Chamberlin v. Puckett Construction

921 P.2d 1237, 277 Mont. 198, 53 State Rptr. 593, 1996 Mont. LEXIS 125
CourtMontana Supreme Court
DecidedJuly 1, 1996
Docket95-470
StatusPublished
Cited by24 cases

This text of 921 P.2d 1237 (Chamberlin v. Puckett Construction) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chamberlin v. Puckett Construction, 921 P.2d 1237, 277 Mont. 198, 53 State Rptr. 593, 1996 Mont. LEXIS 125 (Mo. 1996).

Opinion

JUSTICE GRAY

delivered the Opinion of the Court.

Randall R. Chamberlin, d/b/a Custom Framing (Custom Framing), appeals from the Findings of Fact, Conclusions of Law and Judgment of the Eighteenth Judicial District Court, Gallatin County, concluding that Custom Framing committed an anticipatory breach of the subcontractor agreement between Custom Framing and Puckett Construction and from the court’s subsequent order awarding Puckett Construction attorney's fees and costs. We affirm and remand for determination and award of Puckett Construction’s attorney’s fees and costs on appeal.

We address the following issues:

*201 1. Did the District Court err in concluding that Custom Framing committed an anticipatory breach of the subcontractor agreement?

2. Did the District Court abuse its discretion with regard to the amount of attorney’s fees and costs awarded to Puckett Construction?

3. Is Puckett Construction entitled to attorney’s fees and costs on appeal?

Factual Background

In January of 1994, Puckett Construction executed a contract with LT Hotel Enterprises under which Puckett Construction would be the general contractor for construction of a Ramada Inn in Bozeman, Montana. Thereafter, Puckett Construction received a written bid from Custom Framing to perform the framing work associated with the project. Phil Puckett (Puckett), the owner of Puckett Construction, drafted and signed a subcontractor agreement for the framing, which is dated March 24, 1994, and forwarded it to Randall Chamberlin (Chamberlin), one of the partners and owners of Custom Framing. Chamberlin and his partner, David Worthington (Worthington), made ten changes to the agreement and Chamberlin initialed each change.

Chamberlin signed the revised subcontractor agreement and returned it to Kenneth Cavenah (Cavenah), Puckett Construction’s superintendent and sole on-site representative for the Ramada Inn project. In early April, Cavenah took the revised agreement to South Dakota and reviewed it with Puckett; thereafter, he returned to Bozeman and, on April 14,1994, initialed the changes in the presence of Chamberlin and Worthington.

Inclement weather had delayed the Ramada Inn project several times and Custom Framing was scheduled to begin work on April 25, 1994. Ten days prior to that start date, Chamberlin called Puckett Construction’s office in South Dakota and informed the receptionist that Custom Framing would not begin work until Puckett personally initialed the changes Chamberlin had made to the subcontractor agreement. Puckett Construction subsequently sent Custom Framing a letter advising that “Puckett Construction will not be hiring Custom Framing on the Ramada Inn job.” Puckett Construction hired a different framing subcontractor on April 18,1994.

Procedural History

In June of 1994, Chamberlin, individually and d/b/a Custom Framing, sued Puckett Construction for breach of contract and requested *202 an unspecified amount of damages. Puckett Construction answered and denied the existence of a contract. Both parties conducted discovery.

In April of 1995, Puckett Construction moved for summary judgment on the basis that no contract existed. Custom Framing opposed the motion, arguing that “when the contract was signed and initialed by [Cavenah] that there was indeed a binding agreement.” The District Court denied Puckett Construction’s motion, concluding that a contract was formed when Cavenah, Puckett Construction’s agent, signed and initialed the revised agreement; the court also determined that a factual issue existed as to which party breached that contract. The pretrial order subsequently was amended to include a counterclaim by Puckett Construction alleging that Custom Framing’s “refusal to begin work on the project... constituted a material and total breach of the contract... [and] [Puckett Construction] was entitled to ... terminate the contract.”

