CBRE Heery, Inc.

CourtArmed Services Board of Contract Appeals
DecidedSeptember 15, 2021
DocketASBCA No. 62420
StatusPublished

This text of CBRE Heery, Inc. (CBRE Heery, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CBRE Heery, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) CBRE Heery, Inc. ) ASBCA No. 62420 ) Under Contract No. W9126G-08-D-0056 )

APPEARANCES FOR THE APPELLANT: Heather F. Shore, Esq. Brown & Ruprecht PC Kansas City, MO

Wade Purcell, Esq. Counsel

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Engineer Trial Attorney U.S. Army Engineer District, Savannah

OPINION BY ADMINISTRATIVE JUDGE SWEET

This appeal involves a contract to design and build a replacement medical clinic at Seymour Johnson Air Force Base. Appellant CBRE Heery, Inc. (Heery) 1 did not complete the project on time, and the Army Corps of Engineers (Corps) imposed liquidated damages. Heery filed a claim, seeking recovery of its increased costs and remission of the liquidated damages due to government-caused delay. The contracting officer (CO) issued a final decision (COFD) denying the claim.

On appeal, the parties have elected to proceed under Board Rule 11. Heery argues that the Corps’ direction to strengthen the door and walls of a room in the Medical Logistics Department after Heery already had installed the door and walls constituted a constructive change, and breached the government’s duty of good faith and fair dealing. The government responds that the contract documents required the room’s door and walls to be strengthened because the contract documents mandated that: (1) the room be a

1 Heery International, Inc. signed the contract documents (R4, tab 3.01 at 113, tab 3.06 at 2210-11). On December 15, 2017, CBRE Heery, Inc. entered into a change of name agreement with the government, amending the contract documents to substitute Heery International, Inc. with CBRE Heery, Inc. (R4, tab 2.03) For ease of reference, we refer to both entities as “Heery.” vault for the storage of controlled substances; and (2) Heery comply with applicable codes, criteria, and standards, which required that vaults for the storage of controlled substances have strengthened doors and walls. For the reasons discussed below, we agree with the government, and conclude that there was no constructive change or breach of the duty of good faith and fair dealing. As a result, we deny the appeal. 2

FINDINGS OF FACT

I. Contract Documents

A. MATOC Contract

1. On September 19, 2008, the Corps awarded Multiple Award Task Order Contact W9126G-08-D-0056 (MATOC Contract) for the United States Air Force (Air Force; collectively with the Corps, government) medical design construction services for federal healthcare facilities to Heery (R4, tab 3.01 at 111-13).

2. The MATOC Contract incorporated by reference Federal Acquisition Regulation (FAR) clause 52.243-4, CHANGES (JUN 2007), which provided that Heery is entitled to an equitable adjustment for any changes that increase its costs of, or time required for, performance (R4, tab 3.01 at 150).

3. The MATOC Contract also included a RESPONSIBILITY OF THE CONTRACTOR FOR DESIGN (MAY 2002) Clause, which provided that:

(a) The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other non-construction services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other non-construction services and perform any necessary rework or modifications . . . resulting from the design error or omission.

(b) The standard of care for all design services performed under this agreement shall be the care and skill ordinarily used by members of the architectural or engineering professions practicing under similar conditions at the same time and locality. Notwithstanding the above, in the event that the contract specifies that portions of the Work be

2 Because we find for the government on entitlement, we do not address the alleged number of days of delay or quantum, and deny the government’s motion to strike. 2 performed in accordance with a performance standard, the design services shall be performed so as to achieve such standards.

(c) Neither the Government’s review, approval or acceptance of, nor payment for, the services required under this contract shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of the contract.

(R4, tab 3.01 at 176-77) 3

B. 0039 RFP

4. On November 30, 2012, the government issued Request for Proposal No. W912HN-12-R-0039 (0039 RFP) against the MATOC Contract for the design and construction of a replacement medical clinic at Seymour Johnson Air Force Base in North Carolina (R4, tab 3.02 at 352-54). The 0039 RFP included an order of precedence clause, which indicated that codes, criteria, and standards took precedence over the program for design (PFD), which took precedence over the drawings (R4, tab 3.02 at 271-72).

5. First in order of precedence, the 0039 RFP included a list of codes, criteria, and standards with which a contractor had to comply. Among the enumerated codes, criteria, and standards was United Facilities Criteria (UFC) 4-510-01 (Design: Medical Military Facilities) (R4, tab 3.02 at 1485). UFC 4-510-01 assigned a “Secure Storage, Cage” the room code “SSC01,” and a “Secure Storage, Vault,” the room code “SSV01” (R4, tab G-37 at 348). For a Secure Storage, Vault (SSV01), the doors and walls had to be “[s]pecial. Determined by the Design and Construction Agent in coordination with the Using Military Department” (id. at 320-22, 348).

6. The parties treat Army Regulation (AR) 190-51 as the government’s special determination, agreeing that Heery had to comply with AR 190-51 (app. br. at 8; gov’t br. at 28). AR 190-51, Appendix B-3 addressed vaults for the storage of controlled substances in particular. It required new doors for all risk levels 4 be “Class 5 vault doors [or to] . . . provide delay equal to or greater than the response time,” which we refer to as

3 We use the Bates numbers, where available. 4 Neither AR 190-51, nor the parties, define the risk levels. In any event, as discussed below, Heery’s 100 percent corrected final design and the original door and walls it installed in Room 1919 did not meet AR 190-51, Appendix B-3’s requirements for any risk level. 3 class 5 or similar doors. 5 (R4, tab 7.03 at 12626) AR 190-51, Appendix B-3 also required walls for risk levels I and II to:

[B]e constructed of a minimum of 8-inch-thick concrete reinforced vertically and horizontally on each face with ½ inch diameter reinforcing bars placed 9 inches on center and staggered to form a grid approximately 4 ½-inches square or with 8-inch thick reinforced concrete masonry with ½-inch diameter reinforcing bars placed at 8 inches on center in block cells filled with grout or mortar and with horizontal joint reinforcement at every course. Alternatively, walls may be constructed to provide delay equal to or greater than the response time.

(Id.) Walls for risk level III only could have the reinforced concrete option enunciated for risk levels I and II (id.).

7. UFC 4-510-01 also stated that “[f]eatures to be considered for vault storage areas are outlined in 21 CFR 1301.72” (R4, tab G-37 at 237). Under 28 C.F.R. § 1301

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
James T. Hannon v. Department of Justice
234 F.3d 674 (Federal Circuit, 2000)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Moore v. Los Angeles Iron & Steel Co.
89 F. 73 (U.S. Circuit Court for the District of Southern California, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
CBRE Heery, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cbre-heery-inc-asbca-2021.