy Security Act regulations, the Commission may grant exemptions for small hydroelectric projects if it finds the exemption to be consistent with the public interest. 18 C.F.R. § 4.105(b)(5) (1984). If the Commission does not act on an application for exemption within 120 days after notifying the applicant that its application has been accepted for filing, the exemption will be deemed consistent with the public interest and granted. 18 C.F.R. § 4.105(b)(4) (1984); International Paper Co. v. FERC, 737 F.2d 1159, 1162 (D.C.Cir. 1984).

The Commission has interpreted its public interest standard to require that an exemption proposal “adequately utilize[] the water resources of the site, taking into account other considerations such as environmental constraints.” Frontier Technology, Inc., 22 FERC ¶ 61,267, at 61,479 (1983). Under the Commission’s informal test for adequate utilization, a project adequately utilizes the water resources of a site if it leaves the available water unused no more than 25% of the time. Western Power, Inc., 23 FERC ¶ 61,343, at 61,745 n. 9 (1983). If an exemption proposal does not meet this guideline, the applicant must demonstrate why a lesser use is nevertheless appropriate. Id. Otherwise, the Commission will conclude that the exemption is not in the public interest and will not grant it. Id.

2. The Property Rights Requirement for Exemptions

The Commission requires that exemption applicants own or have an option to purchase the property rights necessary to develop their project. 18 C.F.R. § 4.103(b)(2)(ii) (1984). Unlike license holders, exemption holders have no power of eminent domain. Minnesota Department of Natural Resources, 31 FERC ¶ 61,223, at 61,447 (1985). The Commission’s ownership requirement avoids delays from property rights disputes, thereby effectuating Congress’ directive to expedite power development. See Preamble to Order No. 106, FERC Statutes & Regulations, Regulations Preambles 1977-81 ¶ 30,204 at p. 31,366 (1980); 45 Fed.Reg. 76115, 76119 (Nov. 18, 1980); Fluid Energy Systems, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
799 F.2d 475, 1986 U.S. App. LEXIS 29401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-centralia-washington-v-federal-energy-regulatory-commission-and-ca9-1986.