K. Lee Builders, Inc. v. Barnes

CourtCourt of Appeals of North Carolina
DecidedJuly 1, 2026
Docket25-1029
StatusPublished
AuthorJudge John Arrowood

This text of K. Lee Builders, Inc. v. Barnes (K. Lee Builders, Inc. v. Barnes) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K. Lee Builders, Inc. v. Barnes, (N.C. Ct. App. 2026).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA25-1029

Filed 1 July 2026

Vance County, No. 23CVS001277-900

K. LEE BUILDERS, INC., Plaintiff,

v.

THOMAS SCOTT BARNES, Defendant.

Appeal by defendant from judgment entered 21 March 2025 and order entered

18 June 2025 by Judge Brian C. Wilks in Vance County Superior Court. Heard in

the Court of Appeals 3 June 2026.

Banzet, Thompson, Styers & May, PLLC, by Mitchell G. Styers, and Simpson Law Firm, PLLC, by Benjamin S. Gurlitz and R. Shane Walker, for plaintiff- appellee.

Haynsworth Sinkler Boyd P.A., by Lindsey E. Powell, Todd A. Jones, and Christian Lunghi, for defendant-appellant.

ARROWOOD, Judge.

Thomas Scott Barnes (“defendant”) appeals from judgment entered following

trial, wherein a jury determined that defendant breached a construction contract

with K. Lee Builders, Inc. (“plaintiff”), and from the Status Quo Order obliging the

Clerk of Court to retain funds defendant deposited pursuant to a Cash Bond, pending

disposition of this appeal.

I. Introduction K. LEE BUILDERS, INC. V. BARNES

Opinion of the Court

Defendant entered a construction contract with plaintiff, a licensed general

contractor. The contract was executed and signed by the parties on or around

1 August 2022, and it set out the parties’ responsibilities in connection with the

construction of a home on defendant’s real property in Henderson. Plaintiff was

obligated to supervise construction, furnish all necessary labor and materials, pay

taxes and procure licenses and permits, comply with construction laws and

regulations, complete clean-up, and take all reasonable safety precautions. The

contract contained a warranty of fitness as to all equipment and materials used, a

warranty of workmanlike performance, and a one-year warranty from the date of a

certificate of occupancy. The contract permitted plaintiff to terminate the contract in

the event defendant failed to make a required payment, while permitting defendant

to terminate the contract in the event plaintiff failed to perform its duties under the

agreement and then failed to cure its default within thirty days, but required

defendant to pay for all work performed to date, minus any unpaid portion of

plaintiff’s builder’s fee.

Plaintiff first “broke ground” in the construction project on 2 November 2022.

During February 2023, while construction was ongoing, defendant raised concerns

about plaintiff’s sealing of the basement, and plaintiff attempted fixes which

ultimately did not satisfy defendant. Amid this conflict, plaintiff continued to work

on the property until at least 13 September 2023.

On 4 October 2023, plaintiff filed a Claim of Lien on Real Property pursuant

-2- K. LEE BUILDERS, INC. V. BARNES

to N.C.G.S. § 44A-12, et seq, asserting a claim of $53,410.76, plus interest, attorney’s

fees, and costs, against defendant’s real property. The filing incorrectly recorded the

date that labor was first furnished as 5 September 2022 and incorrectly recorded the

date the labor was last furnished as 25 August 2023. The filing certified that

defendant was served in accordance with statute.

On 14 December 2023, plaintiff filed its Complaint in this dispute, repeating

the above incorrect labor dates, and alleging that defendant materially breached their

contract by failing to pay $53,410.76, causing plaintiff to cease performance. Plaintiff

sought recovery of this amount in actual damages plus interest and costs, judgment

against defendant in the above amount for the reasonable value of services plus

reasonable legal fees expended to enforce the claim, and requested that the judgment

constitute a lien against defendant’s real property. Plaintiff also filed Notice of Lis

Pendens noting the filing of its Complaint. Plaintiff filed an Affidavit of Service of

Process as to the summons and complaint and Notice of Lis Pendens on

11 January 2024.

On 24 January 2024, defendant filed a Cash Bond to Discharge Mechanics

Lien and deposited $53,410.76 with the Clerk of Superior Court in Vance County. On

31 January 2024, defendant filed his Answer and Defenses and Counterclaims

alleging causes of action for breach of contract, breach of express warranty, breach of

implied warranty, fraud, unfair and deceptive trade practices, and punitive damages.

