Century Marine Inc v. United States

CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 27, 1998
Docket03-20991
StatusPublished

This text of Century Marine Inc v. United States (Century Marine Inc v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Century Marine Inc v. United States, (5th Cir. 1998).

Opinion

UNITED STATES COURT OF APPEALS For the Fifth Circuit

No. 97-20281

CENTURY MARINE INCORPORATED,

Plaintiff-Appellant;

VERSUS

UNITED STATES OF AMERICA,

Defendant-Appellee.

Appeal from the United States District Court For the Southern District of Texas August 27, 1998

Before BARKSDALE, BENAVIDES and DENNIS, Circuit Judges.

DENNIS, Circuit Judge:

Appellant Century Marine, Inc. (“Century”), appeals the

district court’s dismissal of its claims for additional

compensation under a fixed-price vessel repair contract with the

Maritime Administration of the United States Department of

Transportation (“MARAD”). MARAD terminated the contract because of

Century’s default in failing to complete the work within the time

specified by the contract. Century filed suit against the United

States seeking to have the termination for default converted to a

termination for the Government’s convenience; and for payments in

addition to the amount MARAD had paid Century under the terminated contract. After a bench trial, the district court rejected

Century’s demands and dismissed its suit with prejudice. We

affirm. On appeal Century does not contest the trial court’s

determination that its contract was properly terminated for

default. Despite its default, Century argues that it is entitled

to recover an amount equal to the unpaid balance of the full fixed

price of the contract less the cost of completion of the unfinished

work under the contract. Century’s argument is contrary to well

established law and federal regulations. Under the Government’s

termination of a fixed-price contract because of the contractor’s

default, the Government is not liable to the contractor for

unperformed or undelivered work. Anticipated but unearned profits

are not recoverable by the contractor when the Government

terminates the contract for the contractor’s default or for the

convenience of the Government. Century’s additional contention

that it should be compensated for extra work is also without merit.

There is warrant in the record and an applicable basis in law for

the district court’s rejection of this claim after a trial on the

merits.

I. FACTUAL AND PROCEDURAL BACKGROUND

In September 1992, Century and MARAD entered into a fixed-

price contract for the repair and renovation of cargo and ballast

tanks of the S.S. MOUNT WASHINGTON, a public vessel of the United

States. Thereafter, MARAD issued three contract modifications

(“Mods”) that increased the contract value by $1,050,000.000, for

a total contract amount of $8,521,910.000. When Century fell

2 behind schedule on the original completion date of May 3, 1993,

MARAD issued three additional Mods that extended the completion

date until September 15, 1993. Despite these extensions, Century

continued to fall behind its work schedule. When it became evident

that Century could not complete the contract timely, by letter

dated September 8, 1993, MARAD terminated Century for default.1 At

the time of termination, MARAD had made progress payments to

Century of $5,903,135.50. On September 22, 1993, the Government

issued Modification No. 0009 (“Mod 9") to the contract that

adjusted the contract price for the value of the unfinished work,

and calculated the final progress payment to Century based on its

completed work. MARAD eventually retained another contractor to

finish Century’s work.2

Mod 9, admitted as a Government exhibit at trial, sets forth

the percentage of completion of each work item, and adjusts the

total contract price by deducting the contract value of Century’s

1 Pursuant to the Federal Acquisition Regulations, the Government may, by written notice of default to the contractor, terminate the contract in whole or in part if the contractor fails to perform the services within the time specified in the contract or any extension. 48 C.F.R. § 52.249.8(a)(1)(i). “Federal regulations which are based upon a grant of authority ‘have the force and effect of law, and, if they are applicable, they must be deemed terms of the contract even if not specifically set out therein, knowledge of which is charged to the contractor.’” General Eng’g & Mach. Works v. O’Keefe, 991 F.2d 775, 780 (Fed. Cir. 1993). 2 Under the Federal Acquisition Regulations, when the services to be provided by the terminated contractor are still required after default, the contracting officer shall repurchase the same services against the contractor’s account as soon as practicable, 48 C.F.R. § 49.402-6(a), and the contractor is liable to the Government for any excess costs incurred in acquiring services similar to those terminated for default. 48 C.F.R. § 49.402-2(e).

3 uncompleted work, estimated at $1,260,861.00. In Mod 9, MARAD

based the percentage of completion in part on Century’s own percent

completion figure provided in its last progress payment request

submitted to MARAD one week prior to termination, with this figure

adjusted for work accomplished by Century during the final week of

the terminated contract. The Government’s estimate in Mod 9 of the

contract value of Century’s uncompleted work also was based on a

thorough inspection and videotaping of each item of unfinished work

by Richard Volkmann, the contracting officer’s technical

representative, who testified at trial.

Based on the Government’s calculations in Mod 9, MARAD made a

final payment to Century of $409,023.56, representing compensation

for all work performed after the latest progress payment but before

Century was terminated for default. According to the contracting

officer’s decision denying Century’s administrative claims for

additional compensation, this final payment to Century represented:

(1) payment for the progress made by Century between the time of

its last progress payment and termination of the contract

($51,532.00); (2) payment of the balance of retainage owed to

Century after deducting the excess cost of procurement

($285,539.06)3; and (3) payment of funds withheld at the direction

of the Government‘s legal department until a separate claim on

another contract was settled ($71,952.50).

3 Under the Federal Acquisition Regulations, “the contracting officer shall use all retained percentages of progress payments previously made to the contractor and any progress payments due for work completed before the termination to liquidate the contractor’s liability to the Government.” 48 C.F.R. § 49.406.

4 In July 1994, Century submitted a “Request For Equitable

Adjustment and For Conversion of a Termination For Default to a

Termination For Convenience.” Century’s Request For Equitable

Adjustment presented an administrative claim for additional

payments of almost $1.3 million under the contract, based on

Century’s allegations that MARAD had underestimated the percentage

of completion of finished work items in Mod 9, and that MARAD was

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schlesinger v. Herzog
2 F.3d 135 (Fifth Circuit, 1993)
Justiss Oil Co. v. Kerr-McGee Refining Corp.
75 F.3d 1057 (Fifth Circuit, 1996)
Burma Navigation Corp. v. Reliant Seahorse MV
99 F.3d 652 (Fifth Circuit, 1996)
United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
United States v. United States Gypsum Co.
333 U.S. 364 (Supreme Court, 1948)
Chandler v. Roudebush
425 U.S. 840 (Supreme Court, 1976)
Grant v. News Group Boston, Inc.
55 F.3d 1 (First Circuit, 1995)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Cupey Bajo Nursing Home, Inc. v. United States
40 Cont. Cas. Fed. 76,952 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Century Marine Inc v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/century-marine-inc-v-united-states-ca5-1998.