Capobianco v. United States

394 F.2d 515, 184 Ct. Cl. 160
CourtUnited States Court of Claims
DecidedMay 10, 1968
DocketNo. 309-62
StatusPublished
Cited by2 cases

This text of 394 F.2d 515 (Capobianco v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capobianco v. United States, 394 F.2d 515, 184 Ct. Cl. 160 (cc 1968).

Opinion

Pee Cueiam:

This case was referred to Trial Commissioner C. Murray Bernhardt with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on March 7, 1968 wherein facts necessary to the opinion are stated. The case is now before the court on a joint motion of the parties, filed April 15, 1968, requesting that the court adopt the commissioner’s report filed March 7, 1968. Since the court agrees with the commissioner’s findings, opinion and recommended conclusion of law, as modified, as hereinafter set forth, it hereby adopts the same, as modified, as the basis for its judgment in this case without oral argument. Therefore, this case is suspended in this court for a reasonable period so that the case may be returned to the Department of Transportation Contract Appeals Board in accordance with the opinion, with plaintiff to advise the court at intervals of not less than 60 days beginning with the date of this opinion, of the status of the case before the Board pursuant to General Order of April 1,1968 implementing Rule 100.

Commissioner Bernhardt’s opinion, as modified by the court, is as follows:

In Roberts v. United States, 174 Ct. Cl. 940, 357 F. 2d 938 (1966), Johnson v. United States, 173 Ct. Cl. 561 (1965), and in Morgan v. United States, 298 U.S. 468 (1936) and 304 U.S. 1 (1938), the courts on judicial review were concerned with certain inadequacies in the administrative procedures accorded claimants, and with the judicial consequences of such inadequacies. These consequences ranged from a de novo court trial in the Roberts case to reversal of the agency ac[163]*163tions in the Johnson and Morgan cases. Speculation as to similar administrative shortcomings prompted the Supreme Court in United States v. Carlo Bianchi & Co., 373 U.S. 709 (1963), to comment at pp. 717, 718:

* * * There are, we believe, two answers to this contention [i.e., “that the Court of Claims has no power to remand a case such as this to the department concerned” for correction of defects or errors in the administrative proceedings]. First, there would undoubtedly be situations in which the court would be warranted, on the basis of the administrative record, in granting judgment for the contractor without the need for further administrative action. Second, in situations where the court believed that the existing record did not warrant such a course, but that the departmental determination could not be sustained under the standards laid down by Congress, we see no reason why the court could not stay its own proceedings pending some further action before the agency involved. * * * Such a stay would certainly be justified where the department had failed to make adequate provision for a record that could be subjected to judicial scrutiny. * * *

This is such a case, not only because the departmental decision is not supported by evidence which could qualify as “substantial”, but also because the record itself is in part not comprehensible and in other parts not so constituted as to breed confidence in the evidence. Because the record is equally insufficient to sustain a judgment for the claimant, the wise course is to return it to the department concerned for whatever further action it deems warranted, whether that be a decision revised to weigh rather than ignore plaintiff’s evidence and to reach other than broad undocumented conclusions, or to undertake at this late date a new hearing which will approach the standards of some of the more established contract appeal boards. In view of the Supreme Court’s repeated reminders that factual determinations in actions re-dressable under contract provisions are initially the exclusive prerogative of the contracting agencies (United States v. Carlo Bianchi & Co., supra, United States v. Anthony Grace & Sons, 384 U.S. 424 (1966), and United States v. Utah Constr. & Mining Co., 384 U.S. 394 (1966)), a remand to the [164]*164appropriate Board rather than a de novo trial in this court is advisable, particularly so since the part-time, ad hoc, rule-less Board which decided the instant appeal has been superseded by a full-time permanent board operating under formal rules of procedure, thus minimizing- the prospect of repeating the oversights of the original proceeding.

The plaintiffs1 seek review of a decision by the earlier Board issued January 15, 1962. They allege its decision is not entitled to finality under the Wunderlich. Act, 68 Stat. 81 (1954), 41 U.S.C. §§ 821-22 (1964 ed.), in that plaintiffs are entitled to an equitable adjustment in the amount of $408,029.99, due under Contract No. WA-llpr-TT81, initially entered into between the Norfolk Construction Company and defendant, acting through the Bureau of Public Roads of the Commerce Department. More particularly, plaintiffs allege that the Board’s decision was inadequate by its failure to find a number of facts critical to the controversy; and that what was decided was arbitrary and unsupported by substantial evidence. These allegations are presented in a series of five Assignments of Error2 that (a) the contract plans and specifications were not followed; (b) Government-provided staking for the road contract was incorrect; (c) changed conditions were encountered; (d) Government supervision was arbitrary and capricious; and (e) payment was not adequate for boulder removal, below grade excavation, and overhaul measurement.

Norfolk Construction Company contracted with the Bureau of Public Roads in September 1949 for the construction of 4.208 miles of mountain road in the White Mountain [165]*165National Forest, Grafton County, New Hampshire. The contract contained the standard form articles covering Changes, Changed Conditions and Disputes. The plans for the road had been prepared by the New Hampshire State Highway Department which originally intended to build the road. However, Federal funds were approved for the project and the Federal Works Agency, Public Eoads Administration, later changed to the Bureau of Public Eoads, was designated as the programming and supervising agency to effectuate the contract. The contract was commenced October 24,1949, and completed October 23, 1953, a total period of 1,459 calendar days in contrast to the 300 days allowed under the original contract. The contractor’s claim to the Bureau of Public Eoads was denied by the contracting officer March 26, 1956, and duly appealed to the Appeals Board of the Department of Commerce, which denied the appeal as heretofore noted, except as to the contractor’s claim for prompt inspection of culvert pipe which was allowed and is not here in issue. Otherwise, the plaintiff’s Assignments of Error parallel his administrative claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)
John Capobianco v. United States
394 F.2d 515 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
394 F.2d 515, 184 Ct. Cl. 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capobianco-v-united-states-cc-1968.