Thompson v. Herrmann

530 P.2d 1183, 91 Nev. 63, 1975 Nev. LEXIS 540
CourtNevada Supreme Court
DecidedJanuary 29, 1975
Docket7324
StatusPublished
Cited by11 cases

This text of 530 P.2d 1183 (Thompson v. Herrmann) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson v. Herrmann, 530 P.2d 1183, 91 Nev. 63, 1975 Nev. LEXIS 540 (Neb. 1975).

Opinion

*64 OPINION

By the Court,

Mowbray, J.:

Walter E. Herrmann and his wife, Fern, filed a complaint in district court against Paul and Oleta Thompson, seeking specific performance or, in the alternative, damages resulting from an alleged breach of contract between the Herrmanns and the Thompsons, wherein Paul Thompson agreed to construct a small dam and reservoir for the Herrmanns in Lyon County. The Thompsons answered the complaint, and they filed a counterclaim, wherein they sought, in alternative causes of action, damages for breach of contract, fraud, unjust enrichment, and quantum meruit. The district judge found in favor of the Herr-manns and awarded them damages in the sum of $77,000, from which judgment the Thompsons have appealed.

1. In January 1970, the Herrmanns agreed to lease to the Thompsons their ranch in Lyon County. The term of the lease was for 7 years. The Thompsons agreed to pay a certain annual rental and to make designated leasehold improvements on the property, including the construction of an irrigation dam and reservoir in El Dorado Canyon. This lease agreement was superseded by a later one, executed by the parties in December 1971, wherein among other things the Thompsons agreed to commence construction and complete the dam before March 7, 1972. 1

The Herrmanns agreed to execute a grant deed conveying to the Thompsons 115 acres of their property, which deed was to be placed in escrow and to be delivered to the Thompsons 45 days after notice of completion of the dam had been recorded, provided that all liens validly recorded within the time prescribed by statute had been satisfied. 2 The agreement also *65 provided: “The construction of said dam shall be under the supervision of and constructed in a manner satisfactory and acceptable to Walter Reed [sic], who shall be compensated by the Parties of the Second Part [the Thompsons] for any expenses incurred from January 1, 1970 to completion, and be acceptable to the State Engineer, so as to satisfy the requirements of Permit Number 23729. Upon Walter Reed [sic] and the State of Nevada accepting the dam as being completed, it shall be complete and a notice of completion shall be recorded in Carson City and Lyon County by Paul Thompson.”

Paul Thompson commenced construction of the dam, following the plans previously drafted by Walter Reid, who on occasion checked the progress of the work. Work continued until January 1972, when it was stopped by the Nevada State Engineer. Starr Hill, Jr., an engineer with the State, testified that construction was stopped because the application for the permit which Mr. Reid had filed with the Division of Water Resources had never been finally approved. After negotiations with the State, Mr. Reid’s plans were amended, and approval to proceed was given by the State. 3

It was at this time that Paul Thompson abandoned the project and returned to his home in California. Starr Hill, Jr., Surface Water Engineer with the State, demanded in March 1972 that Mr. Herrmann either proceed with a firm schedule of construction of the dam or remove what had been done by Paul Thompson. 4

*66 The Hermanns then engaged the Worthington Construction Company of Elko, Nevada, to complete the project. Two of the changes required by the State included a filter blanket and the approval of a natural or constructed keyway at the bottom of the dam. In order to approve the keyway, it was necessary to inspect the bedrock beneath the dam, which required removal of certain compact material. When the removal was commenced, it was discovered that the fill provided by Thompson included large boulders, pine trees and trunks, plus sagebrush, which, of course, were not specified in the plans Reid had furnished Thompson. 5 As a result, it was necessary to remove all the compact fill and start from the beginning to build the dam. 6 Mr. Walter Reid, upon direct examination by Mr. Martillaro, *67 testified that Thompson had failed to follow his plans and specifications and that the work was completely defective. 7

*68 2. The district judge found, and correctly so, that Thompson’s performance was so inadequate and his work so defective that he was barred from any recovery under the agreement of the parties. As the Colorado court said in Little Thompson Water Ass’n v. Strawn, 466 P.2d 915, 917 (1970):

. The rules appear to be that if the promisor proves complete and full performance, he is entitled to recover the complete and full consideration bargained for; if the proof establishes something less than full and complete performance, that is, substantial performance only, he is entitled to recover the contract price less those necessary expenditures required to complete the performance bargained for; and, if the performance falls short of being substantial, then the promisor is entitled to no recovery. See also 3 A. Corbin, Contracts §§ 700-12; 17 Am.Jur.2d Contracts § 375. Whether performance is complete, substantial, or less than substantial involves a factual determination for the trier of facts, here, the jury.”

In the instant case, the district judge as the trier of the facts found a complete failure of performance on Thompson’s part, and the record supports that finding. It may not be disturbed on appeal. Britz v. Consolidated Casinos Corp., 87 Nev. 441, 488 P.2d 911 (1971); Nevada Bank of Commerce v. Esquire Real Estate, Inc., 86 Nev. 238, 468 P.2d 22 (1970).

The Thompsons argue, on the basis of a quantum meruit theory, that the court erred in not awarding them damages for the work that Paul Thompson actually did on the dam and for the alleged moneys he spent in hiring certain help and buying fuel for the machinery. The basis of recovery on quantum meruit, however, is that a party has received from another a benefit which is unjust for him to retain without paying for it. Maui Aggregates, Inc. v. Reeder, 446 P.2d 174 (Hawaii 1968). However, here there was no showing of a benefit flowing from the Thompsons to the Herrmanns. As a matter of fact, the record is uncontroverted that it cost the Herrmanns $21,000 to remove the partially constructed dam because of Thompson’s failure to follow the plans for its construction. 8

*69 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FRESH MIX LLC
D. Nevada, 2023
Sierra Dev. Co. v. Chartwell Advisory Grp., Ltd.
325 F. Supp. 3d 1102 (D. Nevada, 2018)
Las Vegas Sands Corp. v. Suen
Nevada Supreme Court, 2016
Crockett & Myers v. Napier
Ninth Circuit, 2009
Hermann v. Varco-Pruden Buildings
796 P.2d 590 (Nevada Supreme Court, 1990)
Spinella v. B-Neva Inc.
580 P.2d 945 (Nevada Supreme Court, 1978)
Reese v. Utter
551 P.2d 1099 (Nevada Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
530 P.2d 1183, 91 Nev. 63, 1975 Nev. LEXIS 540, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-v-herrmann-nev-1975.