Cb&i Areva Mox Services, LLC v. United States

United States Court of Federal Claims·Decided July 30, 2018·No. 16-950·Published

Opinion

In the United States Court of Federal Claims No. 16-950C, 17-2017C, 18-80C, 18-522C, 18-677C, 18-691C, 18-921C (consolidated)

(Filed: July 30, 2018)1

*************************************

*

CB&I AREVA MOX SERVICES, LLC, * * US/Russia Plutonium Management and Plaintiff, * Disposition Agreement; National Nuclear * Security Administration; Cost-Plus-Fee v. * Construction Contract; Rules 12 and 56 * Cross-Motions; Availability of Declaratory THE UNITED STATES, * Relief; Government Claim Under Contract * Disputes Act; Statute of Limitations.

Defendant. *

*

*************************************

Mark J. Linderman, with whom were Dennis J. Callahan and Stephen L. Bacon, Rogers Joseph O’Donnell, PC, San Francisco, California for Plaintiff.

Joseph E. Ashman, Senior Trial Counsel, with whom were P. Davis Oliver and Anthony Schiavetti, Trial Attorneys, and Chad A. Readler, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Allison Kidd-Miller, Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C. for Defendant.

AMENDED OPINION AND ORDER

WHEELER, Judge.

Plaintiff CB&I AREVA MOX Services, LLC (“MOX Services”) commenced this action on August 5, 2016. The action arises from MOX Services’ cost reimbursement contract with the Department of Energy, National Nuclear Security Administration (“NNSA”) to construct a Mixed Oxide Fuel Fabrication Facility at the Department of Energy’s Savannah River Site, near Aiken, South Carolina. On November 3, 2017, with 1 The Court issued this decision on June 11, 2018. On July 6, 2018, Defendant filed a motion for partial reconsideration concerning a portion of the decision. The Court granted this motion on July 30, 2018. Thus, the Court reissues the opinion, with relevant changes, in full.

the Court’s approval, MOX Services filed a Supplemental Complaint for Damages and Declaratory Relief consisting of five counts: (1) Breach of Contract (Incentive Fee); (2) Declaratory Relief (Premature Claw Back of Provisional Incentive Fee); (3) Breach of Contract (Fixed Fee On Out-of-Scope Work and for the Realization of Risks NNSA Assumed); (4) Breach of Contract (Request for Equitable Adjustment Preparation Costs); and (5) Declaratory Relief (Request for Equitable Adjustment Preparation Costs).

This case, docket no. 16-950C, was the first in a series of actions that MOX Services filed under the same contract. The cases were filed separately in this Court because of individual claims that MOX Services had submitted to the contracting officer, and because of the NNSA’s issuance of individual contracting officer final decisions. On May 15, 2018, the Court ordered the consolidation of these cases for further proceedings and trial.

The present controversy concerns cross-motions that the parties filed under Rules 12 and 56 of the Court. On December 27, 2017, MOX Services filed a motion for partial summary judgment regarding Counts II and V (the declaratory relief counts) of the Supplemental Complaint. MOX Services contends that Count II presents a pure question of contract interpretation on whether the NNSA prematurely clawed back $21.6 million of cost/schedule incentive fee payments it had made to MOX Services. Similarly, MOX Services contends that Count V presents a question of regulatory interpretation on whether the attorneys’ fees and other professional consultant costs claimed by MOX Services for reimbursement as contract administration costs in investigating and preparing a Request for Equitable Adjustment (“REA”) constitute “legal costs” that must comply with the requirements of 10 C.F.R. Part 719 (2013).2

On February 1, 2018, Defendant filed a motion for partial dismissal regarding Counts II, III, and V of the Supplemental Complaint. Defendant argues that Counts II and V should be dismissed for lack of jurisdiction because they were not presented to the contracting officer, they do not present a case or controversy and are not ripe, and because declaratory relief may not be granted when money damages are adequate. Defendant also moved for partial dismissal of Count III because MOX Services failed to provide required contractual notice of the claim, and because the claim allegedly is time barred by the Contract Disputes Act’s six-year statute of limitations, 41 U.S.C. § 7103(a)(4) (2011).

