Cartograf USA, Inc. v. Choate Construction Company

CourtDistrict Court, E.D. Virginia
DecidedApril 7, 2023
Docket3:22-cv-00632
StatusUnknown

This text of Cartograf USA, Inc. v. Choate Construction Company (Cartograf USA, Inc. v. Choate Construction Company) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cartograf USA, Inc. v. Choate Construction Company, (E.D. Va. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Richmond Division CARTOGRAF USA, INC., ) ) ) Petitioner, ) v. ) Civil Action No. 3:22-cv-632—HEH ) CHOATE CONSTRUCTION ) COMPANY, ) ) Respondent. ) MEMORANDUM OPINION (Granting Motion to Dismiss and Closing Case) This matter is before the Court on Respondent Choate Construction Company’s (“Choate”) Motion to Dismiss (the “Motion,” ECF No. 9), filed on October 17, 2022. Choate moves the Court to dismiss Petitioner Cartograf USA, Inc.’s (“Cartograf”) Petition to Vacate Interim and Final Arbitration Awards (the “Petition”). (ECF No. 1.) In Cartograf’s Petition, Cartograf argues that this Court should vacate the Interim and Final Arbitration Awards (collectively, the “Arbitration Award”) issued by the three- member Tribunal of the American Arbitration Association (the “Tribunal”) because the Tribunal exceeded its authority and jurisdiction to arbitrate Phases 2 and 3 of Cartograf’s Construction Contract with Choate. (Pet. J 32-34.) Choate, the prevailing party in the arbitration, seeks to dismiss Cartograf’s Petition for lack of subject matter jurisdiction and for failure to state a claim upon which relief

can be granted. (Mot. at 5-6.) In addition, because the same issues have been fully litigated and are pending final judgment in Chesterfield County Circuit Court (the

“Circuit Court”), Choate argues that this Court should abstain from exercising its jurisdiction under the Colorado River doctrine. (Id. at 8 (citing Colorado River Water Conservation Dist. v. United States, 424 U.S. 800, 817 (1976)).) The parties have filed memoranda supporting their respective positions. On February 28, 2023, the Court heard oral argument. For the reasons discussed below, the Court will grant Choate’s Motion to Dismiss on abstention grounds. I. BACKGROUND Cartograf is a United States subsidiary of Cartograf S.A. de C.V., a Mexican

company that manufactures cardboard packages. (Pet. | 6.) On October 11, 2019, Cartograf and Choate entered into a written agreement (the “Construction Contract”) outlining three phases of construction for a manufacturing facility in which Choate would

serve as a general contractor. (/d. J 12-13.) The Construction Contract did not specify terms of construction for Phases 2 and 3. (/d. 4 13.) It required the parties to complete a change order! if or when (1) either party determined that Choate must perform additional work needed for Phase 1, or (2) the parties decided to include Phases 2 and 3 into the Construction Contract. (Ud. J 13.) From October 2019 to March 2020, Choate oversaw construction on Phase 1 “and both parties generally complied with their contractual obligations.” (Ud. J 16.) However, in March 2020, Cartograf began to face financial difficulties and “fell behind in its

! “The Construction Contract defines ‘Change Order’ as ‘a written instrument prepared by the Architect and signed by the Owner [Cartograf], Contractor [Choate] and Architect stating their agreement upon’ the additional work to be performed and any adjustments to the Contract Price or construction schedule.” (Pet. | 13 (quoting Constr Contract § 7.2).)

