Chard Realty, Inc. v. City of Shakopee

392 N.W.2d 716, 1986 Minn. App. LEXIS 4722
CourtCourt of Appeals of Minnesota
DecidedSeptember 2, 1986
DocketC7-85-2282
StatusPublished
Cited by12 cases

This text of 392 N.W.2d 716 (Chard Realty, Inc. v. City of Shakopee) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chard Realty, Inc. v. City of Shakopee, 392 N.W.2d 716, 1986 Minn. App. LEXIS 4722 (Mich. Ct. App. 1986).

Opinion

OPINION

LANSING, Judge.

Chard Realty, Inc., a developer, appeals the trial court’s grant of summary judgment to the defendants in this suit alleging negligence, breach of contract, and overas-sessment of municipal property taxes. We affirm.

FACTS

Chard Realty owned 47 lots located in the East View First Addition in Shakopee. In August 1979 the City of Shakopee adopted a resolution granting preliminary *718 approval of Chard Realty’s proposed development of a subdivision there. On October 31, 1979, Chard and the city entered a developer’s agreement for the purpose of financing construction of streets, water, sewer, and other public improvements. The developer agreed to pay for all improvements; however, Chard was responsible for constructing Plan A improvements, which consisted only of grading, and the city was responsible for constructing Plan B improvements, which consisted of roadways, sanitary and storm sewers, and watermains. The agreement contained a provision incorporating by reference all contracts let under the developer’s agreement. 1

The Plan B improvements were to be financed through the sale of improvement bonds, the cost of which was to be recouped as special assessments levied against each lot at an 8 percent interest rate. See Minn.Stat. § 429.091 (1984).

In June 1980 the city contracted with Richard Knutson, Inc., to construct the Division I improvements — sewers and water-mains. Division II improvements — street grading — were to be done by a different contractor. The contract required Knutson to complete work within 60 days of being given written notice to proceed and assessed liquidated damages of $100 per day for each day of delay beyond the 60-day deadline. Knutson was given notice to proceed on June 1 and, because of problems in installing the watermains, was approximately 90 days late in completing its work.

In the meantime, on July 12, 1980, the city adopted a resolution declaring that the estimated cost of Plan B improvements would be $301,580.16. The city mailed notice of a public hearing, to take place August 19, to William Chard. Chard did not object at the special assessment hearing. After the hearing the city council adopted a resolution declaring the amount of the special assessment as $295,297.24. On August 26 the city mailed a notice of assessment to Chard reflecting that figure and an 8.75 percent interest rate.

Chard did not appeal the assessment. Instead, he wrote to the city on September 16 requesting reassessment of six lots, on the basis that pre-existing assessments made the additional assessments excessive. The city council subsequently amended the assessment roll, reducing the assessment on those six lots and increasing the assessment on the other 41 lots. The total amended assessment is $294,838.86. Chard did not appeal it.

In September 1982 Chard commenced this action. He alleged the city negligently inspected/supervised the installation of the water mains and breached both the developer’s agreement and the contract between the city and Knutson; that Knutson negligently failed to perform his contract; that Knutson breached its contract with the city by failing to complete work in the time required; that Knutson negligently left rocks on Chard’s property and moved property line markers; that the city demanded excess interest on the assessments and wrongfully kept the interest on bond proceeds; and that the American Insurance Co., as surety for Knutson, owes damages to Chard.

The defendants made various cross-claims and counterclaims on these allegations and then moved for summary judgment. At the hearing on the motion in July 1984, the parties agreed to dismiss the claim against Busse Construction, Inc. On August 27-28, 1984, the trial court granted summary judgment in favor of the remaining defendants on all allegations except Knutson’s negligently leaving rocks on the property and moving property line markers. Those claims were settled in Novem *719 ber 1985 for $1,200. Chard appeals from the judgment subsequently entered. 2

ISSUES

1. Did Chard waive his objections to the special assessment by failing to object in accordance with Minn.Stat. § 429.081?

2. Is Chard entitled to the liquidated damages provided in the contract between the city and Knutson?

ANALYSIS

I

The trial court ruled that Chard waived his objections to the special assessment by failing to object in accordance with the procedure set out in Minn.Stat. § 429.081.

The resolution of assessment disputes is controlled by statute. No appeal may be taken as to the amount of any assessment unless a written objection signed by the affected property owner is filed with the municipal clerk prior to the assessment hearing or presented to the presiding officer at the hearing. Minn.Stat. § 429.061, subd. 1. All objections to the assessments not received at the assessment hearing are waived, unless the failure to object at the hearing is due to a reasonable cause. Id., subd. 2. “All objections to the assessment shall be deemed waived” unless presented on appeal to the district court, which provides “the exclusive method of appeal from a special assessment levied pursuant to this chapter.” § 429.081.

Chard not only failed to raise his objections at the hearing, 3 he failed to appeal to the district court. Chard argues he had reasonable grounds for failing to object because he contacted the city administrator twice before the public hearing and was assured that the assessment was not final but would be adjusted to reflect the actual cost of the improvements. He also alleges that on several occasions after the August hearing, the mayor, a member of the city council, and the city administrator assured him the final assessment would not be made until the actual costs were known.

In Sievert v. City of Lakefield, 319 N.W.2d 43 (Minn.1982), the developer did not object to the special assessment before the city council or seek review by the district court. Instead, he brought suit two years later for breach of contract to supply improvements. The supreme court reversed a jury verdict for the developer, holding the statutory procedure is the exclusive method of appealing a special assessment, and the developer had waived his right to attack it. Id. at 44. Chard received notice of the hearing and assessment and must be deemed to have waived his objections.

Even assuming Chard’s objections were not waived under the statute, there is no evidence to show that the actual costs were different from the amount assessed, even when the liquidated damages are offset. The city presented evidence that the actual cost of the Plan B improvements was $306,-000, or $12,000 more than the amount assessed. There is no evidence in the record contradicting the city’s actual cost figure.

II

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DRB 24, LLC v. City of Minneapolis
976 F. Supp. 2d 1079 (D. Minnesota, 2013)
Dayton Development Co. v. Gilman Financial Services, Inc.
299 F. Supp. 2d 933 (D. Minnesota, 2003)
PACEMAKER PLASTICS CO., INC. v. AFM Corp.
163 F. Supp. 2d 795 (N.D. Ohio, 2001)
614 Co. v. Minneapolis Community Development Agency
547 N.W.2d 400 (Court of Appeals of Minnesota, 1996)
Norwest Financial Leasing, Inc. v. Morgan Whitney, Inc.
787 F. Supp. 895 (D. Minnesota, 1992)
People v. Burton
445 N.W.2d 133 (Michigan Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
392 N.W.2d 716, 1986 Minn. App. LEXIS 4722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chard-realty-inc-v-city-of-shakopee-minnctapp-1986.