Shroyer v. County of Mecklenburg

571 S.E.2d 849, 154 N.C. App. 163, 2002 N.C. App. LEXIS 1402
CourtCourt of Appeals of North Carolina
DecidedNovember 19, 2002
DocketCOA02-15
StatusPublished
Cited by18 cases

This text of 571 S.E.2d 849 (Shroyer v. County of Mecklenburg) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shroyer v. County of Mecklenburg, 571 S.E.2d 849, 154 N.C. App. 163, 2002 N.C. App. LEXIS 1402 (N.C. Ct. App. 2002).

Opinion

HUNTER, Judge.

George and Gail Shroyer (“plaintiffs”) appeal an order granting summary judgment of their claim asserting breach of contract against defendants George Houston (“Houston”) and Connell Mills Partnership (“CMP”). Plaintiffs also appeal an order granting summary judgment on their claims asserting a third-party beneficiary breach of contract and negligence against defendant W.T. Norwood, Inc. (“Norwood”). We affirm the trial court’s orders.

CMP is a real estate developer managed by Houston. In 1990, CMP began development of a subdivision in which plaintiffs eventually built a home. In 1991, CMP requested that the Mecklenburg County Health Department (“the Department”) perform a soil investigation on lots of the subdivision to determine the property’s suitabil *166 ity for installation of a ground absorption sewage disposal system. The results of the investigation revealed that portions of the subdivision property were unsuitable for installation of such a system. Nevertheless, the Department (1) recommended a reduction in the number of lots in the subdivision, resulting in CMP reducing the number of lots from fifty to forty-two, and (2) concluded that the lots would be suitable for homes if an innovative septic tank water treatment system (“septic system”) was designed and installed.

In April of 1996, plaintiffs entered into a contract with CMP to purchase Lot 26 in the subdivision. The contract was “[sjubject to land passing a percolation test in relation to [plaintiffs’] desired house location on lot” to determine whether it was suitable for operation of a residential septic system. The Department performed the test, and Lot 26 passed. Plaintiffs closed on the property on 9 May 1996.

After plaintiffs purchased Lot 26, the general contractor for the home, Helmsman Construction, Inc., subcontracted with Norwood to design and install their septic system. However, in September of 1996, less than a month after moving into their new home, plaintiffs’ septic system failed. Plaintiffs continued to encounter problems despite having numerous repairs made to the septic system. Ultimately, the Department conducted a new soil test and found that unsuitable soil caused the septic tank’s constant failure. Plaintiffs were issued two wastewater violation notices by the Department (on 20 June 1997 and 3 July 1998) for having an inoperable septic system that was in violation of state law.

Plaintiffs filed a complaint against defendants on 3 September 1998. In their complaint, plaintiffs asserted a negligence claim and a third-party beneficiary breach of contract claim against Norwood for faulty design and installation of the septic system. Plaintiffs also asserted a breach of contract claim against CMP and Houston for breaching express and implied warranties regarding the suitability of Lot 26 for operation of a septic system. Plaintiffs asserted claims against other defendants, but those claims are not at issue in this appeal.

CMP and Houston moved for summary judgment in their answer filed on 17 November 1998. Prior to this motion being heard, the affidavit of plaintiff Gail Shroyer was filed in which she stated that plaintiffs would have never purchased Lot 26 had they been informed prior *167 to the purchase about the 1991 soil investigation performed by the Department. On 5 January 1999, the summary judgment motion was heard and granted in favor of CMP and Houston in an order filed 26 May 1999.

With respect to Norwood, it also filed an answer in November of 1998. The case against it and the other defendants proceeded into the discovery phase with the action being calendared for trial during the last week of February 2000. Norwood filed a summary judgment motion on 11 February 2000 requesting the dismissal of all plaintiffs’ claims against it. Plaintiffs’ counsel prepared and filed a pre-trial memorandum for the court. The memorandum stated that plaintiffs were going forward with their third-party beneficiary breach of contract claim against Norwood, but not proceeding to trial on their negligence claim against it. The court subsequently heard and granted Norwood’s motion for summary judgment in an order filed 23 May 2000. Plaintiffs then filed a motion to alter or amend the judgment in favor of Norwood arguing it was overbroad and should not have resulted in the dismissal of their negligence claim. Plaintiffs’ motion was denied in an order entered 14 August 2000.

