New England Telephone & Telegraph Co. v. Public Utilities Commission

354 A.2d 753, 15 P.U.R.4th 128, 1976 Me. LEXIS 423
CourtSupreme Judicial Court of Maine
DecidedMarch 24, 1976
StatusPublished
Cited by21 cases

This text of 354 A.2d 753 (New England Telephone & Telegraph Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Telephone & Telegraph Co. v. Public Utilities Commission, 354 A.2d 753, 15 P.U.R.4th 128, 1976 Me. LEXIS 423 (Me. 1976).

Opinion

WERNICK, Justice.

On October 25, 1974 New England Telephone & Telegraph Company (“New England”) filed a petition for “interim” rate relief with the Public Utilities Commission (“Commission”). On March 11, 1975 the Commission denied the petition. New England then, on April 7, 1975, initiated the instant proceedings for judicial review by invoking this Court’s “appeal” jurisdiction under 35 M.R.S.A. §§ 303 (“Section 303 appeal”) and its additional “complaint” (in equity) jurisdiction under Section 305 (“Section 305 complaint.”)

We dismiss New England’s “Section 303 appeal” for mootness. We deny New England’s “Section 305 complaint” and order judgment thereon in favor of defendant Commission.

I. The Background and Framework of the Proceedings

The precursor of the instant proceedings was a proceeding in September of 1973 precipitated when New England filed with the Commission changes of its then current schedule of permanent 1 intrastate rates, tolls and charges. The changes were calculated to increase the company’s gross annual revenues by approximately $6,300,000. Acting pursuant to 35 M.R.S.A. § 69, the Commission entered an order of suspension *755 thereby preventing New England’s revised schedule from becoming effective, automatically, upon the expiration of 30 days under 35 M.R.S.A. § 64 (hereinafter “Section 64.”) After a hearing and investigation concerning the “justness and reasonableness” of the changes of rates contained in New England’s September 1973 filing, the Commission, on June 13, 1974, found said changes of permanent rates to be neither just nor reasonable. Accordingly, as authorized by 35 M.R.S.A. § 69, (hereinafter “Section 69”) the Commission ordered New England to “substitute” a changed schedule of permanent rates under which New England would derive an increase in its gross annual revenues of $3,964,415.00 (instead of the $6,300,000 contemplated by New England’s original filing). New England filed the Commission-ordered “substituted” changed schedule of permanent rates and shortly thereafter such changed permanent rates went into effect.

On October 8, 1974 New England again filed with the Commission changes of its schedule of intrastate permanent rates designed to produce a further increase of $21,000,000 in New England’s gross annual revenues. Seventeen days thereafter (on October 25) New England filed the petition for “interim” rate relief the Commission’s denial of which constitutes the subject of the instant review proceedings.

New England stated in its petition that it would need “interim” rate relief because it had ascertained that the Commission was about to issue an order of suspension to preclude effectiveness (at the expiration of 30 days under Section 64) of the changes in its schedule of permanent rates as filed by New England on October 8, 1974. The petition asked the Commission to authorize rates which would generate an additional $6,582,987 in New England’s gross annual revenues and have “interim” effectiveness pending the Commission’s decision on New England’s October 8, 1974 filing. New England suggested that the “interim” relief be accomplished by the Commission’s withholding suspension of particular “parts” of the revised schedule filed by New England on October 8, 1974 thus to allow such “parts” to become effective automatically upon the expiration of 30 days from October 8th.

On November 6, 1974 the Commission did suspend in its entirety New England’s October 8, 1974 permanent rate-change filing. On December 30, 1974 the Commission held a hearing on New England’s petition for “interim” rate relief and approximately ten weeks later (on March 11, 1975) denied the petition. Thus, for a potentially maximum period of eight months from November 6, 1974-^the time allowable to the Commission upon an order of suspension (under Section 69) for investigation of the justness and reasonableness of New England’s October 8, 1974 permanent rate-change filing, — New England faced the prospect of living with the June, 1974 rates.

On July 3, 1975 the Commission made an order in which it stated that it

“[saw] no justification for permitting [New England] to collect $21,000,000 ...”

in additional gross annual revenues but authorized New England to file a changed rate schedule to yield an increase in New England’s gross annual revenues of $9,500,000. 2 Such changed schedule of rates was filed by New England and went into effect on July 16, 1975.

