Phoenix Hydro Corp. v. Federal Energy Regulatory Commission

775 F.2d 1187, 249 U.S. App. D.C. 354
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 5, 1985
DocketNos. 84-1197, 84-1207
StatusPublished
Cited by1 cases

This text of 775 F.2d 1187 (Phoenix Hydro Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phoenix Hydro Corp. v. Federal Energy Regulatory Commission, 775 F.2d 1187, 249 U.S. App. D.C. 354 (D.C. Cir. 1985).

Opinion

MIKVA, Circuit Judge:

A builder seeking to construct, operate, or maintain a hydroelectric generating facility must obtain a license from the Federal Energy Regulatory Commission (“the Commission”). Federal Power Act, 16 U.S.C. § 791a et seq. (1982). Congress allows an exemption from this licensing requirement for some small power projects to be built at the site of an existing dam. Phoenix Hydro Corporation (“Phoenix”), which proposed to build a small power project in Phoenix, New York, is appealing the Commission's rescission of its earlier acceptance of Phoenix’s application for an exemption. Phoenix also challenges the Commission’s withdrawal of the company’s application for a preliminary permit at the time that it accepted Phoenix’s application for an exemption. Phoenix argues that [356]*356this withdrawal deprived the company of the priority to which its preliminary permit application entitled it under the normal licensing procedure. For the reasons that follow, we uphold the Commission’s decision that Phoenix was not entitled to an exemption. This determination, however, ought not prejudice or predetermine the hydroelectric plant builder’s application for a preliminary permit. We therefore remand the case to the Commission to reinstate Phoenix’s application for a preliminary permit with the priority it would have had on its own, considered independently from Phoenix’s application for an exemption.

I. Background

The Oneida and Seneca Rivers flow together at Three Rivers, New York. The Oswego River flows north from the confluence of these two rivers. Two and a half miles north on the Oswego River, in Phoenix, New York, Phoenix Hydro Corporation proposed to construct a small hydroelectric power project at the southwest end of a dam in the river. The dam itself, located at the first of seven locks on the river between Three Rivers and Oswego, is owned by the New York State Department of Transportation (NYSDOT). Before Phoenix commenced construction, it duly filed an application for a preliminary permit with the Commission on September 2, 1981. On September 15, 1982, Phoenix also sought an exemption from licensing requirements under 16 U.S.C. § 823a and 42 U.S.C. § 7371, which allow exemptions from licensing for the construction and operation of small hydroelectric facilities in which the applicant owns all necessary water interests. On December 17, 1982, the Deputy Director of the Commission’s Office of Electric Power Regulation (“the Director”), acting under a delegation of authority from the Commission granted by 18 C.F.R. § 385.308, accepted Phoenix’s exemption application for filing. However, the Director rescinded this acceptance on June 16,1983, on the ground that Phoenix lacked the necessary property interests. Phoenix appealed the staff action, maintaining that the Commission had granted exemptions to two previous projects whose builders had property interests identical to those of Phoenix. The Commission denied Phoenix’s appeal, and described the Director’s earlier grants of exemptions to similar projects as erroneous precedents which it declined to follow. The Commission also found that Phoenix had submitted no documentary evidence of property rights, or of options to obtain such rights, in the project dam and impoundment. Phoenix then requested a rehearing, which the Commission denied on March 27, 1984.

The decision on Phoenix’s application for a preliminary permit followed closely behind, and its result was ordained by, the exemption process. The Commission notified Phoenix on January 6, 1983 that its application for a preliminary permit was deemed withdrawn as of December 17, 1982, the date the exemption application was accepted for filing. When the Commission rescinded this acceptance, Phoenix’s preliminary permit application was not reinstated. Nor was the application reinstated when the Commission denied Phoenix’s appeal of the exemption on October 21, 1983. Phoenix filed a timely petition for rehearing of its appeal on November 19, 1983. After the thirty-day statutory maximum for filing a petition for rehearing had elapsed, 16 U.S.C. § 8251, Phoenix on November 28, 1983 filed a supplement seeking a rehearing on the wholly separate issue of the withdrawal of the preliminary permit application, and arguing that the Commission should reinstate this application. The Commission granted rehearing on December 21, 1983 solely for the purpose of further consideration, but declined to consider Phoenix’s petition to reinstate its preliminary permit application. The Commission then finally denied rehearing on March 27, 1984. This appeal followed.

II. The Commission’s Denial of an Exemption to Phoenix

Petitioner first contends that the Commission improperly denied it an exemption. Phoenix's principal argument is that the [357]*357Commission had previously granted exemptions to two small hydroelectric facilities on the same stretch of the Seneca River. According to Phoenix, these exemptions, Niagara Mohawk Power Corp., 19 FERC 1162,372 (May 28, 1982) (“NiMo”), and Seneca Hydroelectric Company, Inc., 18 FERC 11 62,227 (Feb. 17, 1982) (“Seneca”), were granted to builders whose water and property interests were identical to those of Phoenix. Yet, Phoenix argues, the Commission ignored the precedential value of the NiMo and Seneca proceedings in denying Phoenix an exemption from licensing requirements.

Phoenix’s claim raises two related, although separate, questions. First, did the Commission abuse its discretion in interpreting its regulations in a way that denied Phoenix an exemption? Second, regardless of the Commission’s present interpretation of the applicable law and regulations, did the Commission’s issuance of two prior exemptions, which the Commission now regards as erroneous, bind the Commission to issue the exemption to Phoenix?

The Federal Water Power Act, 16 U.S.C. § 791a et seq. (1982), requires those who seek to construct a hydroelectric project to obtain a license from the Commission. 16 U.S.C. § 817. Certain small power projects, however, are allowed to bypass the licensing proceedings and obtain an exemption. Section 408 of The Energy Security Act of 1980, 16 U.S.C. § 2705(d), gives the Commission discretion to exempt projects at the site of “existing dams” which meet certain environmental requirements. In making these exemptions available, Congress intended to expedite the development of hydroelectric facilities and to shorten licensing procedures where possible. H.Conf.Rep. No. 96-1104, 96th Cong., 2d Sess. 276, reprinted in [1980] U.S.Code Cong. & Ad.News at 1743, 2171-72. To achieve this congressional purpose, the Commission has issued regulations which provide that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
775 F.2d 1187, 249 U.S. App. D.C. 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phoenix-hydro-corp-v-federal-energy-regulatory-commission-cadc-1985.