City of Ukiah, California v. Federal Energy Regulatory Commission, Sonoma County Water Agency, Intervenor

729 F.2d 793, 234 U.S. App. D.C. 307, 1984 U.S. App. LEXIS 24814
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 6, 1984
Docket83-1114, 83-1181
StatusPublished
Cited by6 cases

This text of 729 F.2d 793 (City of Ukiah, California v. Federal Energy Regulatory Commission, Sonoma County Water Agency, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Ukiah, California v. Federal Energy Regulatory Commission, Sonoma County Water Agency, Intervenor, 729 F.2d 793, 234 U.S. App. D.C. 307, 1984 U.S. App. LEXIS 24814 (D.C. Cir. 1984).

Opinion

TAMM, Circuit Judge:

Petitioner, City of Ukiah, appeals the Federal Energy Regulatory Commission’s (the Commission) issuance of a permit to Sonoma County Water Agency to study the feasibility of operating a hydroelectric generating plant. Petitioner asserts both substantive and procedural objections to the Commission’s decision. Because we find the Commission’s decision procedurally sound and supported by substantial evidence on the record as a whole, we affirm.

I. BACKGROUND

The City of Ukiah (Ukiah) applied to the Commission on May 27, 1980 for a “preliminary permit” to study the possibility of operating a hydroelectric generating plant at Warm Springs Dam. 1 Sonoma County Water Agency (Sonoma), intervenors in this action, applied for the same permit on August 25, 1980. Under the Commission’s regulations, the first-filed applicant is to be awarded the permit unless a subsequent applicant demonstrates an advantage in generating potential. 2 Here, the Commission found that Sonoma had demonstrated a capacity to produce substantially more electricity than Ukiah. Accordingly, the Commission awarded the permit to Sonoma. 3

The Commission’s conclusion that Sonoma could generate significantly more electricity than Ukiah at Warm Springs Dam rests primarily on a contractual relationship between Sonoma and the Army Corps of Engineers (the Corps). In 1964, Sonoma entered into a contract (1964 contract) with the Corps to purchase three blocks of water storage space in the reservoir (Lake Sonoma) behind Warm Springs Dam. Joint Appendix (J.A.) 649-60. 4 Most important for this case, the contract also gave Sonoma discretion to direct releases and regulate the use of stored water. J.A. 509, 653, 658.

*795 In its initial decision, the Commission found that Sonoma, by virtue of “its authority to direct water releases from [Warm Springs Dam], has demonstrated ... the ability to produce substantially more power ... than ... Ukiah.” City of Ukiah, 18 FERC (CCH) ¶ 61,108, at 61,204 (1982) (Order Issuing Preliminary Permit and Denying Competing Application). The Commission also acknowledged Sonoma’s claim that if it generated electricity at Warm Springs Dam, it would release excess water to increase power production. Id. at 61,203. Since there is a cost associated with releasing stored water, Sonoma noted that it would promote power generation only if it, and not Ukiah, received the benefits from the project. 5 J.A. 71-72. Consequently, the Commission concluded that “Sonoma’s control of water releases from Warm Springs Dam ... uniquely qualifies Sonoma as a superior applicant for a preliminary permit.” Id.

Ukiah applied for a rehearing of this order on March 12, 1982. 6 In its application, Ukiah argued that if Sonoma released water for power generation, Sonoma would be required to begin repayment of the project’s costs. Ukiah thus asserted that even if Sonoma’s contract with the Corps allowed Sonoma to release water for power generation, there would be a significant economic disincentive discouraging such releases.

In October 1982, following the issuance of the Commission’s initial order, Sonoma and the Corps signed an amended contract (1982 contract). In the new contract, Sonoma agreed to purchase a fourth block of storage space and to begin paying the Corps for each block in 1993, 1996, 2001, and 2006 respectively, regardless of when consumptive use begins. J.A. 347-48; see id. at 511, 514. Also, Sonoma retained its discretion to direct releases from the Warm Springs Dam reservoir. J.A. 344-45. In considering Ukiah’s rehearing application, the Commission noted that the 1982 contract “severs the relationship between payback of the project’s costs and actual use of the stored water.” City of Ukiah, 21 FERC (CCH) ¶ 61,133, at 61,361 n. 2 (1982) (Order Denying Rehearing). The Commission determined that since Sonoma could release water without triggering its repayment obligation, no economic disincentive would discourage Sonoma from releasing stored water for power generation before the water was needed for consumption. Id. at 61,361. The Commission thus concluded that Sonoma had the “operational flexibility” regarding water releases to produce significantly more power at the dam than Ukiah, and rejected Ukiah’s rehearing application. Id. at 61,361 n. 2.

