CDC San Francisco v. Critchfield Mechanical CA1/2

CourtCalifornia Court of Appeal
DecidedJanuary 9, 2025
DocketA168357
StatusUnpublished

This text of CDC San Francisco v. Critchfield Mechanical CA1/2 (CDC San Francisco v. Critchfield Mechanical CA1/2) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CDC San Francisco v. Critchfield Mechanical CA1/2, (Cal. Ct. App. 2025).

Opinion

Filed 1/9/25 CDC San Francisco v. Critchfield Mechanical CA1/2 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION TWO

CDC SAN FRANCISCO, LLC, Plaintiff and Appellant, A168357 v. CRITCHFIELD MECHANICAL (San Francisco County Super. INC., Ct. No. CGC-18-563971) Defendant and Respondent.

After prevailing at trial against defendant Critchfield Mechanical Inc. (Critchfield), plaintiff CDC San Francisco, LLC (CDC) sought over $9 million in prejudgment interest. The trial court denied the motion, based in part on its finding that “the amount of damages was in serious dispute,” and thus damages were not certain or capable of being made certain by calculation. We affirm. BACKGROUND CDC owns the InterContinental San Francisco Hotel, a 33-story, high- rise hotel located in San Francisco, California. Critchfield is a heating ventilation and air conditioning (HVAC) contractor that installed the hotel’s HVAC system. The hotel’s HVAC system “consists of several different systems,” including a four-pipe fan coil system for heating and cooling guestrooms. The

1 guestrooms are equipped with a visible “fan coil unit” that controls the temperature using water from chillers and boilers at the roof level. The water is transported through a vertically oriented system of piping called “risers” that connect the fan coil units in the guestrooms with the chillers and boilers on the roof. At some point after installation, CDC discovered a water leak in the hot water supply risers on the 21st floor of the hotel, which CDC later found impacted the 21st and 22nd floors of the hotel, causing several guestrooms to be removed from service. CDC operations personnel subsequently learned the water leak was “considerable and extensive, spanning multiple floors and damaging other aspects” of the hotel’s infrastructure. Thus, on January 30, 2018, CDC sued Critchfield for breach of contract and negligence, alleging Critchfield failed to properly design and construct the hotel’s HVAC system. The defective HVAC system allegedly caused damage to the hotel’s framing, shear walls, drywall, paint, flooring, and piping, although CDC’s “investigation of the latent defects” was ongoing. In January 2023, the action proceeded to a jury trial, which “lasted for over six weeks, spanned 26 witnesses, including about 19 expert witnesses.” CDC’s expert, James Howard, proposed a “full horizontal replacement” of the risers, costing $24,570,800, plus “other costs” of $2,830,315, for a total of $27,401,115. On the other hand, Critchfield’s experts testified to different remediation plans, including a “full vertical replacement” estimated by William Ivey to cost $15,655,991, and another by Jeff Harris to cost $15,532,232.89. Alternatively, Critchfield expert John Littrell proposed a “band-aid repair” for $5,019,547, which would fix only “the two hot water

2 risers, but not the two chilled water risers or the fan coil units in each room.” The estimates of CDC’s future lost profits ranged from $0 to $2,257,086. The jury returned a verdict for CDC, awarding past economic damages of $457,000 and future economic damages of $17,913,077 for a total award of $18,370,077.1 The court reduced the award to $17,370,077 based on CDC’s settlements with other parties and entered judgment on April 17, 2023. CDC then moved for prejudgment interest pursuant to Civil Code section 3287 (section 3287),2 seeking “interest at the rate of 10% per annum from January 30, 2018 through April 17, 2023, on actual damages awarded in the amount of $17,370,077.00, for a total of $9,056,243.79.” CDC argued that damages were “certain,” within the meaning of section 3287, subdivision (a) (section 3287(a)), because Critchfield “has long been in the business of estimating construction costs” and thus “could calculate” the dollar value of labor and materials needed to replace the HVAC system. CDC also pointed to its November 8, 2018 demand for $16 million, which represented “the dollar value of the labor and materials needed to replace the system”; an April 30, 2020 document production to Critchfield containing “bids, plans, prior repair invoices, estimates, testing information, leak charts, occupancy reports, and CDC’s P&Ls”; a June 16, 2020 “full-day

1 CDC asserts that the jury must have “accepted” Critchfield’s

estimates because $15,655,991 (Critchfield’s estimated cost of repair) plus $2,257,086 (future lost profits) equals $17,913,077, which is what the jury awarded in future damages. 2 Below, CDC sought interest pursuant to section 3287, subdivision (a),

which provides for mandatory prejudgment interest on liquidated claims, and subdivision (b), which provides for discretionary prejudgment interest on unliquidated contract claims. (North Oakland Medical Clinic v. Rogers (1998) 65 Cal.App.4th 824, 828–829.) On appeal, CDC argues entitlement to prejudgment interest pursuant to subdivision (a) only, so we do not address discretionary interest in this opinion.