A bench trial was held in June of 1995. The District Court directed a verdict on behalf of Puckett Construction on Custom Framing’s breach of contract claim, awarded Puckett Construction damages in the amount of $11,405 on its counterclaim, and determined that Puckett Construction was entitled to reasonable attorney’s fees and costs. Thereafter, the District Court held a hearing on attorney's fees and costs and awarded Puckett Construction $9,600 in attorney’s fees and $1,990.65 for costs. Custom Framing appeals.

Discussion

1. Did the District Court err in concluding that Custom Framing committed an anticipatory breach of the subcontractor agreement?

An anticipatory breach of a contract is a repudiation of the promisor’s contractual duty before the time fixed for performance has arrived. STC, Inc. v. City of Billings (1975), 168 Mont. 364, 370, 543 P.2d 374, 377 (citations omitted). A repudiation must be entire, absolute and unequivocal to support an action for anticipatory breach. STC, 543 P.2d at 379. An expression of intent not to perform, standing alone, is not enough. STC, 543 P.2d at 379. An anticipatory breach by one party excuses further performance by the other. See STC, 543 P.2d at 378.

The District Court concluded that Chamberlin’s statement during the telephone call to Puckett Construction on April 15,1994, that Custom Framing would not begin work until Puckett personally initialed the changes Chamberlin made to the subcontractor agreement, constituted an anticipatory breach of the agreement. We review *203 a district court’s conclusions of law to determine whether the court’s interpretation of the law is correct. Loney v. Milodragovich, Dale & Dye, P.C. (1995), 273 Mont. 506, 510, 905 P.2d 158, 161 (citing Boreen v. Christensen (1994), 267 Mont. 405, 408, 884 P.2d 761, 762).

We have not previously addressed whether a party’s demand for performance of terms not contained in a contract, accompanied by a statement that it will not perform if those terms are not met, constitutes an anticipatory breach. Other courts, however, have held that such a demand constitutes an anticipatory repudiation. See, e.g., P & L Contractors, Inc. v. American Norit Co. (5th Cir. 1993), 5 F.3d 133, 139; United California Bank v. Prudential Ins. Co. (Ariz. Ct. App. 1983), 681 P.2d 390, 430; Twenty-Four Collection, Inc. v. M. Weinbaum Constr. (Fla. Ct. App. 1983), 427 So. 2d 1110, 1111.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Parenting of A.P.V.W.
2022 MT 159N (Montana Supreme Court, 2022)
Bridger Del Sol, Inc. v. VincentView, LLC
2017 MT 293 (Montana Supreme Court, 2017)
Marriage of Cadena v. Fries
2015 MT 90 (Montana Supreme Court, 2015)
Boyne USA, Inc. v. Spanish Peaks Development, LLC
2013 MT 1 (Montana Supreme Court, 2013)
Parkwood Associates Ltd. Partnership v. United States
97 Fed. Cl. 809 (Federal Claims, 2011)
Boyne USA, Inc. v. Lone Moose Meadows, LLC
2010 MT 133 (Montana Supreme Court, 2010)
Zier v. Lewis
2009 MT 266 (Montana Supreme Court, 2009)
Lorang v. Fortis Insurance
2008 MT 252 (Montana Supreme Court, 2008)
Havre Daily News, LLC v. City of Havre
2006 MT 215 (Montana Supreme Court, 2006)
Chase v. Bearpaw Ranch Ass'n
2006 MT 67 (Montana Supreme Court, 2006)
Ray v. Nansel
2002 MT 191 (Montana Supreme Court, 2002)
Pankratz v. Teske
2002 MT 112 (Montana Supreme Court, 2002)
Henderson v. Estate of Henderson
2002 MT 56N (Montana Supreme Court, 2002)
Marshall v. Anderson Consulting
2002 MT 19N (Montana Supreme Court, 2002)
Eschenbacher v. Anderson
2001 MT 206 (Montana Supreme Court, 2001)
Transaction Network, Inc. v. Wellington Technologies, Inc.
2000 MT 223 (Montana Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
921 P.2d 1237, 277 Mont. 198, 53 State Rptr. 593, 1996 Mont. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chamberlin-v-puckett-construction-mont-1996.