Canady v. Creech

218 S.E.2d 383, 288 N.C. 354, 1975 N.C. LEXIS 983
CourtSupreme Court of North Carolina
DecidedOctober 7, 1975
Docket80
StatusPublished
Cited by3 cases

This text of 218 S.E.2d 383 (Canady v. Creech) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Canady v. Creech, 218 S.E.2d 383, 288 N.C. 354, 1975 N.C. LEXIS 983 (N.C. 1975).

Opinion

EXUM, Justice.

The questions for decision are: (1) Whether plaintiff’s claim of lien is fatally defective because of the erroneous statement of the date of first furnishing? (2) If not, whether the defect in any event precludes enforcement of the lien against defendants Korte? Both questions, we hold, are properly answered negatively.

Part 1, Article 2, Chapter 44A of our General Statutes provides for statutory liens on real property for mechanics, laborers and materialmen who deal with the owner of the property. Properly perfected liens “take effect from the time of the first furnishing of labor or materials . . . . ” N. C. Gen. Stat. 44A-10. Such liens are perfected by filing a claim of lien in the Clerk’s office in the County where the real property is located “at any time after the maturity of the obligation secured thereby but not later than 120 days after the last furnishing of labor or materials. . . .” N. C. Gen. Stat. 44A-12 (a) (b). The form for a claim of lien is prescribed by N. C. Gen. Stat. 44A-12(c). This section provides that a claim of *356 lien must “substantially” comport with the form set out. Item 5 of the form provides a place for furnishing the “[d]ate upon which labor or materials were first furnished upon said property by the claimant.” Immediately following the prescribed form there is this provision: “A general description of the labor performed or materials furnished is sufficient. It is not necessary ... to file an itemized list ... or a detailed statement . ” N. C. Gen. Stat. 44A-12 (c).

Because of an error in plaintiff’s claim of lien whereby the date of first furnishing was given as being beyond the date of filing of the claim itself, both the trial court and the Court of Appeals were of the opinion that the claim of lien was fatally defective. The Court of Appeals reasoned:

“If laborers can file notices of lien stating an incorrect date of first furnishing and then enforce their liens with priority as of the actual date of first furnishing, it would be impossible for anyone to determine the priority of laborer’s liens by a search of the records.” 23 N.C. App. at 675-76, 209 S.E. 2d at 513.

The Court of Appeals suggested also that it would be impossible to uphold the date actually given in the claim of lien.

We disagree. First, we are not dealing here with priorities of competing liens nor with any party who relied on the claim of lien as filed. Second, the Court of Appeals seems to have assumed that if the lien were effective at all it would have to be effective either from the date of actual first furnishing. or from the date of first furnishing as given in the claim of lien. There are other possibilities.

We agree with Judge Baley that the date of first furnishing “is an obvious clerical error which could not mislead any interested party.” 23 N.C. App. at 676, 209 S.E. 2d at 513. This is so because one whose interest in the property arose after the date this claim of lien was filed would be on notice not only that the stated date of first furnishing was obviously error but also that the first furnishing of labor and materials must have antedated the filing of the claim itself. The lien could then without prejudice be given effect at least as of the date of filing.

None of our cases deal with the precise point here involved. They were decided before the enactment of Chapter 44A under a statute which required that all claims of lien *357 “shall be filed in detail, specifying the materials furnished or labor performed, and the time thereof.” N. C. Gen. Stat. 44-38 and its predecessors. They also involve claims of lien defective in respects other than, and in some cases in addition to, an incorrect statement of the date of furnishing materials and labor. Lumber Co. v. Builders, 270 N.C. 337, 154 S.E. 2d 665 (1967) ; Lowery v. Haithcock, 239 N.C. 67, 79 S.E. 2d 204 (1953) ; Jefferson v. Bryant, 161 N.C. 404, 77 S.E. 341 (1913) ; Cook v. Cobb, 101 N.C. 68, 7 S.E. 700 (1888) ; Wray v. Harris, 77 N.C. 77 (1877). Our Court has, however, sustained the claim of lien when it was “a reasonable and substantial compliance with the statute.” Cameron v. Limber Co., 118 N.C. 266, 268, 24 S.E. 7, 7 (1896) (“No one need misunderstand it who should become interested in the property.”)

Cases from other jurisdictions are more on point and instructive. Schwartz v. Lewis, 138 App. Div. 566, 123 N.Y.S. 319 (Sup. Ct. App. Div. 1910) was an action to foreclose a mechanic’s lien. Claim of lien, filed April 18, 1908, stated that the first furnishing occurred October 24, 1907, and the last furnishing January 29, 1907.- The New York lien statute required the dates of both first and last furnishings to be given. In fact, the last furnishing occurred January 29, 1908. The Court said:

“If by any fair construction the statement can be read so as to show the date intended, and that date is substantially correct, effect will be given to the notice.” Id. at 568, 123 N.Y.S. at 320.
“The first item was furnished October 24, 1907. The lien was filed April 18, 1908. The last item must necessarily have been subsequent in point of time to the first, and prior in point of time to the filing .... We may therefore reject the year after January as surplusage which does not mislead anyone.” (Emphasis supplied.) Id. at 568, 123 N.Y.S. at 321.

In Pearce v. Knapp, 71 Misc. 324, 127 N.Y.S. 1100 (Otsego County, 1911) claim of lien stated that the first work was performed April 20, 1910, and the last work about May 2, 1910; that the first item of material was furnished about May 20, 1910, and the last item about May 2, 1910. The court sustained the lien holding that the dates of furnishing materials were obviously transposed as could be ascertained by looking at the *358 claim in its entirety. Robison v. Thatcher, 252 Ore. 603, 451 P. 2d 863 (1969) affirmed a decree foreclosing a mechanic’s lien. The claim of lien stated in one place that the owner did not request some extra work involved and in another place stated that he did. The court held that such an internal inconsistency in the claim of lien caused by scrivener’s error would not defeat an otherwise valid lien.

Having determined that the claim of lien is not fatally defective because of an obvious scrivener’s error in stating the date of first furnishing we now consider whether the lien might in any event be enforced against defendants Korte who purchased before the claim was filed. If we assume the claim was filed within “120 days after the last furnishing of labor or materials,” N. C. Gen. Stat. 44A-12(b), and the Kortes, consequently, purchased before the claim of lien was required to be filed, they were in effect charged with notice of the facts giving rise to the lien. “[I]t is entirely possible for a buyer of improved real estate to complete a purchase in the belief that the title is clean and then, a month or two later, to find himself faced with a lien filed by an unpaid workman hired by the former owner.” Dale A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gaston Grading and Landscaping v. Young
449 S.E.2d 475 (Court of Appeals of North Carolina, 1994)
Brown v. Middleton
356 S.E.2d 386 (Court of Appeals of North Carolina, 1987)
Beach & Adams Builders, Inc. v. Northwestern Bank
220 S.E.2d 414 (Court of Appeals of North Carolina, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
218 S.E.2d 383, 288 N.C. 354, 1975 N.C. LEXIS 983, Counsel Stack Legal Research, https://law.counselstack.com/opinion/canady-v-creech-nc-1975.