On 17 January 2025, following discovery and depositions, plaintiff moved for

-3- K. LEE BUILDERS, INC. V. BARNES

Summary Judgment. Defendant moved for Judgment on the Pleadings on

10 February 2025, alleging that plaintiff’s claim of lien was fatally defective due to

failure to include “all substantive and procedural requirements necessary” and

requesting an order granting attorneys’ fees and damages resulting from cloud on

title. Defendant also moved for Summary Judgment, arguing that the incorrect date

of first furnishing failed to perfect plaintiff’s lien, and that the lien was fatally

defective. Defendant again moved for Summary Judgment on 28 February 2025

“with respect to whether Plaintiff has breached the contract at issue[.]”

The court heard oral arguments from both parties in a pretrial hearing on

10 March 2025. Defendant’s counsel argued that the lien had been fatally defective

and was therefore unenforceable, because the “dates of first and last furnishing on a

lien are critical because when a lien is enforced, the lien will be held to relate back

and become effective from the first date of the furnishing” and that “[n]obody

searching the records and looking at the lien in the Complaint would have reason to

know that these dates are false.” Accordingly, if “contractors are allowed to put false

dates of furnishing on their lien, it sends a message to any other contractor that they

don’t need to be accurate with respect to the dates” and could thereby “establish false

lien priority” and “sidestep the strict statutes [setting out] the time in which they

[must] enforce the lien.”

Plaintiff’s counsel argued that, as a matter of statute, the matter was moot

because the lien was cancelled when defendant filed his cash bond in the sum

-4- K. LEE BUILDERS, INC. V. BARNES

equaling the claim. Plaintiff’s counsel also pointed out that no other parties were

“dependent on this lien date” and that because plaintiff had no claim regarding work

performed outside those dates, defendant would not have been prejudiced.

The court granted defendant’s first Motion for Summary Judgment in open

court because “the dates [in plaintiff’s Complaint] are not in compliance with the

statute.” However, the following day, the court announced that this was mistaken:

“The Court, having time to reflect on that and do further research . . . It was simply

a wrong beginning and end date that the Court will modify . . . to correspond with the

evidence as brought out through arguments and further discovery.” Following

further argument, the court found “that the defendant was put on notice of the subject

matter of the lien, that the error is not a fatal error[.]” The court “in a sanction for

the error in its discretion, will comport the dates to the evidence presented as to

timeframe, which under [N.C.G.S. §] 44A-16, the lien was discharged, which makes

the plaintiff’s claim to enforce that lien a moot point.” The court noted defendant’s

objection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estrada v. Jaques
321 S.E.2d 240 (Court of Appeals of North Carolina, 1984)
Mebane Lumber Co. v. Avery & Bullock Builders, Inc.
154 S.E.2d 665 (Supreme Court of North Carolina, 1967)
Frank H. Conner Co. v. Spanish Inns Charlotte, Ltd.
242 S.E.2d 785 (Supreme Court of North Carolina, 1978)
Whitaker v. Clark
427 S.E.2d 142 (Court of Appeals of North Carolina, 1993)
Shroyer v. County of Mecklenburg
571 S.E.2d 849 (Court of Appeals of North Carolina, 2002)
Beach & Adams Builders, Inc. v. Northwestern Bank
220 S.E.2d 414 (Court of Appeals of North Carolina, 1975)
Goldston v. American Motors Corp.
392 S.E.2d 735 (Supreme Court of North Carolina, 1990)
Wood v. McDonald's Corp.
603 S.E.2d 539 (Court of Appeals of North Carolina, 2004)
Barrier v. Randolph
133 S.E.2d 655 (Supreme Court of North Carolina, 1963)
Waters v. Qualified Personnel, Inc.
240 S.E.2d 338 (Supreme Court of North Carolina, 1978)
Sherrill v. Amerada Hess Corp.
504 S.E.2d 802 (Court of Appeals of North Carolina, 1998)
Strickland v. General Building & Masonry Contractors, Inc.
207 S.E.2d 399 (Court of Appeals of North Carolina, 1974)
Canady v. Creech
218 S.E.2d 383 (Supreme Court of North Carolina, 1975)
George v. Hartford Accident and Indemnity Co.
412 S.E.2d 43 (Supreme Court of North Carolina, 1992)
Cook v. . Cobb
7 S.E. 700 (Supreme Court of North Carolina, 1888)
Cameron v. Consolidated Lumber Co.
24 S.E. 7 (Supreme Court of North Carolina, 1896)
North Carolina Farm Bureau Mutual Insurance v. Sadler ex rel. Sadler
711 S.E.2d 114 (Supreme Court of North Carolina, 2011)
Brown v. Middleton
356 S.E.2d 386 (Court of Appeals of North Carolina, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
K. Lee Builders, Inc. v. Barnes, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-lee-builders-inc-v-barnes-ncctapp-2026.