Chapman v. Brewer

62 N.W. 320, 43 Neb. 890, 1895 Neb. LEXIS 427
CourtNebraska Supreme Court
DecidedFebruary 19, 1895
DocketNo. 5670
StatusPublished
Cited by22 cases

This text of 62 N.W. 320 (Chapman v. Brewer) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chapman v. Brewer, 62 N.W. 320, 43 Neb. 890, 1895 Neb. LEXIS 427 (Neb. 1895).

Opinion

Harrison, J.

This action was instituted in the district court of Cedar county by the plaintiff H. T. Chapman to foreclose a real estate mortgage, executed and delivered to him by Isaac and Lucinda Brewer, upon property described in the petition, situated in Cedar county. The other parties made defendants to the action, in addition to the Brewers, were the Cedar County Bank and the Des Moines Manufacturing & Supply Company. The defendant company answered and filed a cross-bill, in which it claimed a mechanic’s lien prior in point of time to either of the mortgages. The Cedar County Bank filed an answer or cross-petition setting up a lien by mortgage executed and delivered to it by the Brewers, claiming it to be second and subsequent only to plaintiff’s mortgage. Plaintiff filed a reply to the answer and cross-petition of the company, by which was raised the question of the priority of the mechanic’s lien of the company. Upon trial the court determined and adjudged that the liens 'of the plaintiff and Cedar County Bank were prior and superior to that of the company, and from this decree the company has appealed to this court.

In the original claim of lien filed which was introduced in evidence, there appears the following statement: “That pn and between the 30th day of December, 1889, and the 25th day of January, 1890, they furnished lumber and materials and machinery supplies and labor for said building,” etc. The mortgage to Chapman was dated November 15, 1889, and recorded November 21, 1889, and the mortgage of the Cedar County Bank was dated November [895]*89515, 1889, and recorded November 27, 1889. In the answer, or cross-petition, of the Des Moines Manufacturing & Supply company it was stated that work was commenced November 5, 1889, in and on the mill, by a party sent by it from Des Moines for such purpose, and the proof shows that work was so commenced by their workman, Morris, on the 5th or 7th of November, 1889, and that some of the material was furnished during the month of October immediately preceding. In the bill, or statement of account, attached to the claim of lien there is, of date December 31,1889, an item of charge in the following words, viz.: “50-days by Morris to Dec. 31,’89, @ $4, $200.” It is strenuously argued that the company is bound by the statement in the claim filed in reference to the dates between which the labor was performed and material furnished, and that the evidence introduced, of a different and earlier date of the commencement of such labor, etc., was incompetent and could not be received to vary or change the date assigned in the claim as it appeared of record. It may be well, in order to fully and properly understand the situation of the parties, to state here that the claim of lien was filed-March 17, 1890. The statute of this state in regard to mechanics’ liens is as follows: “ Any person entitled to a lien under this chapter shall make an account, in writing, of the items of labor, skill, machinery, or material furnished, or either of them, as the case may be, and, after making oath thereto, shall, within four months of the time of performing such labor and skill, or furnishing such machinery or material, file the same in the office of the register of deeds,” etc., and does not require that the dates of performance of labor or furnishing material shall be stated in the claim for lien; and where it appears from the affidavit filed and the accompanying account of labor or material that such performance and furnishing were within the time required by the law to entitle the claimant- to a lien it is sufficient. The lien papers in this case disclose that [896]*896the last labor was performed, or material furnished, January 25, 1890, and the claim filed March 17 of the same year. This fulfilled the requirement of the statute. In Noll v. Kenneally, 37 Neb., 879, this court stated the rule to be as follows: “The failure of an account filed to secure a mechanic’s lien to state the dates the various items of materials were furnished will not vitiate the lien, if it appears from the account and affidavit thereto attached that such materials were furnished within the requisite time to entitle the claimant to a lien therefor.” In Henry & Coatsworth Co. v. Fisherdick, 37 Neb., 207, it was held: “A party taking a mortgage on real estate is bound, at the time, to know whether material has been furnished or labor performed in the erection, reparation, or removal of improvements on the premises within the four prior months;” and further, “the lien of a mortgage on real estate, taken while a building is in process of erection thereon, is subject to the claims of material-men and laborers for material already and thereafter furnished, and for labor already and thereafter performed, in the erection of such building, when the commencement of such furnishing of material, or the commencement of the performance of such labor, was prior to the record of said mortgage.” Applying the rules of law as announced by this court, just quoted, to the facts in the case at bar, and further bearing in mind that by the provisions of our statute on the subject under discussion the lien attaches at the commencement of the labor or furnishing material, and the relative positions of the liens involved are not, in so far as they are governed by their respective dates, very difficult to ascertain or of assignment. The fact that the date of the commencement of labor or furnishing of material was stated to be December 30, 1889, when it should have been November 5th or 7th, could not, and did not, have any significance for or to mortgage lien-holders, or in any manner affect their rights under the mortgages executed during the month of November at a time [897]*897when the work and furnishing which were the foundation •of the lien were in progress; and had been from a date prior to such execution, as they were bound to take notice of these things, and their mortgages were taken subject to any rights of lien which had accrued or attached in favor of mechanics or material-men. Their rights were acquired long prior to the time the statement was filed in which appeared the erroneous date, and such statement was not notice to them, nor could or were their liens or rights in any way affected by it, and the evidence of the true date was •competent and its reception in no manner or extent harmful or prejudicial to the parties holding the mortgages. (2 Jones, Liens, sec. 1066; Wakefield v. Latey, 39 Neb., 285.)

