Charles N. White Construction Co. v. Department of Labor

476 F. Supp. 862, 26 Cont. Cas. Fed. 83,883, 1979 U.S. Dist. LEXIS 10072
CourtDistrict Court, N.D. Mississippi
DecidedAugust 31, 1979
DocketWC 79-108-K
StatusPublished
Cited by5 cases

This text of 476 F. Supp. 862 (Charles N. White Construction Co. v. Department of Labor) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles N. White Construction Co. v. Department of Labor, 476 F. Supp. 862, 26 Cont. Cas. Fed. 83,883, 1979 U.S. Dist. LEXIS 10072 (N.D. Miss. 1979).

Opinion

MEMORANDUM OPINION

KEADY, Chief Judge.

In this action Charles N. White Construction Co., Inc. (White), plaintiff, sues the Department of Labor, an agency of the United States of America (DOL), defendant, seeking injunctive relief from DOL continuing with a construction contract on a project known as the Batesville Job Corps Center, No. IFB-ONP-79-29-JC, at Bates-ville, Mississippi, until a ruling is made on its bid protest filed with the Comptroller General within the General Accounting Office (GAO), an agency of the United States. Jurisdiction is invoked pursuant to 28 U.S.C. § 1331 (federal question) for cause of action arising under the Administrative Procedure Act, 5 U.S.C. § 551 et seq. 1 White alleged that on or about June 1,1979, DOL issued an invitation for bids on the project and that it, White, prepared and filed with DOL a bid to perform all work required for the project for a total contract price of $2,934,900.00, with no qualifications; that on July 17 White’s bid and the bids of other contractors were received and opened by DOL. Plaintiff alleged that at the bid opening the apparent low bidder was JESCO, the second low bidder was White and the third low bidder was T. H. Taylor, Jr., Inc. (Taylor); that the bid of JESCO was determined to be inappropriate and hence rejected by DOL because it did not qualify as a small business contractor; that on August 1 DOL rejected White’s bid as being nonresponsive on the ground that White had failed to acknowledge on the bid form that it had received various addenda which had been issued after the invitation for bids was submitted; that DOL, on the same date it received White’s bid, awarded the project to Taylor; that thereafter White filed a bid protest with GAO that DOL awarded the contract to Taylor without giving White an opportunity to have its protest determined by GAO. On August 15 White applied for a temporary restraining order. At that time the court determined that Taylor should be notified and made a party defendant to the action, and also because of the complexity of the case, the cause should be set on August 27 for a hearing on the preliminary injunction.

Taylor moved to intervene as a defendant, which was allowed by the court, and filed an answer denying that White was *864 entitled to injunctive relief. 2 DOL orally adopted the answer of Taylor, intervenordefendant, and took the position that the contract had been lawfully awarded to Taylor and White’s bid was properly rejected. It was agreed by counsel for all parties that pursuant to Rule 65(a)(2), F.R.Civ.P., hearing on the merits of the cause would be consolidated with the application for preliminary injunction, and the court could dispose of the matter as if it were on final hearing. Both sides presented oral and documentary evidence and memorandum briefs, as well as oral arguments, so that the matter is now ripe for decision on the merits. The court incorporates herein its findings of fact and conclusions of law as required by Rule 52, F.R.Civ.P.

1. Findings of Fact.

On June 1, 1979, DOL issued invitation for bids on Project No. IFB-ONP-79-29JC, through its architect/engineer for the project, Cooke-Douglas-Farr, Ltd. (CDF), of Jackson, Mississippi. The invitation requested bids for the construction of the Batesville Job Corps Center. Bids were to be opened at 2:00 p.m. on July 17 in Jackson.

Subsequent to the original invitation to bid, CDF issued five addenda, or modifications of the original solicitation. CDF prepared and issued all five addenda. Although DOL has authority in solicitations such as this one to revoke or modify addenda issued by project architect/engineers, CDF has authority to issue addenda on its own and has often done so without objection or prior clearance from DOL. However, it has no authority to award a contract. Only DOL, acting through its contracting officer, has such authority.

The first two of the five addenda, A and B, were attached to and mailed out with the original solicitation. Addendum C, the third addendum, was issued on June 28. It included a new form to be used in bidding. The final two Addenda, D and E, were issued respectively on July 9 and July 13. Addendum D called for modifications that would add $4,638.00 to a bid. Addendum E called for modifications that would add $10,266.00.

July 13, the issuance date of Addendum E, was a Friday. The date bids were due was July 17, which was the following Tuesday. On Monday, July 16, Nelson Douglas of CDF, cognizant of the uncertain delivery date of items entrusted to the United States Postal Service, decided to contact all bidders on the Batesville project to ascertain that they were aware of all addenda, including Addendum E, which had been mailed three days before, i.e., the Friday before the weekend. Douglas instructed his secretary, Shirley Smith, to call all the general construction bidders to ensure their knowledge of the addenda, especially of Addendum E. Ms. Smith did so; Charles White says he was so contacted and informed at 1:50 p.m. on July 16. Ms. Smith, however, did not testify. At that time Ms. Smith, according to Charles White, asked him whether White knew of and had received all addenda; Charles White testified that he answered Ms. Smith in the affirmative.

The bid form on which bids for the Bates-ville project were to be received contains spaces in which various information must be inserted. Among the information, of course, is the important item of the bid price for the contract. Standard operating procedure in the construction business, according to the evidence, is to complete bid forms only a few minutes before bids are to be opened. Pursuant to this practice, White sent its employee, Gail McGowan, to Jackson, where the bids were to be submitted to CDF and opened at its office. Ms. McGowan was to await a phone call from Charles White, plaintiff’s president, by which she would be informed of the amount of White’s bid. Approximately ten minutes before 2:00 p.m. on July 17, Charles White telephoned Ms. McGowan, his em *865 ployee, that the amount of the White bid would be $2,934,900.00. Ms. McGowan filled in this amount on the bid form, and submitted the bid before the 2:00 p.m. deadline. The correct bid form, Addendum C, was utilized by White.

Another space on the bid form was for the purpose of noting all the addenda that the contractor had received. The contractor was required to fill in the number and date of each addendum so received by it. If this information was not included, the bid would be deemed by DOL to be nonresponsive and would not be considered for the project. Though fuzzy, the printing on the bid form indicating the space for addenda acknowledgement is legible. Charles White, however, was well aware of the requirement for noting all addenda received on the bid form and of the sanction for failing to do so. Through clerical oversight on White’s part, none of the Addenda A-E was acknowledged in writing on the bid form.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sebena Paving, Inc. v. Gallatin Airport Authority
801 P.2d 614 (Montana Supreme Court, 1990)
State v. NM Dept. of Fin. & Admin.
704 P.2d 79 (New Mexico Court of Appeals, 1985)
Mil-Tech Systems, Inc. v. United States
32 Cont. Cas. Fed. 72,719 (Court of Claims, 1984)
Martel Construction, Inc. v. Montana State Board of Examiners
668 P.2d 222 (Montana Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
476 F. Supp. 862, 26 Cont. Cas. Fed. 83,883, 1979 U.S. Dist. LEXIS 10072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-n-white-construction-co-v-department-of-labor-msnd-1979.