Because of the Commission’s action of July 3, 1975 New England has modified its claim before this Court. It has informed this Court that the Court’s review of the correctness of the Commission denial of the petition for “interim” rate relief is to *756 be confined to consideration of such injury as New England claims to have suffered by being deprived of an increase in revenues during the period from March 11, 1975 to July 16, 1975 — the period, now entirely in the past, between the denial of New England’s petition for “interim” rate relief and the July 16, 1975 effective date of the changed rates which would provide New England a $9,500,000 increase in its revenues.

On August 13, 1975 the Commission moved this Court to dismiss the proceedings in this Court on the ground that the relief sought by New England is beyond the power of this Court to grant under either a “Section 303 appeal” or a “Section 305 complaint.”

The issue precipitated by the Commission’s motion to dismiss may be more sharply delineated as follows. New England, in essence, maintains that the Commission’s denial of its petition for “interim” rate relief left New England in the position of being required to charge during the period from March 11, 1975 to July 16, 1975 rates shown by New England to be unjust and unreasonable because confiscatory. Thus, says New England, this Court should now provide New England with a remedy for the loss of the increased revenues which New England claims it has shown were its constitutional entitlement during the entirely past period March 11 to July 16, 1975. The remedy New England seeks — as consistent with the prospectivity with which changes of rates are to be made effective — is that this Court order a rate surcharge to be paid by those who will be purchasing New England’s services after this Court’s order becomes effective and to continue operative until New England has received the amount claimed as its constitutional due for said past period.

The Commission’s position is that under Maine’s statutory scheme of rate regulation this Court, insofar as it has been authorized to review actions of the Commission relative to rates, lacks power to order remedial relief, i. e., relief as to a situation entirely in the past — whether by “surcharge” on future ratepayers or otherwise ■ — -to compensate a utility for revenue losses alleged to have been unlawfully caused the utility during a period which, at the time of this Court’s judicial review, is no longer continuing but has entirely terminated.

The issue thus presented requires us to examine the development of Maine’s statutory scheme of rate regulation.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Public Advocate v. Public Utilities Commission
1998 ME 218 (Supreme Judicial Court of Maine, 1998)
Casco Bay Island Transit District v. Public Utilities Commission
528 A.2d 448 (Supreme Judicial Court of Maine, 1987)
Columbia Gas of West Virginia, Inc. v. Public Service Commission
311 S.E.2d 137 (West Virginia Supreme Court, 1983)
Potomac Electric Power Co. v. Public Service Commission
457 A.2d 776 (District of Columbia Court of Appeals, 1983)
Central Maine Power Co. v. Maine Public Utilities Commission
436 A.2d 880 (Supreme Judicial Court of Maine, 1981)
First Hartford Corp. v. Central Maine Power Co.
425 A.2d 174 (Supreme Judicial Court of Maine, 1981)
Casco Bay Lines v. Public Utilities Commission
390 A.2d 483 (Supreme Judicial Court of Maine, 1978)
Portland Water District v. Public Utilities Commission
388 A.2d 91 (Supreme Judicial Court of Maine, 1978)
In re Stratton Water Co. Proposed Increase in Rates
383 A.2d 1373 (Supreme Judicial Court of Maine, 1978)
Central Maine Power Co. v. Public Utilities Commission
382 A.2d 302 (Supreme Judicial Court of Maine, 1978)
Mechanic Falls Water Co. v. Public Utilities Commission
381 A.2d 1080 (Supreme Judicial Court of Maine, 1977)
Friends of the Earth v. Public Service Commission
254 N.W.2d 299 (Wisconsin Supreme Court, 1977)
New England Telephone & Telegraph Co. v. Public Utilities Commission
362 A.2d 741 (Supreme Judicial Court of Maine, 1976)
Maine Motor Rate Bureau
357 A.2d 518 (Supreme Judicial Court of Maine, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
354 A.2d 753, 15 P.U.R.4th 128, 1976 Me. LEXIS 423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-telephone-telegraph-co-v-public-utilities-commission-me-1976.