CEI Enterprises, Inc. v. Professional Coating Technologies, Inc

CourtDistrict Court, D. New Mexico
DecidedSeptember 29, 2023
Docket1:21-cv-01212
StatusUnknown

This text of CEI Enterprises, Inc. v. Professional Coating Technologies, Inc (CEI Enterprises, Inc. v. Professional Coating Technologies, Inc) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CEI Enterprises, Inc. v. Professional Coating Technologies, Inc, (D.N.M. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW MEXICO ____________________

CEI ENTERPRISES, INC.,

Plaintiff, Case No. 1:21-cv-01212-MLG-LF v.

PROFESSIONAL COATING TECHNOLOGIES, INC. and MARK WINKELMAN,

Defendants.

MEMORANDUM OPINION AND ORDER DENYING DEFENDANTS’ MOTION FOR LEAVE TO FILE FIRST AMENDED ANSWER AND COUNTERCLAIM

This matter comes before the Court on a Motion for Leave to File First Amended Answer and Counterclaim filed by Defendants Professional Coating Technologies, Inc., and Mark Winkelman (collectively, “PCT”) on October 14, 2022. Doc. 79. Plaintiff CEI Enterprises, Inc. (“CEI”) filed a response (Doc. 93), to which PCT replied. Doc. 95. Having reviewed the parties’ submissions and the applicable law, the Court denies the motion. BACKGROUND This suit arises from an alleged breach of contract. CEI manufactured asphalt-rubber blending plants and related equipment and parts. Doc. 1 ¶ 7. PCT produces asphalt emulsions used in road building to coat water pipes. Id. ¶ 8. Winkelman is PCT’s chief executive officer. Id. Sometime between 2017 and 2018, CEI and PCT entered into a contract stipulating that CEI would build a “complete system” to be used in manufacturing PCT’s products in order to “automate its facility to significantly increase production and sales.” Doc. 79 at 2. The complete system consisted of two phases: (1) the installation of large tanks and related equipment and (2) the design, construction and installation of an automation system that would work with those tanks. Doc. 13 at 3. In PCT’s view, “those tanks [were] useless without completion of the second phase of the project,” and that, due to personnel changes at CEI, “very little work” was done on the project throughout 2018. Id. at 3, 4. Ultimately, PCT alleges that “the system is not complete, does not work, and never has worked.” Doc. 79 at 2.

On January 22, 2019, the parties executed a Secured Promissory Note (“Note”) and Guaranty. Doc. 1-1. PCT alleges that it executed the Note as confirmation of the remaining balance on the contract and its intention to pay that balance in exchange for CEI’s completion of the work. Doc. 13 at 5. By contrast, CEI claims that the Note was executed because “PCT experienced alleged difficulties paying for the [system] and requested CEI’s assistance in working out a formal payment schedule.” Doc. 1 at 2. At any rate, the parties executed the Note which reflected PCT’s payment obligation to CEI in connection with the sale of the complete system, namely, a principal sum of $1,071,453.75 plus interest and an estimated balance of $678,742.44. Doc. 1 at 3; Doc. 1- 1 at 1. Winkelman signed the Guaranty, which served as material inducement for CEI to make the loan evinced in the Note. Id.

In 2020, CEI closed its operations. Doc. 79 at 2. It informed PCT that it would transfer the project to two entities affiliated with CEI: Astec Industries, Inc. (a nonparty corporation that owns CEI) and Heatec, Inc. (a nonparty corporation owned by Astec). Id. According to PCT, CEI informed the company that the Note “was being transferred to Heatec” and “directed PCT to pay monthly payments on the Note to Heatec.” Id.; see also Doc. 79-4 (Deposition of Michael Anderson, CEI President). However, CEI disputes this fact. Instead, it claims that CEI never transferred or assigned the Note or Guaranty to Heatec, Astec or any other nonparty entity.1 Doc. 93 at 10-11.

1 CEI also points to Anderson’s testimony as corroboration of this fact. Doc. 93 at 10. After PCT allegedly failed to pay the outstanding balance on the Note by the maturity date, CEI filed a complaint against PCT on December 22, 2021. Doc. 20 at 2-3; see generally Doc. 1. PCT answered on February 17, 2022, asserting various affirmative defenses and counterclaims. Doc. 13 at 2-8. Several weeks later, CEI moved to dismiss those counterclaims. Doc. 19. Then, on

October 14, 2022—months after the deadline of March 25, 2022, to amend pleadings and over one month after discovery terminated on August 29, 2022—PCT moved for leave to amend its answer and counterclaims. Doc. 18 at 2-3; see generally Doc. 79. Based on what it sees as new information revealed during and after discovery, PCT seeks to add defenses and a counterclaim including standing, waiver by assignment/equitable assignment, waiver by estoppel, and intentional misrepresentation. Doc. 79 at 1. DISCUSSION If the deadline for amendments set in the scheduling order has passed, a party may only amend her complaint if she demonstrates both good cause for seeking modification under Federal Rule of Civil Procedure 16(b)(4) and satisfies the Federal Rule of Civil Procedure 15(a) standard.

