State Drywall, Inc. v. Rhodes Design & Development

127 P.3d 1082, 122 Nev. 111, 122 Nev. Adv. Rep. 11, 2006 Nev. LEXIS 12
CourtNevada Supreme Court
DecidedFebruary 9, 2006
Docket42422
StatusPublished
Cited by18 cases

This text of 127 P.3d 1082 (State Drywall, Inc. v. Rhodes Design & Development) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Drywall, Inc. v. Rhodes Design & Development, 127 P.3d 1082, 122 Nev. 111, 122 Nev. Adv. Rep. 11, 2006 Nev. LEXIS 12 (Neb. 2006).

Opinion

*113 OPINION

By the Court,

Hardesty, J.:

In this breach of contract action, we conclude that a plaintiff is entitled to prejudgment interest on money paid under the contract during a pending collection suit, even though that payment is not included in the principal amount of the subsequent judgment. Further, for purposes of determining cost-shifting under NRCP 68(g) and NRS 17.115(5), we conclude that pre-offer prejudgment interest must be computed on payments made during the pendency of the suit and added to the actual judgment when it is compared to the offer of judgment despite the offer’s silence on the inclusion of interest.

BACKGROUND

This case arises out of a breach of contract dispute between appellant State Drywall, Inc., and respondent Rhodes Design & *114 Development. Rhodes, the general contractor for a residential housing development, had contracted with State Drywall to perform insulation, drywall, and painting work on several houses. After the work was completed, Rhodes failed to pay State Drywall for part of the work, the last unpaid invoice for which became due on January 21, 1999. As a result, State Drywall filed suit against Rhodes in April 1999 for breach of contract, seeking collection for the balance due. 2

While the litigation was pending, Rhodes paid State Drywall two payments on the contract, $26,500 in December 1999 and $81,250.02 in October 2002. After making the payments, but before trial, Rhodes made an offer of judgment under NRS 17.115 and NRCP 68 for $180,000, inclusive of costs. State Drywall did not accept the offer.

Following a bench trial, the district court found that Rhodes had breached its contract with State Drywall. Relying on a special master’s report that determined the balance due, the district court awarded State Drywall $106,502.01. The amount of the report and award did not include the payments made by Rhodes while the litigation was pending. The court also awarded State Drywall $42,244.02 in prejudgment interest on the judgment, calculated from the date the last invoice became due, January 21, 1999, to the date of Rhodes’s offer of judgment, June 10, 2003. The district court, however, did not award prejudgment interest on the two payments Rhodes made to State Drywall during the litigation, finding that because those payments were not part of the judgment, they could not earn prejudgment interest. 3

Thereafter, the district court conducted a cost-shifting analysis under NRS 17.115 and NRCP 68 and compared the offer of judgment to the actual judgment plus pre-offer prejudgment interest thereon. After doing so, the court awarded Rhodes costs and attorney fees, finding that State Drywall had not obtained a more favorable judgment than Rhodes’s offer. State Drywall appeals.

DISCUSSION

On appeal, State Drywall contends that the district court should have awarded it prejudgment interest on the two payments that Rhodes made before trial and added that prejudgment interest to *115 the judgment in making the comparison to the offer of judgment under NRS 17.115(5) and NRCP 68(g). 4 We agree.

Determination of the proper statute to calculate prejudgment interest

Before reaching State Drywall’s arguments, however, we must first determine which of two statutes governs the calculation of prejudgment interest. State Drywall contends that the general prejudgment interest provision for contractual matters, NRS 99.040(1), is controlling because this is a contract dispute and Rhodes owed its payment to State Drywall on a particular date. Conversely, Rhodes argues that NRS 17.130(2), the general statute for calculating interest “[w]hen no rate of interest is provided by contract or otherwise by law,” governs because NRS 99.040(2)(b) states that NRS 99.040(1) does not apply to money owed “[b]y a contractor to his subcontractor pursuant to NRS 624.630.” Rhodes contends that because it was a general contractor and State Drywall was a subcontractor, subsection (2)(b) precludes the calculation of prejudgment interest under NRS 99.040(1).

The district court calculated interest under NRS 99.040(1), as is evident from the court’s conclusion of law that prejudgment interest should be calculated from January 21, 1999, the date that *116 Rhodes’s final payment was due to State Drywall. 5 We review a district court’s statutory interpretations de novo. 6 The district court properly concluded that NRS 99.040(1) governs prejudgment interest in this case.

NRS 99.040(2)(b) provides that the statute is inapplicable to a contractor’s payments owed under NRS 624.630. NRS 624.630 governs the timing of payments made to subcontractors out of funds received by a contractor from an owner. Thus, NRS 99.040(2)(b) only limits the application of that statute when a contractor’s failure to pay its subcontractor is the direct result of not having received the necessary funds from the owner. Here, Rhodes’s reason for withholding payment to State Drywall was not the result of an owner’s failure to pay Rhodes. Consequently, NRS 624.630

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beauregard v. Sampson
D. Nevada, 2024
Aguilar v. Lucky Cab Co.
Nevada Supreme Court, 2024
HARRISON VS. RAMPARTS, INC.
2021 NV 65 (Nevada Supreme Court, 2021)
Harrison v. Ramparts, Inc.
500 P.3d 603 (Court of Appeals of Nevada, 2021)
Medical Recovery Svc v. Neumeier
Idaho Supreme Court, 2018
Med. Recovery Servs., LLC v. Neumeier
415 P.3d 372 (Idaho Supreme Court, 2018)
Slinker v. Zaleski
Nevada Supreme Court, 2014
Albios v. Horizon Communities, Inc.
132 P.3d 1022 (Nevada Supreme Court, 2006)
McCrary v. Bianco
131 P.3d 573 (Nevada Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
127 P.3d 1082, 122 Nev. 111, 122 Nev. Adv. Rep. 11, 2006 Nev. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-drywall-inc-v-rhodes-design-development-nev-2006.