Certified Fire Protection, Inc. v. Precision Construction, Inc.

283 P.3d 250, 128 Nev. 371
CourtNevada Supreme Court
DecidedAugust 9, 2012
DocketNo. 54603; No. 55514
StatusPublished
Cited by157 cases

This text of 283 P.3d 250 (Certified Fire Protection, Inc. v. Precision Construction, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Certified Fire Protection, Inc. v. Precision Construction, Inc., 283 P.3d 250, 128 Nev. 371 (Neb. 2012).

Opinion

OPINION

By the Court,

Pickering, J.:

To recover in quantum meruit, a party must establish legal liability on either an implied-in-fact contract or unjust enrichment basis. Because we agree with the district court that appellant/cross-respondent Certified Fire Protection, Inc. did not provide sufficient [375]*375evidence to establish either an implied-in-fact contract or unjust enrichment, we affirm. Additionally, we affirm on cross-appeal the district court’s order denying attorney fees.

I.

Respondent/cross-appellant Precision Construction, Inc., a general contractor pursuing a contract for a warehouse construction project in 2005, solicited bids from subcontractors for the design and installation of an early suppression, fast response sprinkler system.1 Certified picked up a set of plans detailing the sprinkler system’s requirements and, in mid-November, submitted a bid of $480,000. Precision notified Certified that it had won the bid, and Precision entered into a contract with the owner to complete the project.

On December 5, Certified obtained a copy of the subcontract along with a set of construction plans and sprinkler system specifications. The subcontract’s provisions required Certified to complete the preliminary design drawings of the sprinkler system within two weeks and to obtain a certificate naming Precision as an additional insured. Over the next few weeks, Precision asked Certified several times to sign the subcontract and provide the additional-insured certificate.

Certified objected to the subcontract as imposing terms that differed from the bid specifications. It complained that the unanticipated terms changed the scope of work—including the size of pipes to be used, the placement of the fire riser, and the two-week time frame for producing drawings—and that it would have to amend its bid accordingly. Certified also took exception to some of the generic contractual provisions, including the additional-insured requirement.

On December 20, Precision notified all subcontractors, including Certified, that construction was under way. Certified hired Ron Dusky to draft the sprinkler system designs and, sometime in mid-January 2006, Dusky began drafting the designs. On January 19, with the subcontract still unsigned, Certified submitted a $33,575 progress bill to Precision, representing that it had completed seven percent of its work. But the design drawings apparently were still unfinished (or at least undelivered) because six days later, Precision wrote Doug Sartain, Certified’s owner, requesting the sprinkler plans “ASAP” and advising that Precision would not process the progress payment without a signed subcontract. The next day, January 26, Precision again contacted Sartain, asking [376]*376whether Certified planned to continue with the project and notifying him that its delay in submitting the plans was delaying the whole project.

On January 27, Certified reiterated its objections to the subcontract but assured Precision that it had begun the fire protection drawings. Certified completed the design work and submitted the sprinkler system drawings on February 1. Precision and Certified communicated several more times about getting the subcontract signed, and, on February 8, Precision learned that the drawings contained errors that needed correcting. It again asked Certified about the unsigned subcontract.

On February 16, Precision terminated its relationship with Certified for refusing to sign the subcontract, for not providing the additional-insured endorsement, and for incorrect designs. At Precision’s request, Certified submitted an itemized billing for the work it had performed; its bill reported costs of $25,185.04, which included design work and permit fees for the project. Precision deemed the costs too high and never paid. Certified placed a mechanic’s lien on the property and sued to recover for its design-related work. Certified’s complaint sought to foreclose the mechanic’s lien and damages for unjust enrichment, quantum meruit, and breach of contract.

The case proceeded to a bench trial, where Certified provided documentary evidence and the testimony of Certified owner Doug Sartain, Certified employee Gary Wooldridge, and the deposition testimony of Dusky, who drew the designs. At the close of Certified’s case-in-chief, Precision moved for judgment on partial findings pursuant to NRCP 52(c). The district court granted the motion and expunged the mechanic’s lien. The district court found that no contract existed, and that Certified’s claim for “quantum meruit has not been established based upon the fact that the design materials could not be utilized by [Precision].” For the same reason—failure to show that Precision had benefited from the design drawings—the court concluded that Precision had not been unjustly enriched. After entry of judgment, Precision moved for attorney fees under NRS 17.115 and NRS 108.237, which the district court denied.

On appeal, Certified argues that the district court failed to determine whether a contract for the design-only work existed but concedes that the parties never reached agreement on the full design and installation contract. Certified also asserts error in the district court’s conclusion that Precision was neither unjustly enriched nor liable to Certified in quantum meruit because Precision did not benefit from the work performed. On cross-appeal, Preci[377]*377sion argues that the district court abused its discretion in denying Precision’s motion for attorney fees.

n.

NRCP 52(c) allows the district court in a bench trial to enter judgment on partial findings against a party when the party has been fully heard on an issue and judgment cannot be maintained without a favorable finding on that issue. Although Certified argues otherwise, in entering a Rule 52(c) judgment, “[t]he trial judge is not to draw any special inferences in the nonmovant’s favor”; “since it is a nonjury trial, the court’s task is to weigh the evidence.” 9C Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 2573.1, at 256-60 (3d ed. 2008) (addressing NRCP 52(c)’s federal cognate, Fed. R. Civ. P. 52(c)); see Robert E. Jones et al., Rutter Group Practice Guide: Federal Civil Trials and Evidence § 17:92 (2011) (“Because the court acts as the factfinder when ruling on a [motion] for judgment on partial findings, it need not consider the evidence in a light favorable to the nonmoving party . . . .”). “Where a question of fact has been determined by the trial court, this court will not reverse unless the judgment is clearly erroneous and not based on substantial evidence.” Kockos v. Bank of Nevada, 90 Nev. 140, 143, 520 P.2d 1559, 1361 (1974).

In granting Precision’s motion for judgment on partial findings, the district court found that “there was no meeting of the minds on the material contractual terms . . . sufficient to form ... [a] contract,” and that the work Certified did could not be used by Precision and thus “conveyed no value” to Precision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Naessens v. Breslin
D. Nevada, 2025
IN RE: PARAMETRIC SOUND CORP. SHAREHOLDERS' LITIG. C/W 84971, 85358
140 Nev. Adv. Op. No. 36 (Nevada Supreme Court, 2024)
CAPITAL ADVISORS, LLC v. CAI C/W 85378
140 Nev. Adv. Op. No. 34 (Nevada Supreme Court, 2024)
COHEN v. PADDA C/W 81172
2022 NV 18 (Nevada Supreme Court, 2022)
KORTE CONSTR. CO. VS. STATE, BD. OF REGENTS
2021 NV 37 (Nevada Supreme Court, 2021)
NAUTILUS INS. CO. VS. ACCESS MED., LLC (NRAP 5)
2021 NV 10 (Nevada Supreme Court, 2021)
NEVADA STATE EDUC. ASS'N VS. CLARK CTY. EDUC. ASS'N
2021 NV 8 (Nevada Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
283 P.3d 250, 128 Nev. 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/certified-fire-protection-inc-v-precision-construction-inc-nev-2012.