Can Softtech, Inc v. United States

United States Court of Federal Claims·Decided February 18, 2025·No. 24-1009·Published

Opinion

IN THE UNITED STATES COURT OF FEDERAL CLAIMS ______________________________________ ) CAN SOFTTECH, INC., ) ) Plaintiff, ) No. 24-1009 ) v. ) Filed: January 31, 2025 ) THE UNITED STATES, ) Re-issued: February 18, 2025 ∗ ) Defendant. ) ______________________________________ )

SUPPLEMENTAL ORDER AND OPINION

Plaintiff CAN Softtech, Inc. (“CSI”) previously moved for an order requiring the

Government to complete the Administrative Record with additional evidence CSI believes the

Government improperly withheld. See Mot. to Complete, ECF No. 18. The Court found that CSI

largely failed to meet its burden of showing that the record is incomplete, except with respect to a

missing attachment, consisting of a draft memorandum, referenced in a decisional document in the

Administrative Record regarding potential Procurement Integrity Act (“PIA”) violations. See Op.

& Order at 14–15, ECF No. 34. The Court ordered the Government to submit the draft

memorandum and associated documents for in camera review and a final determination of whether

the materials should be included in the Administrative Record. For the reasons that follow, the

Court GRANTS IN PART CSI’s request with respect to this document and ORDERS the

Government to complete the Administrative Record with a redacted copy of the draft

memorandum as described below.

∗ The Court issued this order and opinion under seal on January 31, 2025, and directed the

parties to file any proposed redactions by February 11, 2025. As the parties did not propose any redactions, the Court reissues the order and opinion publicly in full. Pursuant to the Court’s order, the Government submitted the attachment, which is entitled

“Draft D&F ELFF Procurement Integrity Violation or Possible Violation” (“Draft PIA Memo”),

see Admin. R. at 781, ECF No. 19-1 (“AR”), 1 for in camera review on October 8, 2024. See

Notice of Submission (Oct. 8, 2024). The submission included 23 attachments—largely email

communications—referenced within the Draft PIA Memo. The Government also filed a Notice

explaining its basis for withholding the draft memorandum and associated attachments. See Notice

of Submitting Docs. for In Camera Review, ECF No. 33. The Government explains that none of

the materials were “developed and considered in making the decisions involving the solicitation

and incumbent contract” at issue in this litigation. Id. at 1. The Government further argues that

the materials reflect “pre-decisional and deliberative information,” as well as attorney-client

privileged information, “that is not necessary for meaningful judicial review.” Id. at 3. It declined

to propose any redactions to its submission.

As the Court explained in its Opinion and Order, the standard that a plaintiff must meet to

complete the administrative record is different than the standard to supplement the record. See

ECF No. 34 at 4 (citing Poplar Point RBBR, LLC v. United States, 145 Fed. Cl. 489, 494 (2019);

Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 1379–80 (Fed. Cir. 2009)). The

supplementation standard asks whether the existing record is “sufficient to permit meaningful

judicial review” or, conversely, whether “the omission of extra-record evidence precludes effective

judicial review.” Axiom, 564 F.3d at 1380 (quoting Murakami v. United States, 46 Fed. Cl. 731,

735 (2000)). The completion standard—CSI’s basis for seeking additional evidence here—asks

only whether the plaintiff has provided “clear evidence” that the agency “generated or considered”

1 For ease of reference, citations to the Administrative Record refer to the bates-labeled page numbers rather than the ECF page numbers. 2 information “during the procurement and decisionmaking process” but omitted that information

from the record filed in court. Poplar Point, 145 Fed Cl. at 494 (quoting ARKRAY USA, Inc. v.

United States, No. 14-233C, 2014 WL 2905127, at *4 (Fed. Cl. Apr. 28, 2014)); ELB Servs., LLC

v. United States, 172 Fed. Cl. 233, 241 (2024). Internal deliberative and other privileged materials

are generally considered not to be part of the administrative record. ECF No. 34 at 7–8 (collecting

cases); see also Op. & Order at 9–12, ECF No. 40 (denying CSI’s motion for reconsideration).

Having reviewed the Government’s in camera submission, the Court agrees that the

agency’s findings and determination on the potential PIA violations are not in themselves at issue

in this protest. But the Government affirmatively included the final determination, entitled

“Memorandum to the File” (“Final PIA Memo”), in the Administrative Record because it is

“tangentially related to the challenged decisions, to the extent that it explains the delay of about

one month in executing GSA’s decision to terminate the contract and issue a new solicitation.”

ECF No. 33 at 2. The Final PIA Memo lays out a timeline of the events underlying the PIA

allegations and GSA’s investigation thereof, but that timeline is only a partially complete set of

facts that picks up where the Draft PIA Memo left off. The Final PIA Memo explicitly incorporates

by reference certain factual information from the Draft PIA Memo without providing a separate

overview of the content of that reference. See AR 780 (providing a “timeline of the events that

took place subsequent to April 30, 2024, the last date identified in the [Draft PIA Memo]”). In

essence, the existing Administrative Record assumes the reader’s familiarity with the events

outlined in the Draft PIA Memo—without including the draft memorandum itself. If, as the

Government concedes, the timing of the PIA investigation is tangentially related to review of the

challenged decisions in this case, then the full timeline must be included in the Administrative

Record.

3 The Court, however, agrees that some parts of the submission that the Government

provided in camera need not be included in the Administrative Record on privilege grounds. Two

doctrines are relevant here: attorney-client privilege and the deliberative-process privilege. The

attorney-client privilege protects “[c]onfidential disclosures by a client to an attorney made in

order to obtain legal assistance.” Fisher v. United States, 425 U.S. 391, 403 (1976). The privilege

“does not shield all information that a client divulges to an attorney, or vice versa, but rather is

limited to instances where legal advice is sought or rendered.” Deseret Mgmt. Corp. v. United

States, 76 Fed. Cl. 88, 90 (2007) (quoting Pac. Gas & Elec. Co. v. United States, 69 Fed. Cl. 784,

810 (2006)). The privilege is not limited to private litigants; it extends to communications by the

Department of Justice to a client agency and by the agency’s attorneys to non-attorneys “seeking

or being provided with legal advice.” Id. at 91. The privilege “does not protect disclosure of the

underlying facts by those who communicated with the attorney.” Upjohn Co. v. United States,

449 U.S. 383, 395 (1981). Further, the broad subject matter and general nature of the

communication or the specific attorney-client relationship are generally not privileged. Oasis Int’l

Waters, Inc. v. United States, 110 Fed. Cl. 87, 100 (2013). But a particular fact’s inclusion in a

Free access — add to your briefcase to read the full text and ask questions with AI

Can Softtech, Inc v. United States, (uscfc 2025).

Can Softtech, Inc v. United States (Can Softtech, Inc v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fisher v. United States
425 U.S. 391 (Supreme Court, 1976)
Upjohn Co. v. United States
449 U.S. 383 (Supreme Court, 1981)
Axiom Resource Management, Inc. v. United States
564 F.3d 1374 (Federal Circuit, 2009)
Oasis International Waters, Inc. v. United States
110 Fed. Cl. 87 (Federal Claims, 2013)
Murakami v. United States
46 Fed. Cl. 731 (Federal Claims, 2000)
Pacific Gas & Electric Co. v. United States
69 Fed. Cl. 784 (Federal Claims, 2006)
Deseret Management Corp. v. United States
76 Fed. Cl. 88 (Federal Claims, 2007)
Carl Zeiss Stiftung v. V. E. B. Carl Zeiss, Jena
40 F.R.D. 318 (District of Columbia, 1966)