Colorado-Ute Electric Ass'n v. Public Utilities Commission

760 P.2d 627, 12 Brief Times Rptr. 1084, 1988 Colo. LEXIS 127
CourtSupreme Court of Colorado
DecidedJuly 11, 1988
Docket86SA244, 86SA246
StatusPublished
Cited by35 cases

This text of 760 P.2d 627 (Colorado-Ute Electric Ass'n v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colorado-Ute Electric Ass'n v. Public Utilities Commission, 760 P.2d 627, 12 Brief Times Rptr. 1084, 1988 Colo. LEXIS 127 (Colo. 1988).

Opinions

ROVIRA, Justice.

These two cases concern a judgment of the Montrose County District Court which set aside orders promulgated by the Public Utilities Commission of Colorado (PUC or Commission) involving the design of electric power rates to be charged by Colorado-Ute Electric Association (Colo-Ute).

We reject Colo-Ute’s claim that this appeal is moot. We further hold, contrary to the district court’s order, that the PUC possessed statutory authority to determine whether the tariffs filed by Colo-Ute were just and reasonable. Moreover, the PUC's order that Colo-Ute’s proposed all-energy rate should be replaced by a seasonally-differentiated demand-energy rate is supported by adequate findings of fact and substantial evidence. We do, however, affirm the ruling of the district court setting aside that portion of the PUC’s order which allocated $24,084,126 of generation fixed costs to the energy component of the demand-energy rate design. Accordingly, we reverse in part, affirm in part, and remand for further proceedings consistent with this opinion.

I.

Colo-Ute generates and transmits electrical power on a wholesale basis to 14 member rural electrical cooperatives (co-ops), which in turn market the electrical power on a retail basis to electrical consumers. The co-ops are consumer owned and have representatives on the board of directors of Colo-Ute, a non-profit corporation.

In December 1981, Colo-Ute filed Advice Letter No. 45 with the PUC. The purpose of the filing was to increase Colo-Ute’s wholesale electric power rates and thus increase annual revenue from the co-ops by approximately $11,120,603. At the time Advice Letter No. 45 was filed, Colo-Ute’s pricing scheme for its member co-ops was on a “flat” or “all-energy” rate basis.1 This pricing method had been approved by the PUC in February 1981. To reach its desired revenue increase, Colo-Ute proposed increasing its all-energy rate by a uniform 12.157 percent.

A revised rate schedule became effective on January 15, 1982. As a result of a statutory provision adopted by the legislature in 1981, which is central to a resolution of the jurisdictional issue in this case, the Commission is without authority to suspend the effective date of tariff changes filed by cooperative electric associations. See § 40 — 6—11 l(4)(a), 17 C.R.S. (1984). The PUC, assuming that this statutory provision relating to suspension had no effect on its authority to investigate rate filings, on January 12, 1982, initiated Case No. 6076 for the purpose of investigating the reasonableness of the tariffs filed by Colo-Ute, and set the matter for hearing.

A number of parties intervened and participated in Case No. 6076. Intervening parties included the co-ops, as well as customers of the co-ops: Union Carbide Corporation, Shell Oil Company, Exxon Company, USA (Exxon), Atlantic Richfield Company (ARCO), and the City of Delta, Colorado. At the hearings, Colo-Ute and some of the co-ops presented evidence both in support of the revenue increase and in the continued use of a flat or all-energy rate. The PUC’s staff offered evidence generally supporting a revenue increase, but recommended abandoning the continued use of the all-energy rate, which the staff asserted was not “cost tracking,” and therefore, no longer appropriate for Colo-Ute.2 In its [632]*632place, the staff recommended a seasonally-differentiated demand-energy rate.3 The intervening customers concurred in the recommendations of the Commission’s staff.

The Commission approved the revenue increase sought by Colo-Ute. However, it disapproved the continued use of the all-energy rate, and ordered Colo-Ute to file “demand energy rates for its wholesale electric customers with seasonally differentiated demand charges and an annualized energy [charge] on a uniform kwh basis.” Decision No. C83-1176.

Intervenors ARCO and Exxon, while in general agreement with the PUC’s ultimate findings regarding the revenue increase and the substitution of the demand-energy rate, objected to that part of the PUC’s decision which allocated over $24 million in generation fixed or demand costs to the energy component of the demand-energy rate design. Thereupon, ARCO, Exxon, Colo-Ute, and the co-ops filed applications for rehearing, reargument, and reconsideration. In Decision No. C83-1392, the Commission denied the application of Colo-Ute and the co-ops and granted the application of ARCO and Exxon in part. Decision No. C83-1176 was modified as a result, but such modifications are not at issue.4

Colo-Ute and the co-ops sought judicial review in the Montrose County District Court. The appeal was assigned Case No. 83CV218. They challenged the authority of the PUC to commence an investigation concerning the rate increase on its own motion. They also claimed that the Commission’s orders with respect to rate design were arbitrary, capricious, unconstitutional, an abuse of discretion, and not in accordance with the law and the evidence. Finally, they moved for a stay or suspension of the Commission’s decisions, pending final determination by the district court of their challenge. This motion was granted.