On January 26, 1983, the Commission rejected Ukiah’s second application for rehearing essentially for the same reasons that it granted Sonoma the permit in its initial decision. City of Ukiah, 22 FERC (CCH) ¶ 61,063 (1983) (Notice Rejecting Application for Rehearing and Reconsideration). Ukiah has appealed the Commission’s denials of rehearing as well as its initial issuance of the permit to Sonoma. Ukiah asserts that the Commission’s issuance of the permit is not supported by substantial evidence and is proeedurally flawed. After full consideration, we find that the Commission’s decision is substantively and proeedurally sound. Accordingly, we affirm.

II. UKIAH’S SUBSTANTIVE CLAIM

Ukiah contends that the Commission’s decision to grant Sonoma' the permit was not supported by substantial evidence. Ukiah disputes the Commission’s finding *796 that Sonoma’s contractual relation with the Corps gives Sonoma a comparative advantage in power generation. Ukiah argues instead that both applicants can produce essentially the same amount of power and that it, as the first-filed applicant, therefore deserves the permit.

Sonoma’s contract will afford it an advantage in power generation if three conditions exist. First, Sonoma must have excess water in its storage space that could be released for nonconsumptive purposes. Second, the contract must give Sonoma the discretion to release its stored water for nonconsumptive purposes. Third, there must be no significant economic disincentive discouraging Sonoma from releasing its stored water for noneonsumptive purposes.

The first condition is an empirical concern and may be disposed of briefly. All parties to this litigation agree that Sonoma County probably will not require consumptive use of Sonoma's stored water until the 1990’s. The last block of Sonoma’s stored water is not scheduled for use until approximately 2010. J.A. 64. Thus, for about twenty-five years at least a portion of the stored water will be available for nonconsumptive releases. 7

The second two conditions require an examination of Sonoma’s contract and the Water Supply Act of 1958, 43 U.S.C. § 390b (1976) (Water Supply Act). Both inquiries may be considered questions of law. Danks v. Fields, 696 F.2d 572, 575 (8th Cir.1982) (interpretation of a written document is question of law).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wisconsin Gas Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Anr Pipeline Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Great Lakes Gas Transmission Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Midwestern Gas Transmission Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Tennessee Gas Pipeline Company, a Division of Tenneco Inc. v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. City Gas Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Madison Gas & Electric Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Wisconsin Power & Light Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Wisconsin Natural Gas Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Wisconsin Power & Light Company v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Wisconsin Public Service Corporation v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Michigan Gas Utilities Company, Intervenors. Trunkline Gas Company v. Federal Energy Regulatory Commission, Michigan Gas Utilities Company, Intervenors. Migc, Inc. v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Texas Eastern Transmission Corporation v. Federal Energy Regulatory Commission, Michigan Consolidated Gas Company, Intervenors. Arkansas Louisiana Gas Company, a Division of Arkla, Inc. v. Federal Energy Regulatory Commission, Pan-Alberta Gas Ltd., Intervenors. Transcontinental Gas Pipe Line Corporation v. Federal Energy Regulatory Commission, Pan-Alberta Gas Ltd., Intervenors. Algonquin Gas Transmission Company v. Federal Energy Regulatory Commission, Pan-Alberta Gas Ltd., Intervenors. Texas Gas Transmission Corporation v. Federal Energy Regulatory Commission, Consumers Power Company, Intervenors. Pacific Interstate Offshore Company v. Federal Energy Regulatory Commission, Consumers Power Company, Intervenors. Cascade Natural Gas Corporation, Northwest Natural Gas Company, Washington Natural Gas Company v. Federal Energy Regulatory Commission, Consumers Power Company, Intervenors. Arkansas Louisiana Gas Company, a Division of Arkla, Inc. v. Federal Energy Regulatory Commission, Pacific Gas and Electric Company, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Pan-Alberta Gas Ltd., Intervenors. Migc, Inc. v. Federal Energy Regulatory Commission, Arkansas Louisiana Gas Company, a Division of Arkla, Inc. v. Federal Energy Regulatory Commission
770 F.2d 1144 (D.C. Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
729 F.2d 793, 234 U.S. App. D.C. 307, 1984 U.S. App. LEXIS 24814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-ukiah-california-v-federal-energy-regulatory-commission-sonoma-cadc-1984.