payments to Choate.” (/d.) In May 2020, Cartograf’s Chief Executive Officer, Juan Paramo, met with Choate representatives and expressed “surprise” that the construction of the facility’s roof and south wall remained incomplete. (/d. {J 18-19.) He orally instructed Choate to proceed with the work. (/d.) During the arbitration proceedings, Mr. Paramo “testified that he believed Choate was already obligated to undertake this work within Phase 1 and at no additional cost beyond the contract price.” (/d. J 19.) Choate, however, maintained that the roof and south wall construction constituted additional work outside of Phase 1 (“Purported Additional Work”). (/d.) Neither party ever executed a change order incorporating the Purported Additional Work. (/d.) Nevertheless, Choate performed the Purported Additional Work, as requested by Mr. Paramo. (d. { 20.) On June 4, 2020, Choate informed Cartograf in writing of its intent to stop working on the project due to Cartograf’s failure to make payments. (/d. 21.) Choate, however, continued working on the Purported Additional Work and sent a proposed change order to Cartograf, which neither party ever signed. (/d. 22.) On July 17, 2020, Choate advised Cartograf in writing that it would cease all construction work on the project, and on November 10, 2020, Choate notified Cartograf of its intent to terminate the Construction Contract. Ud. J] 23—24.) Shortly thereafter, Choate filed a lawsuit in the Circuit Court, raising three counts against Cartograf: (1) enforcement of mechanics liens, (2) breach of contract, and, in the alternative, (3) quantum meruit and unjust enrichment under Virginia law. (/d. 424.) On

December 7, 2020, Cartograf filed an answer and motion to stay the dispute pending mediation and arbitration. (Resp’t’s Mem. in Supp. at 2, ECF No. 10 (citing Ex. A to Resp’t’s Mot. to Dismiss, ECF No. 10-1).) Cartograf’s filing included an alternative Motion to Compel Mediation and Arbitration. (/d.) In addition to suing Cartograf, Choate named six defendants as interested parties due to their respective and separate mechanics liens on the property. (/d.) On March 10, 2021, the Circuit Court entered an order titled “Order Granting Motion to Stay,” which inter alia, stayed the matter “pending completion of the mediation and arbitration.” (Ex. G to Resp’t’s Mem. in Supp., ECF No. 10-7.) Cartograf’s counsel signed the Order as “Seen and Agreed.” (/d.) The parties conducted arbitration proceedings administered by the American Arbitration Association as was required by the arbitration provision in the parties’ Construction Contract. (Resp’t’s Mem. in Supp. at 3.) Choate filed its Statement of Claims against Cartograf and Choate filed its Statement of Defenses. (/d.) The parties now disagree as to whether Cartograf objected to the Tribunal’s jurisdiction. Cartograf maintains that “[i]n both its pre-hearing and post-hearing briefs, [it] repeated its position

2 Section 6.2 of the Construction Contract states: “(I]f the parties have selected arbitration as the method for binding dispute resolution in the Agreement, any Claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement.” (Ex. 4 to Pet. at 26, ECF No. 1-4.)

that the Tribunal lacked jurisdiction to hear claims relating to the Purported Additional Work[.]” (Pet. | 29.) Whereas Choate contends that “[n]Jotably, Cartograf’s Statement of Defenses argues that the construction at issue fell outside the scope of the contract . . . [but] did not, however, object to the jurisdiction of the Arbitrator.” (Resp’t’s Mot. to Dismiss at 3.) On February 25, 2022, Cartograf moved the Tribunal to issue “an order estopping [Choate] from asserting claims for construction work that Choate concedes was not part of Phase I work under the Construction Contract.” (Pet. § 28 (quoting Ex. 9 to Pet., ECF No. 1-9).) Before the Tribunal, Cartograf maintained that Choate should not have performed the Purported Additional Work or work on Phases 2 or 3, and that such work is “outside the scope of this arbitration.” (/d. § 27.) Choate now argues before this Court that in Cartograf’s motion, Cartograf “essentially admitted that it was aware of Choate’s arguments about the contract when Cartograf filed its Statement of Defenses . . . but provided no explanation for its failure to raise its objection regarding the arbitrability of the claims[.]” (Resp’t’s Mem. in Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Cartograf USA, Inc. v. Choate Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cartograf-usa-inc-v-choate-construction-company-vaed-2023.