CGI Federal Inc. v. FCi Federal, Inc.

CourtSupreme Court of Virginia
DecidedJune 7, 2018
Docket170617
StatusPublished

This text of CGI Federal Inc. v. FCi Federal, Inc. (CGI Federal Inc. v. FCi Federal, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CGI Federal Inc. v. FCi Federal, Inc., (Va. 2018).

Opinion

PRESENT: All the Justices

CGI FEDERAL INC. OPINION BY v. Record No. 170617 JUSTICE ELIZABETH A. McCLANAHAN June 7, 2018 FCi FEDERAL, INC.

FROM THE CIRCUIT COURT OF FAIRFAX COUNTY Michael F. Devine, Judge

This appeal involves claims for fraudulent inducement, breach of contract, and unjust

enrichment related to a teaming agreement entered between FCi Federal, Inc. (“FCi”) and CGI

Federal Inc. (“CGI”) to obtain a federal government contract. The jury awarded CGI

approximately $12 million in damages for the fraudulent inducement and breach of contract

claims. After determining that the teaming agreement did not obligate FCi to extend a

subcontract to CGI and that CGI did not prove fraud damages, the circuit court set aside the

jury’s verdict. The circuit court then granted FCi’s motion for summary judgment on CGI’s

alternative claim for unjust enrichment. On appeal, CGI contends the circuit court erred in

setting aside the verdict and entering summary judgment for FCi on the unjust enrichment claim.

Concluding there is no reversible error in the judgment of the circuit court, we affirm.

I. Facts & Proceedings

When a circuit court grants a motion to set aside a verdict, we grant the party for whom

the jury found the “benefit of all reasonable inferences that may be drawn from the evidence and

of all substantial conflicts in the evidence.” Stover v. Norfolk & Western Ry. Co., 249 Va. 192,

194, 455 S.E.2d 238, 239-40 (1995). We recite the facts in accord with these principles. A. The Original Teaming Agreement

In 2012, the United States Department of State solicited bids for a visa processing

contract (“visa contract” or “prime contract”). CGI, as a large contractor, was ineligible to bid

because the State Department reserved the visa contract for small businesses. Although FCi, as a

smaller contractor, was eligible to bid for the visa contract, it did not have the capabilities to

perform the work alone. Unable to compete for the visa contract individually, FCi and CGI

agreed to cooperate in submitting a proposal for the visa contract. To that end, the parties

entered a teaming agreement on September 19, 2012 to prepare a proposal for the visa contract.

The teaming agreement set forth FCi’s and CGI’s rights and obligations in preparing the

proposal.

Under the teaming agreement, FCi was required to submit a proposal as the prime

contractor and include CGI as a subcontractor. By entering the teaming agreement with FCi,

CGI was prohibited from assisting any other parties competing for the visa contract. CGI

committed to furnish “personnel, information, and materials as necessary” and “to assist FCi . . .

in developing and preparing sections of the prime proposal.” CGI also promised to provide

“cooperation as may reasonably be deemed necessary or desirable by FCi . . . to ensure the

success of the” visa contract proposal. Under Section 2.0 of the teaming agreement, FCi

“retain[ed] express and exclusive control over all prime proposal activities . . . as well as

negotiation of any resulting prime contract.”

From the outset, CGI determined it wanted at least 40% of the work available under the

visa contract (“workshare”) or its participation in the teaming agreement would not be

worthwhile. Accordingly, the parties negotiated a “Statement of Work,” labeled as Exhibit A of

the teaming agreement, which provided, “Subject to the final solicitation requirements, [CGI]

2 will receive forty-five percent (45%) work share of the total contract value . . . but the work

share commitment may not be exactly 45% each year.”

If the proposal resulted in a contract award to FCi, the teaming agreement provided a

framework for the parties to negotiate a subcontract. For example, Section 3.1 of the teaming

agreement required the parties to “enter good faith negotiations for a subcontract . . . subject to

applicable laws, regulations, terms of the prime contract and . . . [CGI’s] best and final proposal

to FCi.” Section 3.2 of that agreement, in turn, reiterated the “contemplated subcontract” was

subject to numerous conditions including: (1) an award of the prime contract to FCi; (2) the

government’s approval of CGI as a subcontractor; (3) inclusion in the prime contract of CGI’s

statement of work and; (4) “[m]utual agreement of the parties . . . to the statement of work,

financial terms, and reasonable subcontract provisions.”