ARCO and Exxon sought judicial review in the Denver District Court of that portion of the PUC’s decisions which allegedly had misclassified certain demand costs as energy costs. Given the similarities of the parties in the Denver and Montrose District Court actions, and the presence of common questions, the Denver District Court ordered the case transferred to the Montrose District Court, pursuant to C.R.C.P. 98(f)(1), where it was assigned Case No. 84CV7. Subsequently, the court consolidated the two cases for hearing. The only issue in Case No. 84CV7 concerns the PUC’s decision to shift substantial demand costs onto the energy portion of the demand-energy rate.

With respect to Colo-Ute’s claims in Case No. 83CV218, the district court held, inter alia, that: (1) The PUC does not possess statutory authority, in the absence of a complaint, to investigate and modify the rate design of an electric cooperative association, such as Colo-Ute; (2) The PUC’s orders concerning rate design amount to an unwarranted intrusion into the management prerogative and discretion of Colo-Ute; (3) The Commission’s findings are conclusory in nature and are not supported by substantial evidence.5 The dis[633]*633trict court thereupon set aside that part of Decision No. C83-1176 which required Colo-Ute to file rates and tariffs ordered by the Commission.

In Case No. 84CV7, the district court concurred in the arguments presented by ARCO and Exxon, finding that the decision of the Commission to allocate over $24 million of demand costs to energy costs was not supported by substantial evidence or adequate findings of fact, was arbitrary and capricious, and resulted in an unjust and discriminatory rate. The court set aside that portion of Decision No. C83-1176 which allocated $24 million of the demand costs to the energy costs and further held that if this court (supreme court) were to find lawful the Commission’s imposition of the demand-energy rate, the PUC would be directed to allocate demand-energy costs in accordance with the staffs cost-of-service study, as contained in Exhibit No. 84.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colorado Medical Board v. Singer
Colorado Court of Appeals, 2025
Todd Creek Village Metropolitan District v. Valley Bank & Trust Co.
2013 COA 154 (Colorado Court of Appeals, 2013)
People ex rel. Vivekanathan
2013 COA 143 (Colorado Court of Appeals, 2013)
Turney v. Civil Service Commission
222 P.3d 343 (Colorado Court of Appeals, 2009)
Durango Transportation, Inc. v. Colorado Public Utilities Commission
122 P.3d 244 (Supreme Court of Colorado, 2005)
Huddleston v. Board of Equalization
31 P.3d 155 (Supreme Court of Colorado, 2001)
Citizens' Utility Ratepayer Board v. State Corp. Commission
16 P.3d 319 (Court of Appeals of Kansas, 2000)
AviComm, Inc. v. Colorado Public Utilities Commission
955 P.2d 1023 (Supreme Court of Colorado, 1998)
Phoenix Power Partners, L.P. v. Colorado Public Utilities Commission
952 P.2d 359 (Supreme Court of Colorado, 1998)
CF&I Steel, L.P. v. Public Utilities Commission
949 P.2d 577 (Supreme Court of Colorado, 1997)
Havens v. Board of County Commissioners
924 P.2d 517 (Supreme Court of Colorado, 1996)
Mountain City Meat Co. v. Oqueda
919 P.2d 246 (Supreme Court of Colorado, 1996)
Feigin v. Colorado National Bank, N.A.
897 P.2d 814 (Supreme Court of Colorado, 1995)
Integrated Network Services, Inc. v. Public Utilities Commission
875 P.2d 1373 (Supreme Court of Colorado, 1994)
Bryant v. Arkansas Public Service Commission
871 S.W.2d 414 (Court of Appeals of Arkansas, 1994)
Colowyo Coal Co. v. City of Colorado Springs
879 P.2d 438 (Colorado Court of Appeals, 1994)
Committee for Better Health Care for All Colorado Citizens v. Meyer
830 P.2d 884 (Supreme Court of Colorado, 1992)
Dempsey v. Romer
825 P.2d 44 (Supreme Court of Colorado, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
760 P.2d 627, 12 Brief Times Rptr. 1084, 1988 Colo. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colorado-ute-electric-assn-v-public-utilities-commission-colo-1988.