Gorsuch, Ltd., B.C. v. Wells Fargo Nat’l Bank Ass’n, 771 F.3d 1230, 1240 (10th Cir. 2014). Therefore, in order for PCT to amend its answer, it must satisfy both the Rule 16 and 15 standards.2 I. PCT has not demonstrated good cause under Rule 16(b)(4). Rule 16(b)(4) provides that the Court may modify a scheduling order “only for good cause and with the judge’s consent.” This standard “requires the movant to show the scheduling deadlines cannot be met despite the movant’s diligent efforts.” See Gorsuch, Ltd., B.C., 771 F.3d

2 Because there is a “rough similarity” between the “good cause” standard of Rule 16 and the “undue delay” standard of Rule 15, see Bylin v. Billings, 568 F.3d 1224, 1231 (10th Cir. 2009), the analysis of the two standards overlaps. Moreover, if PCT cannot demonstrate good cause under Rule 16, there is no need to analyze Rule 15. Regardless, the Court offers an analysis under both rules. at 1240 (internal quotation marks and brackets omitted). “This . . . means it must provide an adequate explanation for any delay.” Minter v. Prime Equip. Co., 451 F.3d 1196, 1214 n.4 (10th Cir. 2006). For example, an adequate explanation exists where “a [party] learns new information through discovery or if the underlying law has changed.”3 Gorsuch, Ltd., B.C., 771 F.3d at 1240;

see also March v. Raabe, No. 21-cv-00921-MLG-KK, 2023 WL 3092881, at *3 (D.N.M. Apr. 26, 2023) (granting motion for leave to amend where the plaintiff demonstrated diligence in seeking to amend the complaint with new evidence uncovered during discovery). By contrast, there is no adequate explanation where the movant “knew of the underlying conduct but simply failed to raise [their] claims.” Husky Ventures, Inc. v. B55 Invs., Ltd., 911 F.3d 1000, 1020 (10th Cir. 2018). District courts retain discretion to make such determinations. See Gorsuch, Ltd., B.C., 771 F.3d at 1240. In this case, PCT argues that good cause exists on two bases: (1) the “impossibility of the tight” deadline to amend which was set for two weeks after the scheduling order was issued and five months before the close of discovery and (2) the discovery of new information pertaining to

the proposed amendments. Doc. 79 at 7. CEI disagrees that good cause exists. Doc. 93 at 8-9. Instead, it asserts that PCT failed to diligently pursue discovery and that there were no “new facts” because PCT already had documents in its possession that revealed the relationships between CEI, Astec and Heatec. Id. at 9. In its reply, PCT maintains that it acted diligently and that it learned new information during discovery justifying amendment. Doc. 95 at 1-4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Gohier v. Enright
186 F.3d 1216 (Tenth Circuit, 1999)
Bradley v. Val-Mejias
379 F.3d 892 (Tenth Circuit, 2004)
Minter v. Prime Equipment Co.
451 F.3d 1196 (Tenth Circuit, 2006)
Bylin v. Billings
568 F.3d 1224 (Tenth Circuit, 2009)
Cohen v. Longshore
621 F.3d 1311 (Tenth Circuit, 2010)
Childs v. UNIFIED LIFE INSURANCE COMPANY
781 F. Supp. 2d 1240 (N.D. Oklahoma, 2011)
Jenkins Subway, Inc. v. Jones
990 S.W.2d 713 (Court of Appeals of Tennessee, 1998)
J.R. Hale Contracting Co. v. United New Mexico Bank
799 P.2d 581 (New Mexico Supreme Court, 1990)
Husky Ventures, Inc. v. B55 Invs., Ltd.
911 F.3d 1000 (Tenth Circuit, 2018)
Nowell v. Medtronic Inc.
372 F. Supp. 3d 1166 (D. New Mexico, 2019)
Collins v. Wal-Mart, Inc.
245 F.R.D. 503 (D. Kansas, 2007)
Wagner Equipment Co. v. Wood
289 F.R.D. 347 (D. New Mexico, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
CEI Enterprises, Inc. v. Professional Coating Technologies, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cei-enterprises-inc-v-professional-coating-technologies-inc-nmd-2023.