Mary Jane Ruderman Hirschey v. Federal Energy Regulatory Commission, Long Lake Energy Corporation, Intervenor

701 F.2d 215, 226 U.S. App. D.C. 204, 1983 U.S. App. LEXIS 30184, 1983 WL 813512
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 25, 1983
Docket82-2170
StatusPublished
Cited by14 cases

This text of 701 F.2d 215 (Mary Jane Ruderman Hirschey v. Federal Energy Regulatory Commission, Long Lake Energy Corporation, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mary Jane Ruderman Hirschey v. Federal Energy Regulatory Commission, Long Lake Energy Corporation, Intervenor, 701 F.2d 215, 226 U.S. App. D.C. 204, 1983 U.S. App. LEXIS 30184, 1983 WL 813512 (D.C. Cir. 1983).

Opinion

Opinion for the Court filed by EDWARDS, Circuit Judge.

HARRY T. EDWARDS, Circuit Judge:

Petitioner Mary Jane Ruderman Hirschey seeks review of a Federal Energy Regulatory Commission (“FERC” or “Commission”) order vacating her exemption from the licensing requirements of the Federal Power Act, 16 U.S.C. §§ 791a to 825r (1976 & Supp. V 1981) (“FPA” or “Act”). Because, on the facts of this case, the FERC had no authority to vacate petitioner’s exemption, we reverse.

I.

A.

Under part I of the FPA it is “unlawful for any person, ... for .the purpose of developing electric power, to construct, operate, or maintain any dam, water conduit, reservoir, power house, or other works incidental thereto across, along, or in any of the navigable waters of the United States, ... except under and in accordance with the terms of . .. a license granted pursuant to [the Act].” 16 U.S.C. § 817 (1976). Congress has authorized the FERC to exempt certain small hydroelectric projects from the licensing requirements imposed by this provision. Under section 405(d) of the Public Utilities Regulatory Policies Act of 1978, “[t]he Commission may in its discretion (by rule or order) grant an exemption in whole or in part from the requirements (including the licensing requirements) of part I of . . . the [FPA] to small hydroelectric power projects having a proposed installed capacity of 5,000 kilowatts or less .... ” 16 U.S.C. § 2705(d) (Supp. V 1981) (“PURPA”).

Pursuant to the PURPA, the FERC has adopted regulations setting forth procedures governing exemption applications. Applications are first reviewed by the FERC for compliance with filing requirements. See 18 C.F.R. §§ 4.105(b), 4.31(c)-(g) (1982). When the FERC determines that an application is complete, the applicant is notified that it has been accepted for filing. See id. § 4.31(c)(1). The Commission then issues public notice of the filing and invites protests, petitions to intervene, or competitive proposals. See id. § 4.31(c)(2). An application is deemed approved and granted 120 days after its acceptance for filing if within that period the Commission takes no action affirmatively to grant the exemption in whole or in part, deny the exemption, or suspend operation of the 120-day rule. 1 Once an application *217 for an exemption has been granted, the decision is final subject only to rehearing procedures. See id. § 1.30(d) (1982). Any party may petition for rehearing within 30 days after an application has been granted, see id. § 1.34 (1982); however, if a petition for rehearing is not filed within 30 days, the exemption grant becomes nonreviewable. 2

B.

Petitioner is one of several developers seeking to build hydroelectric power plants along a stretch of the Black River in New York State. Petitioner and three other developers have proposed to construct small projects that would involve renovation of existing hydroelectric sites. The remaining developer, Long Lake Energy Corporation (“Long Lake”), 3 has proposed to build a large project that would involve the use of a dam upstream from the other proposed sites. While the small projects could all be operated compatibly with one another, operation of the Long Lake project would lower the river’s water level downstream and thus foreclose simultaneous operation of the small projects.

Petitioner filed an application for a licensing exemption on December 16, 1981. The FERC accepted the application on February 5, 1982, notifying petitioner that, under the automatic grant rule, her application would be deemed granted if no action were taken on it within 120 days. Thereafter, the FERC took no action to grant or deny the application or to suspend operation of the 120-day rule. Petitioner’s application was thus automatically granted on June 7, 1982, and as of that date a petition for rehearing could have been filed. Although Long Lake had a competitive application on file with the FERC, neither Long Lake nor any other party filed a petition for rehearing to contest the automatic grant of petitioner’s application. Since no petition for rehearing was filed, petitioner’s exemption became nonreviewable on July 7, 1982. 4

On July 20, 1982, the FERC, sua sponte, issued an order vacating petitioner’s exemption. The FERC asserted that it had inadvertently failed to suspend operation of the 120-day rule on petitioner’s application; the FERC claimed, further, that because several competing applications for authority to construct hydroelectric projects along the same stretch of the Black River had been filed, a comparative evaluation of all of the applications would have to be undertaken. The Commission thus justified vacating petitioner’s exemption as necessary to return matters to the status quo ante so that a comparative evaluation could be achieved.

This petition for review followed.

II.

The FERC argues that there are two statutory bases supporting its vacation of petitioner’s exemption. First, the Commission relies on section 313(a) of the FPA, which grants the FERC the power to modify or set aside any finding or order at any time until the administrative record is filed in a court of appeals. 5 But in Pan Ameri *218 can Petroleum Corp. v. FPC, 322 F.2d 999 (D.C.Cir.), cert. denied, 375 U.S. 941, 84 5. Ct. 346, 11 L.Ed.2d 272 (1963), this court made it clear that, under section 313(a), the Commission only has the “power to correct an order ... until such time as the record on appeal has been filed with a court of appeals or the time for filing a petition for judicial review has expired.” Id. at 1004 (emphasis added). The time for judicial review in this case expired on July 7, the final date for filing a petition for rehearing. Thus, section 313(a) provides no authority for the FERC’s action in this case.

Second, the FERC cites section 309 of the FPA, which grants the Commission “power to perform any and all acts, and to prescribe, issue, make, amend, and rescind such orders, rules, and regulations as it may find necessary or appropriate to carry out the provisions of [the Act].” But it is plain that section 309 has no application under the circumstances of this case. The general authority of section 309 does not empower the FERC to vacate final and nonreviewa-ble license exemptions. To imply such authority from section 309 would make a sham of the carefully crafted license exemption regulations and render superfluous the specific revocation procedures set forth in 18 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Natural Resources Defense Council, Inc. v. Thomas
838 F.2d 1224 (D.C. Circuit, 1988)
Badger-Powhatan, a Div. of Figgie Intern. v. United States
633 F. Supp. 1364 (Court of International Trade, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
701 F.2d 215, 226 U.S. App. D.C. 204, 1983 U.S. App. LEXIS 30184, 1983 WL 813512, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mary-jane-ruderman-hirschey-v-federal-energy-regulatory-commission-long-cadc-1983.