FEDERAL · 16 U.S.C. · Chapter SUBCHAPTER I—REGULATION OF THE DEVELOPMENT OF WATER POWER AND RESOURCES

Conduit hydroelectric facilities

16 U.S.C. § 823a
Title16Conservation
ChapterSUBCHAPTER I—REGULATION OF THE DEVELOPMENT OF WATER POWER AND RESOURCES

This text of 16 U.S.C. § 823a (Conduit hydroelectric facilities) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
16 U.S.C. § 823a.

Text

(a)Qualifying conduit hydropower facilities
(1)A qualifying conduit hydropower facility shall not be required to be licensed under this subchapter.
(2)(A) Any person, State, or municipality proposing to construct a qualifying conduit hydropower facility shall file with the Commission a notice of intent to construct such facility. The notice shall include sufficient information to demonstrate that the facility meets the qualifying criteria.
(B)Not later than 15 days after receipt of a notice of intent filed under subparagraph (A), the Commission shall—
(i)make an initial determination as to whether the facility meets the qualifying criteria; and
(ii)if the Commission makes an initial determination, pursuant to clause (i), that the facility meets the qualifying criteria, publish public

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crossroads Cogeneration Corporation v. Orange & Rockland Utilities, Inc
159 F.3d 129 (Third Circuit, 1998)
52 case citations
Kamine/Besicorp Allegany L.P. v. Rochester Gas & Electric Corp.
908 F. Supp. 1180 (W.D. New York, 1995)
10 case citations
In Re Megan-Racine Associates, Inc.
949 F. Supp. 873 (N.D. New York, 1996)
7 case citations
Swanson Mining Corporation v. Federal Energy Regulatory Commission
790 F.2d 96 (D.C. Circuit, 1986)
6 case citations
Crossroads Cogeneration Corp. v. Orange & Rockland Utilities, Inc.
969 F. Supp. 907 (D. New Jersey, 1997)
6 case citations
City of Tacoma v. Federal Energy Regulatory Commission
331 F.3d 106 (D.C. Circuit, 2003)
5 case citations
Steamboaters v. Federal Energy Regulatory, Commission
759 F.2d 1382 (Ninth Circuit, 1985)
3 case citations
Idaho Power Company v. Federal Energy Regulatory Commission
767 F.2d 1359 (Ninth Circuit, 1985)
3 case citations
Wisconsin Valley Improvement Co. v. Meyer
910 F. Supp. 1375 (W.D. Wisconsin, 1996)
3 case citations
Phoenix Hydro Corp. v. Federal Energy Regulatory Commission
775 F.2d 1187 (D.C. Circuit, 1985)
1 case citations
Bristol Energy Corp. v. State of New Hampshire Public Utilities Commission
827 F. Supp. 81 (D. New Hampshire, 1993)
1 case citations
Monticello v. Public Service Commn
2019 UT 43 (Utah Supreme Court, 2019)
1 case citations
Adrian Energy v. MI Pub Serv
(Sixth Circuit, 2007)

Source Credit

History

(June 10, 1920, ch. 285, pt. I, §30, as added Pub. L. 95–617, title II, §213, Nov. 9, 1978, 92 Stat. 3148; amended Pub. L. 99–495, §7, Oct. 16, 1986, 100 Stat. 1248; Pub. L. 113–23, §4(a), Aug. 9, 2013, 127 Stat. 494; Pub. L. 115–270, title III, §3002, Oct. 23, 2018, 132 Stat. 3863.)

Editorial Notes

Editorial Notes

References in Text
The Fish and Wildlife Coordination Act, referred to in subsec. (c), is act Mar. 10, 1934, ch. 55, 48 Stat. 401, which is classified generally to sections 661 to 666c–1 of this title. For complete classification of this Act to the Code, see section 661(a) of this title, Short Title note set out under section 661 of this title, and Tables.

Prior Provisions
A prior section 30 of act June 10, 1920, was classified to section 791 of this title, prior to repeal by act Aug. 26, 1935, ch. 687, title II, §212, 49 Stat. 847.

Amendments
2018—Subsec. (a)(2)(C). Pub. L. 115–270, §3002(1), substituted "30 days" for "45 days" in introductory provisions.
Subsec. (a)(3)(C)(ii). Pub. L. 115–270, §3002(2), substituted "40 megawatts" for "5 megawatts".
2013—Subsecs. (a), (b). Pub. L. 113–23, §4(a)(1), added subsecs. (a) and (b) and struck out former subsecs. (a) and (b) which authorized the Commission to grant exemptions from the requirements of this subchapter for certain hydroelectric facilities and prohibited the granting of exemptions to facilities with certain capacities.
Subsec. (c). Pub. L. 113–23, §4(a)(2), substituted "subsection (b)" for "subsection (a)" in introductory provisions.
Subsec. (d). Pub. L. 113–23, §4(a)(3), substituted "subsection (b)" for "subsection (a)".
1986—Subsec. (b). Pub. L. 99–495, §7(a), inserted provision setting the maximum installation capacity for exemptions under subsec. (a) at 40 megawatts in the case of a facility constructed, operated, and maintained by an agency or instrumentality of a State or local government solely for water supply for municipal purposes.
Subsec. (c). Pub. L. 99–495, §7(b), which directed the insertion of "National Marine Fisheries Service" after "the Fish and Wildlife Service" in both places such term appears, was executed by inserting "National Marine Fisheries Service" after "the United States Fish and Wildlife Service" and "the Fish and Wildlife Service", as the probable intent of Congress.
Subsec. (e). Pub. L. 99–495, §7(c), added subsec. (e).

Statutory Notes and Related Subsidiaries

Effective Date of 1986 Amendment
Amendment by Pub. L. 99–495 effective with respect to each license, permit, or exemption issued under this chapter after Oct. 16, 1986, see section 18 of Pub. L. 99–495, set out as a note under section 797 of this title.

Application of Subsection (c)
Pub. L. 99–495, §8(c), Oct. 16, 1986, 100 Stat. 1251, provided that: "Nothing in this Act [see Short Title of 1986 Amendment note set out under section 791a of this title] shall affect the application of section 30(c) of the Federal Power Act [16 U.S.C. 823a(c)] to any exemption issued after the enactment of this Act [Oct. 16, 1986]."

Cite This Page — Counsel Stack

Bluebook (online)
16 U.S.C. § 823a, Counsel Stack Legal Research, https://law.counselstack.com/usc/16/823a.