Center for Biological Diversity v. United States Department of the Interior

623 F.3d 633, 72 ERC (BNA) 1064, 2010 U.S. App. LEXIS 19767, 2010 WL 3704200
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 23, 2010
Docket07-16423
StatusPublished
Cited by37 cases

This text of 623 F.3d 633 (Center for Biological Diversity v. United States Department of the Interior) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Center for Biological Diversity v. United States Department of the Interior, 623 F.3d 633, 72 ERC (BNA) 1064, 2010 U.S. App. LEXIS 19767, 2010 WL 3704200 (9th Cir. 2010).

Opinions

Opinion by Judge WILLIAM A. FLETCHER; Dissent by Judge TALLMAN.

ORDER

This court’s opinion filed September 14, 2009, and reported at 581 F.3d 1063, is withdrawn, and is replaced by the attached Opinion and Dissent.

The full court has been advised of the petition for rehearing en banc and no judge of the court has requested a vote on whether to rehear the matter en banc. Fed. R.App. P. 35.

[636]*636The petition for rehearing en banc, filed October 29, 2009, is DENIED. Judge Tallman voted to grant the petition for rehearing en banc.

No further, petitions for rehearing or rehearing en banc will be accepted.

OPINION

W. FLETCHER, Circuit Judge:

The Center for Biological Diversity, the Western Land Exchange Project, and the Sierra Club (collectively, “Appellants”) bring suit against Asarco LLC (“Asarco”), a mining company, and the Department of Interior and the Bureau of Land Management (collectively, “BLM”). Appellants contend that the BLM’s approval of a land exchange violates the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-70; the Federal Land Policy and Management Act (“FLPMA”), 43 U.S.C. §§ 1701-87; and the Mining Law of 1872, 30 U.S.C. §§ 21-54.

If the proposed exchange does not occur, the land will continue to be owned by the United States. In that event, Asarco will be permitted to conduct mining operations on the land only if it complies with the Mining Law of 1872. Specifically, Asarco will not be able to conduct a new mining operation on the land without first submitting a Mining Plan of Operations (“MPO”) to the BLM. The MPO would have to include detailed information about the operations, management, monitoring, and environmental impacts of the proposed mining activities. The BLM would then have to approve the MPO before the new mining could proceed.

If the proposed exchange occurs, Asarco would take fee simple ownership of the exchanged land. In that event, Asarco’s use of the land would not be subject to the requirements of the Mining Law of 1872. Asarco has spent sixteen years, and considerable amounts of time and money, seeking to achieve private ownership of the exchanged land, which would allow Asarco to avoid having to prepare the MPOs that are required so long as the land remains in public hands.

As part of the process of approving the land exchange, the BLM prepared a Final Environmental Impact Statement (“FEIS”) pursuant to NEPA. In the FEIS, the BLM assumed without analysis that the MPO process would impose no constraints on, and would have no effect on, the manner in which Asarco would conduct new mining operations on the exchanged land. That is, the BLM assumed that the manner and extent of Asarco’s new mining operations would be the same whether or not the United States owned the land. Because of this assumption, the BLM did not compare the environmental effects of exchanging the land with the effects of not exchanging the land.

Under these circumstances, we hold that the BLM has not “taken a ‘hard look’ at the environmental consequences of its proposed action” in violation of NEPA, and that its action was therefore arbitrary and capricious. Blue Mountains Biodiversity Project v. Blackwood, 161 F.3d 1208, 1211 (9th Cir.1998). We also hold that the BLM’s approval of the proposed land exchange was a violation of FLPMA and similarly arbitrary and capricious. Webb v. Lujan, 960 F.2d 89, 91 (9th Cir.1992). We therefore reverse the decision of the district court approving the actions of the BLM.

I. Background

Asarco owns and operates the Ray Mine complex in Gila and Pinal Counties, Arizona. The complex now includes a 265,000 ton-per-day open pit copper mine, a copper smelter with an acid plant, solution extraction/electrowinning plants, mills, con[637]*637centrators, leaching systems, and related support facilities. Ore from the mine is transported eighteen miles to the Hayden Smelter for processing. In 1996, the complex produced 430 million pounds of copper anodes, over 70 million pounds of copper cathodes, 1.3 million ounces of silver in concentrate, and 623,000 tons of sulfuric acid. The Ray Mine is the second most productive copper mine in Arizona and the third most productive copper mine in the United States.

In 1994, Asarco proposed a land exchange with the BLM that would consolidate its holdings and expand its mining operations at the complex. As amended in 1997, the proposed land exchange would convey to Asarco in fee simple thirty-one parcels of public land totaling 10,976 acres (the “selected lands”). In return, Asarco would convey to the BLM eighteen parcels of private land totaling roughly 7,300 acres (the “offered lands”). FLPMA authorizes the Secretary of Interior to approve land exchanges. 43 U.S.C. § 1716.

The United States owns, and the BLM administers as full estates, 8,196 acres of the selected lands. The remaining 2,780 acres of the selected lands are owned and administered as “split estates.” Asarco owns or is purchasing, in transactions not at issue in this appeal, the surface estate of these lands, while the United States owns and the BLM administers the mineral estate. Twenty-three of the thirty-one parcels of selected lands are located near the Ray Mine and the community of Ray, Arizona. Five of the parcels are located twelve to fifteen miles southeast of the Ray Mine, near the communities of Hayden and Winkleman, Arizona. The remaining three parcels are located about 50 miles west of the Ray Mine near the community of Casa Grande, Arizona.

The selected lands provide important wildlife and plant habitat, including high priority reintroduction habitat for desert bighorn sheep, 6,860 acres of endangered desert tortoise habitat, and potential habitat for threatened and endangered birds. Upland plant communities cover 99.2% of the selected lands and include riparian plant communities and three plant species designated for special status by the BLM. Some of the selected lands are immediately adjacent to the White Canyon Area of Critical Environmental Concern, and some are adjacent to or in close proximity to the White Canyon Wilderness. The selected lands include seventy-eight archaeological sites, of which forty are regarded as eligible for nomination to the National Register of Historic Places.

The selected lands are now encumbered by 751 mining claims or mill site claims under the Mining Law of 1872, of which 747 are held by Asarco. These claims are unpatented, and the BLM has not determined if they are valid. Every parcel of the selected lands except for Parcel CH-5 (comprising 480 acres) is encumbered by at least one such claim.

Asarco and the BLM are forthright in stating that they foresee the following five mining and mining-related uses for the selected lands following the land exchange. These uses are described, with specified acreage, in the FEIS as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
623 F.3d 633, 72 ERC (BNA) 1064, 2010 U.S. App. LEXIS 19767, 2010 WL 3704200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/center-for-biological-diversity-v-united-states-department-of-the-interior-ca9-2010.