It is argued that it appears upon the face of the original claim of lien, filed by appellant, which was introduced in evidence, that the claim was verified' before Gardner Y. Wright, a notary public, and who was secretary of the appellant company, and also shown by the articles of incorporation to be a stockholder therein and thus directly interested, and that being so interested he was incompetent to administer the oath to the party verifying the lien. However this may be, it was not, we think, sufficiently raised by the pleadings and was, evidently, not an issue in the trial court and cannot be considered in this court. It is further urged that the verification of the claim of lien was upon information and belief, and that it should have been sworn to positively to fulfill the requirements of our statutory provisions in regard to the verification of a claim for a mechanic’s lien. Such has been stated to be the rule in Kansas, under a statute very similar in its exactions in this respect to our own. (Dorman v. Crozier, 14 Kan., 224. See, also, Globe Iron Roofing & Corrugating Co. v. Thatcher, 6 So. Rep. [Ala.], 366).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brazier Forest Products, Inc. v. Northern Transport, Inc.
724 P.2d 970 (Washington Supreme Court, 1986)
Canady v. Creech
218 S.E.2d 383 (Supreme Court of North Carolina, 1975)
Central Nebraska Public Power & Irrigation District v. Walston
299 N.W. 609 (Nebraska Supreme Court, 1941)
Caird Engineering Works v. Seven-Up Gold Mining Co., Inc.
111 P.2d 1267 (Montana Supreme Court, 1940)
O. G. Pierce Co. v. Century Indemnity Co.
285 N.W. 91 (Nebraska Supreme Court, 1939)
People's State Bank v. Smith
231 N.W. 141 (Nebraska Supreme Court, 1930)
Portland Building & Loan Ass'n v. Peck
149 A. 214 (Supreme Court of Connecticut, 1930)
McDonald-Weist Logging Co. v. Cobb
278 F. 167 (Ninth Circuit, 1921)
Etheredge v. Chicago, Burlington & Quincy Railroad
181 N.W. 928 (Nebraska Supreme Court, 1921)
State v. Duniway
128 P. 853 (Oregon Supreme Court, 1912)
Lyons v. Howard
117 P. 842 (New Mexico Supreme Court, 1911)
Fairbanks-Morse Co. v. Union Bank & Trust Co.
104 P. 815 (Washington Supreme Court, 1909)
Wetzel & T. Ry. Co. v. Tennis Bros.
145 F. 458 (Fourth Circuit, 1906)
Tennis Bros. v. Wetzel & T. Ry. Co.
140 F. 193 (U.S. Circuit Court for the District of Northern West Virginia, 1905)
Kneisley Lumber Co. v. Edward B. Stoddard Co.
88 S.W. 774 (Missouri Court of Appeals, 1905)
Woolacott v. Case
64 P. 965 (Supreme Court of Kansas, 1901)
Goodwin v. Cunningham
74 N.W. 315 (Nebraska Supreme Court, 1898)
Hersh & Son v. Carman
71 N.W. 713 (Nebraska Supreme Court, 1897)
Farmers' & Mechanics' National Bank v. Taylor
40 S.W. 876 (Texas Supreme Court, 1897)
Missouri Pacific Railway Co. v. Bradley
71 N.W. 283 (Nebraska Supreme Court, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
62 N.W. 320, 43 Neb. 890, 1895 Neb. LEXIS 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chapman-v-brewer-neb-1895.