On March 28, 2018, Defendant filed a response to MOX Services’ motion for partial summary judgment, and purported to cross-move for partial summary judgment in its favor. However, as MOX Services notes, Defendant’s “cross-motion” essentially was only a response, and not a cross-motion, to the arguments advanced by MOX Services. MOX

2 10 C.F.R. Part 719, entitled “Contractor Legal Management Requirements,” calls for Department of Energy contractors to submit detailed information to the agency whenever a contractor retains a law firm or individual attorney as outside counsel. Payment of law firm invoices by the agency is subject to contractor compliance with these requirements.

Services, with some justification, objected to Defendant’s filing of the final reply brief through the use of a “cross-motion.” The Court nevertheless has accepted all of the briefs submitted by the parties, concluding that Defendant did not obtain any advantage by filing the final brief.

The parties completed their briefing by April 25, 2018. The Court heard oral argument on the motions on May 17, 2018. For the reasons explained below, the Court GRANTS MOX Services’ motion for partial summary judgment on Counts II and V, and DENIES Defendant’s motion to dismiss Counts II, III, and V, and DENIES Defendant’s cross-motion for partial summary judgment.

Factual Background3

On March 22, 1999, the NNSA awarded Contract No. DE-AC02-99CH10888 to MOX Services’ predecessor in interest, Duke Cogema, Stone & Webster, LLC. The Mixed Oxide Fuel Fabrication Facility (“MFFF”) is intended to transform weapons-grade plutonium into mixed oxide fuel rods that may be used in commercial nuclear power plants. The MFFF represents the United States’ performance of its obligations under the Plutonium Management and Disposition Agreement (“PMDA”) between the United States and Russia. Under the PMDA, the United States and Russia agreed to dispose of 34 metric tons of weapons-grade plutonium roughly in parallel.

Construction of the MFFF is a considerable undertaking, and when built will constitute one of the largest and most complex fabrication facilities in the world. According to MOX Services, the main physical plant will require over 4.5 million cubic feet of concrete and 70 million pounds of reinforced steel. The hundreds of process units and other equipment to be installed in the plant, many of which include conveyors and lifts and are sealed within hardened glove boxes, are being fabricated by specialty manufacturers in the United States and around the world at great expense. The controls and utilities that join the building to the equipment will require, among other utility delivery channels, over 80 miles of piping, nearly 1,300 miles of cabling, and over 1.3 million pounds of HVAC ducts. As a nuclear construction project where contractors will be working with weapons-grade plutonium and uranium oxide, the operations are governed by the regulations of the Nuclear Regulatory Commission.

The contract consists of a base contract for the design of the MFFF and three options: Option 1 is for construction of the MFFF (including fabrication and installation of

3 The facts below are taken from MOX Services’ Supplemental Complaint, and are assumed to be true for purposes of Defendant’s motion for partial dismissal. See Bell Atl. Corp. v. Twombly, 550 U.S. 544, 572 (2007); Scheuer v. Rhodes, 416 U.S. 232, 236–37 (1974). The Court also is satisfied that the declaratory relief counts of MOX Services’ Supplemental Complaint (Counts II and V) present legal questions of contract and regulatory interpretation, and that no material fact issues exist.

Free access — add to your briefcase to read the full text and ask questions with AI

Cb&i Areva Mox Services, LLC v. United States, (uscfc 2018).

Cb&i Areva Mox Services, LLC v. United States (Cb&i Areva Mox Services, LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McNutt v. General Motors Acceptance Corp.
298 U.S. 178 (Supreme Court, 1936)
Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Colonel David W. Palmer, II v. United States
168 F.3d 1310 (Federal Circuit, 1999)
Wallace Forman v. United States
329 F.3d 837 (Federal Circuit, 2003)