Continuing, Section 5.1(8) provided that the teaming agreement would expire 90 days

after an award of the visa contract to FCi, if the parties could not agree on the terms and

conditions of a subcontract. In Section 2.7, the parties acknowledged they would bear their “own

respective costs, expenses, risks and liabilities arising out of performance” of the teaming

agreement. Section 8.3 stated there was no basis “for the sharing of the profits or losses arising

out of the efforts of either or both of the parties,” and section 9.0 precluded the recovery of lost

profits for a breach of the agreement.

B. The Amended Teaming Agreement

After three months of work with CGI, on December 6, 2012, FCi submitted a proposal to

the State Department. FCi, however, did not provide CGI a copy of the proposal and, at the time

of submission, FCi did not inform CGI the proposal allocated a 38% workshare to CGI. On

March 8, 2013, the State Department notified FCi the proposal was competitive, but directed FCi

3 to address certain deficiencies and submit a revised proposal by April 18, 2013. Based on the

State Department’s response, FCi informed CGI its workshare would have to be reduced in a

revised proposal because the government required additional work to be provided to other

subcontractors. Accordingly, CGI’s workshare as a subcontractor could not exceed 41% because

FCi, as the prime contractor, was required to have 51% workshare for the prime contract.

CGI agreed to accept a 41% workshare for its continued participation in the revised

proposal. To offset this workshare reduction, CGI requested that FCi allocate ten management

positions for CGI employees working on the visa contract. FCi recognized that CGI’s continued

involvement was critical for the success of the proposal. In responding to CGI’s request, on

April 17, 2013, FCi’s President, Scott Miller, emailed CGI’s Senior Vice-President, Toni

Townes-Whitley, assuring her “that our revised teaming agreement with CGI affirms our

commitment to CGI providing 10 management/supervisory positions . . . . In addition, the

agreement will reflect CGI’s 41% total contract value work share.” Based on these

representations, CGI continued to cooperate with the revised proposal and executed an amended

teaming agreement, with an April 17, 2013 effective date. Except for the provision concerning

CGI’s 41% workshare and the ten management positions designated for CGI, if FCi were

awarded the prime contract (“post-award provisions”), the amended teaming agreement did not

alter the parties’ original teaming agreement.

One day after Miller’s email to Townes-Whitley, FCi submitted a revised proposal to the

State Department. Contrary to Miller’s representations in his email to Townes-Whitley, the

revised proposal allocated only a 35% workshare to CGI and reserved all management positions

for FCi.

4 C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sunrise Continuing Care, LLC v. Wright
671 S.E.2d 132 (Supreme Court of Virginia, 2009)
Miller-Jenkins v. Miller-Jenkins
661 S.E.2d 822 (Supreme Court of Virginia, 2008)
W.J. Schafer Associates, Inc. v. Cordant, Inc.
493 S.E.2d 512 (Supreme Court of Virginia, 1997)
Stover v. Norfolk & Western Railway Co.
455 S.E.2d 238 (Supreme Court of Virginia, 1995)
Horner v. Ahern
153 S.E.2d 216 (Supreme Court of Virginia, 1967)
Murray v. Hadid
385 S.E.2d 898 (Supreme Court of Virginia, 1989)
McLeskey v. Ocean Park Investors, Ltd.
405 S.E.2d 846 (Supreme Court of Virginia, 1991)
Pierce v. Plogger
286 S.E.2d 207 (Supreme Court of Virginia, 1982)
Hop-In Food Stores, Inc. v. Serv-N-Save, Inc.
440 S.E.2d 606 (Supreme Court of Virginia, 1994)
Packard Norfolk, Inc. v. Miller
95 S.E.2d 207 (Supreme Court of Virginia, 1956)
Goldstein v. Miles
859 A.2d 313 (Court of Special Appeals of Maryland, 2004)
William H. Gordon Assocs., Inc. v. Heritage Fellowship
784 S.E.2d 265 (Supreme Court of Virginia, 2016)
Navar, Inc. v. Federal Business Council
784 S.E.2d 296 (Supreme Court of Virginia, 2016)
Holston Salt & Plaster Co. v. Campbell
16 S.E. 274 (Supreme Court of Virginia, 1892)
Wilson v. Hundley
30 S.E. 492 (Supreme Court of Virginia, 1898)
Rinehart v. Pirkey
101 S.E. 353 (Supreme Court of Virginia, 1919)
Ewig v. Dutrow
104 S.E. 791 (Supreme Court of Virginia, 1920)
C. G. Blake Co. v. W. R. Smith & Son, Ltd.
133 S.E. 685 (Court of Appeals of Virginia, 1926)
Southern Biscuit Co. v. Lloyd
6 S.E.2d 601 (Supreme Court of Virginia, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
CGI Federal Inc. v. FCi Federal, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cgi-federal-inc-v-fci-federal-inc-va-2018.