3 presentation” which included “a detailed estimate summary of costs to replace the defective HVAC system”; and the trial testimony by Critchfield’s experts, who “calculated the cost to replace the defective HVAC system at $15,532,232.89 and $15,655,991, respectively,” plus an additional amount for lost profits. In opposition, Critchfield argued the parties disputed “the nature, extent and computation of [CDC’s] alleged damages” throughout the litigation. Thus, according to Critchfield, “the amount of damages was not only in serious dispute but . . . the dispute could not be resolved except by verdict or judgment,” making damages uncertain and not amenable to an award of prejudgment interest pursuant to section 3287(a). On reply, CDC asserted that Critchfield’s dispute concerned “the scope” of repairs, which “does not mean that the dollar amount of the repair is incapable of calculation.” “What is relevant,” CDC argued, “is that the varying options [for repair or replacement of the HVAC systems] were calculated or could be calculated.” The court ultimately denied CDC’s motion for prejudgment interest, explaining that “the amount of damages was in serious dispute” and the jury’s award “was roughly $16 million less than the amount [CDC] sought to prove at the commencement of trial.” CDC timely appealed. DISCUSSION Section 3287(a) provides, in relevant part, “A person who is entitled to recover damages certain, or capable of being made certain by calculation, and the right to recover which is vested in the person upon a particular day, is entitled also to recover interest thereon from that day. . . .” To recover prejudgment interest under section 3287(a), there are two relevant

4 requirements: certainty and vesting. (See Chesapeake Industries, Inc. v. Togova Enterprises, Inc. (1983) 149 Cal.App.3d 901, 906 (Chesapeake); Leff v. Gunter (1983) 33 Cal.3d 508, 520 [noting “the additional requirement for prejudgment interest under section 3287 that plaintiff’s entitlement to damages vest ‘upon a particular day’ ”].) If the requirements are satisfied, then “the trial court has no discretion—it must award prejudgment interest from the first day there exists both a breach and a liquidated claim.” (Watson Bowman Acme Corp. v. RGW Construction, Inc. (2016) 2 Cal.App.5th 279, 293 (Watson).) “California cases uniformly have interpreted the ‘vesting’ requirement as being satisfied at the time that the amount of damages become certain or capable of being made certain, not the time liability to pay those amounts is determined.” (Evanston Ins. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leff v. Gunter
658 P.2d 740 (California Supreme Court, 1983)
Coleman Engineering Co. v. North American Aviation, Inc.
420 P.2d 713 (California Supreme Court, 1966)
Evanston Insurance v. OEA, Inc.
566 F.3d 915 (Ninth Circuit, 2009)
Levy-Zentner Co. v. SOUTHERN PAC. TRANSPORTATION
74 Cal. App. 3d 762 (California Court of Appeal, 1977)
Polster, Inc. v. Swing
164 Cal. App. 3d 427 (California Court of Appeal, 1985)
Hartford Accident & Indemnity Co. v. Sequoia Insurance
211 Cal. App. 3d 1285 (California Court of Appeal, 1989)
Chesapeake Industries, Inc. v. Togova Entreprises, Inc.
149 Cal. App. 3d 901 (California Court of Appeal, 1983)
Overholser v. Glynn
267 Cal. App. 2d 800 (California Court of Appeal, 1968)
Kgm Harvesting Co. v. Fresth Network
36 Cal. App. 4th 376 (California Court of Appeal, 1995)
Children's Hospital & Medical Center v. Bonta
118 Cal. Rptr. 2d 629 (California Court of Appeal, 2002)
Watson Bowman Acme Corp. v. RGW Construction, Inc.
2 Cal. App. 5th 279 (California Court of Appeal, 2016)
North Oakland Medical Clinic v. Rogers
65 Cal. App. 4th 824 (California Court of Appeal, 1998)
Collins v. City of Los Angeles
205 Cal. App. 4th 140 (California Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
CDC San Francisco v. Critchfield Mechanical CA1/2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cdc-san-francisco-v-critchfield-mechanical-ca12-calctapp-2025.