Central Maine Power Co. v. Public Utilities Commission

416 A.2d 1240, 1980 Me. LEXIS 606
Supreme Judicial Court of Maine·Decided July 2, 1980·Published·Cited by 6 cases

Opinion

NICHOLS, Justice.

St. Regis Paper Company, Keyes Fibre Company and Scott Paper Company, three industrial customers of Central Maine Power Company and intervenors in the present rate proceedings before the Public Utilities Commission, 1 appeal pursuant to 35 M.R. S.A. § 303 from the Commission’s August 22,1979, Supplemental Order No. 4, approving the utility’s proposed new rate schedule. The focus of this appeal is upon the “rate design” portion of the Order which on a uniform percentage basis to all customer classes allocates the revenue increases permitted by the order. The Intervenors contend that the Commission’s rejection of the utility’s proposed rate design in the absence of evidence to support any alternate design was unreasonable and erroneous as a matter of law, because there was substantial evidence on the record to support acceptance of the utility’s proposal. They further assert that the uniform percentage increase imposed by the Commission is unreasonable and unjustly discriminatory as a matter of law because that design is not supported by “substantial evidence” on the record.

We affirm the Commission’s decision.

I. Procedural History, Facts and Issues

This rate case was previously before us in Central Maine Power Company v. Public Utilities Commission, Me., 405 A.2d 153 (1979). On that consolidated appeal, the utility and several intervenors challenged the Commission’s disallowance of the revised schedule of rates filed by the utility on January 16, 1978. In this original rate schedule, filed pursuant to 35 M.R.S.A. § 64, the utility requested increased revenues of approximately 25 million dollars and proposed a new rate design by which the utility would allocate the requested revenue increase by varying percentages among its seven major classes of customers 2 in such a way as to decrease alleged disparity in the rates of return among those customer classes. The proposed design was supposed to bring each class closer to the system average rate of return so that no class would have to shoulder more than its fair share of the utility’s cost of providing electricity. The increases ranged from 3.7% for the GS-1 and GST classes to 17% for the residential class.

In support of its proposed allocation of the revenue increase by varying percentages, the utility submitted to the Commission a cost of service study prepared by Frederick E. Anderson, Director of the utility’s Rate Department [the “Anderson Study”]. This cost of service study, based on a 1977 test year, purported to show the relationship of the rates of return among the various customer classes.

The Anderson study attempted to assign responsibility to the various rate classes for the embedded costs of providing each class with service. By comparing the total costs assigned to each class with the revenues collected from each class, the utility determined the rate of return it earns from each class of service. The proposed rates allocated the greatest portion of the revenue increase to the classes generating the lowest rate of return and the least portion to those generating the highest rate of return. In *1242 this way, the utility hoped to relate the electric rate paid by each class more closely to the cost of providing electricity.

The process of determining the rate of return for each class was complex. All costs were divided into one of several functions (e. g., power supply, transmission, distribution). Each of the functions was then “classified” in order to determine whether it had demand, energy, or customer components. Finally, all costs were allocated to the various customer classes by means of allocation factors which are derived by various methods depending upon the function and classification of the cost.

A significant portion of the overall costs of providing electrical service is classified by the utility as “demand” cost. The Anderson Study employed the so-called “one-hour coincident peak method” in allocating to each class its portion of total demand costs generated during the 1977 test year. Under this method, the utility first determined the one hour during the entire test year when demand for electricity was at its peak. In 1977, the one-hour coincident peak occurred between 5:00 P.M. and 6:00 P.M. on December 12. The utility next determined the number of kilowatts each class was demanding at that particular peak hour, and from this information calculated the proportion of each class’s contribution to the utility’s demand costs during that one hour.

The “one-hour coincident peak method” of allocation assumes that the load usage during the single hour of the annual system peak is representative of each class’s responsibility for costs over the entire year. The Anderson study, therefore, took the proportionate contribution to cost of each class during the one peak hour and assigned total test year costs to each class in the same proportions. It then compared the costs assigned to each class with the revenues collected from each class and determined their various rates of return.

The utility employed the results of the Anderson Study in designing the allocation among the classes of its proposed revenue increase. The utility compared the rates of return calculated by Anderson with its overall average rate of return, and assigned the proposed additional revenues in varying amounts to the different classes in such a way as to bring each class’s rate of return closer to the system average. 3

From May 8, 1978, through August 9, 1978, the Commission held 27 days of hearings, pursuant to 35 M.R.S.A. § 69, on the. utility’s revised schedule of rates. Much of the testimony and many of the exhibits concerned the new rate design proposal. The utility and the Intervenors presented several expert witnesses and introduced into evidence a number of exhibits on the issue of rate design. The Commission staff also presented its own expert witness. The witnesses were in general agreement that the allocation of revenues to each customer class should reflect the cost of serving that *1243 class; that the rates of return among the customer classes were not currently equivalent; and that the evidence tended to show the residential rate of return was below the system average and the general service transmission (GST) rate of return was above the system average. There were, however, significant differences of opinion as to the best method of computing accurate rates of return. Much of the testimony was grossly technical and need not be elaborated upon in this opinion. A sampling of the varied opinions with which the Commission was faced, however, follows.

Frederick E. Anderson, the author of the Anderson Study, testified in great detail in support of the “one-hour coincident peak method.” He said that his objective in preparing the study was to aid the utility in making its rates more cost-related.

Dr. John W.

Free access — add to your briefcase to read the full text and ask questions with AI

Central Maine Power Co. v. Public Utilities Commission, 416 A.2d 1240, 1980 Me. LEXIS 606 (Me. 1980).

416 A.2d 1240 (Central Maine Power Co. v. Public Utilities Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Industrial Energy Consumer Group v. Public Utilities Commission
2024 ME 60 (Supreme Judicial Court of Maine, 2024)
Colorado-Ute Electric Ass'n v. Public Utilities Commission
760 P.2d 627 (Supreme Court of Colorado, 1988)
Welch v. Pennsylvania Public Utility Commission
464 A.2d 568 (Commonwealth Court of Pennsylvania, 1983)
New England Telephone & Telegraph Co. v. Public Utilities Commission
448 A.2d 272 (Supreme Judicial Court of Maine, 1982)
Central Maine Power Co. v. Public Utilities Commission
433 A.2d 331 (Supreme Judicial Court of Maine, 1981)