As the case continued towards trial, plaintiffs settled their claims against the other defendants. A voluntary dismissal without prejudice was entered regarding the claims against those defendants on 27 September 2001. Thereafter, plaintiffs timely filed notice of appeal with respect to the court’s summary judgment orders in favor of Norwood, CMP, and Houston.

I. Standard of Review

The assignments of error plaintiffs bring forth against Norwood, CMP, and Houston all involve whether the court erred in granting summary judgment in defendants’ favor. On an appeal from a grant of summary judgment, this Court reviews the trial court’s decision de novo. Falk Integrated Tech., Inc. v. Stack, 132 N.C. App. 807, 809, 513 S.E.2d 572, 574 (1999). Thus, when viewing the evidence in the light most favorable to the non-movant, we must determine whether the trial court properly concluded that the moving party showed, through pleadings and affidavits, that there was no genuine issue of material fact and that the moving party was entitled to judgment as a matter of law. Bruce-Terminix Co. v. Zurich Ins. Co., 130 N.C. App. 729, 733, 504 S.E.2d 574, 577 (1998).

*168 II. Norwood

By their first assignment of error plaintiffs argue, in part, that they should be allowed to bring a third-party beneficiary breach of contract claim against Norwood, a subcontractor, for failing to properly design and install their septic system. We disagree.

North Carolina case law clearly holds that a landowner is not a third-party beneficiary to a subcontract between the builder and one of the builder’s subcontractors. See Vogel v. Supply Co. and Supply Co. v. Developers, Inc., 277 N.C. 119, 177 S.E.2d 273 (1970). Specifically, our Supreme Court has held that the landowner is a mere incidental beneficiary of the construction contract between the builder and subcontractor and cannot maintain an action against the subcontractor for its breach. Id. at 126, 177 S.E.2d at 277. Here, plaintiffs admit that no contract or direct privity existed between them and Norwood. Plaintiffs only support the validity of their claim by citing to several North Carolina cases where the courts held that privity of contract is not required for a tenant/landowner to maintain a negligence claim against a subcontractor. See Prince v. Wright, 141 N.C. App. 262, 541 S.E.2d 191 (2000); Olympic Products Co. v. Roof Systems, Inc., 88 N.C. App. 315, 363 S.E.2d 367

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis & Taft Architecture, P.A. v. DDR-Shadowline
Court of Appeals of North Carolina, 2019
SRS Arlington Offices 1, LLC v. Arlington Condo. Owners Ass'n, Inc.
760 S.E.2d 330 (Court of Appeals of North Carolina, 2014)
Premier, Inc. v. Peterson
755 S.E.2d 56 (Court of Appeals of North Carolina, 2014)
Sutton v. Driver
712 S.E.2d 318 (Court of Appeals of North Carolina, 2011)
Discover Bank v. Calhoun
665 S.E.2d 595 (Court of Appeals of North Carolina, 2008)
Sellers v. Morton
661 S.E.2d 915 (Court of Appeals of North Carolina, 2008)
Gilreath v. North Carolina Department of Health & Human Services
629 S.E.2d 293 (Court of Appeals of North Carolina, 2006)
Strickland v. Lawrence
627 S.E.2d 301 (Court of Appeals of North Carolina, 2006)
Excel Staffing Service, Inc. v. HP Reidsville, Inc.
616 S.E.2d 349 (Court of Appeals of North Carolina, 2005)
Daniels v. Durham County Hospital Corp.
615 S.E.2d 60 (Court of Appeals of North Carolina, 2005)
Brust v. ICE VENTURES, INC.
605 S.E.2d 267 (Court of Appeals of North Carolina, 2004)
Whitehead v. Sparrow Enterprise, Inc.
605 S.E.2d 234 (Court of Appeals of North Carolina, 2004)
Hyman v. Efficiency, Inc.
605 S.E.2d 254 (Court of Appeals of North Carolina, 2004)
Eckard v. Smith
603 S.E.2d 134 (Court of Appeals of North Carolina, 2004)
White v. Consolidated Planning, Inc.
603 S.E.2d 147 (Court of Appeals of North Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
571 S.E.2d 849, 154 N.C. App. 163, 2002 N.C. App. LEXIS 1402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shroyer-v-county-of-mecklenburg-ncctapp-2002.