Can Softtech, Inc v. United States

United States Court of Federal Claims·Decided July 29, 2025·No. 24-1009·Published

Opinion

IN THE UNITED STATES COURT OF FEDERAL CLAIMS ______________________________________ ) CAN SOFTTECH, INC., ) ) Plaintiff, ) No. 24-1009 ) v. ) Filed: July 17, 2025 ) THE UNITED STATES, ) Re-issued: July 29, 2025 ∗ ) Defendant. ) ______________________________________ )

OPINION AND ORDER

Plaintiff CAN Softtech, Inc. (“CSI”) challenges the General Services Administration’s

(“GSA” or “the Agency”) decisions first to reevaluate quotes under a solicitation for information

technology support services for the United States Air Force and then to terminate CSI’s award in

order to re-solicit the requirement under a revised solicitation. It also challenges GSA’s sole-

source extension of the incumbent’s contract. CSI argues that GSA’s rationale for initially

reevaluating the award is unexplained, while GSA’s later cancellation and re-solicitation decision

lacks a rational basis and any reasonable explanation. CSI contends GSA’s sole-source extension

is both contrary to law and arbitrary and capricious. Before the Court are the parties’ dispositive

motions and CSI’s Motion to Strike. As explained below, the Court GRANTS IN PART AND

DENIES IN PART CSI’s Motion for Judgment on the Administrative Record, GRANTS IN

PART AND DENIES IN PART the Government’s Motion to Dismiss and Cross-Motion for

Judgment on the Administrative Record, DENIES CSI’s Motion to Strike, and REMANDS to the

Agency for further explanation of its decision to terminate CSI’s contract award and re-solicit.

∗ The Court issued this opinion under seal on July 17, 2025, and directed the parties to file

any proposed redactions by July 24, 2025. As the parties did not propose any redactions, the Court reissues the opinion publicly in full. I. BACKGROUND

A. The Solicitation

On August 15, 2023, GSA issued Request for Quote No. 47QFLA23Q0116 (“RFQ” or “the

Solicitation”) for the award of a task order for eFINANCE, LeaveWeb, FMSuite, and FMDQS

(collectively, “ELFF”) information-technology support services to be provided by the contractor

to the Air Force. Admin. R. (“AR”) at 66, 155, ECF No. 19-1. 1 GSA issued the Solicitation

pursuant to the authority of Federal Acquisition Regulation (“FAR”) 8.405, under GSA’s Multiple

Award Schedule – Small Business, and classified the Solicitation as a small business set-aside. Id.

The Solicitation indicated that GSA would award a single task order with Firm Fixed Price and

Time and Material/Labor Hour line items. Id. GSA noted that the phase-in period would begin

on January 1, 2024, and that the base year of the task order was February 1, 2024, to January 31,

2025. Id. The Solicitation included four additional option years, continuing through January 31,

2029. AR 67. The Solicitation initially closed on September 6, 2023, which is when quotes were

due. AR 155. After some amendments to correct “discrepancies” and to revise certain other

requirements, GSA extended the due date to September 15, 2023. AR 160.

GSA notified offerors that its evaluation of quotes would be conducted using the best-value

tradeoff approach. AR 81. The Solicitation indicated that GSA would consider several factors in

its evaluation, as well as compliance with mandatory requirements (pass/fail). AR 70–85. GSA

further attached to the Solicitation a Performance Work Statement (“PWS”) that defined additional

1 For ease of reference, citations to the Administrative Record refer to the bates-labeled page numbers rather than the ECF page numbers. The original Administrative Record includes pages 1–781 (ECF No. 19-1), an amendment with additional documents not provided in the original record includes pages 782–948 (ECF Nos. 27-1, 46-2), and an amendment with redacted copies of documents reviewed in camera includes CSI-IC 1–87 (ECF No. 42-2). The Court will collectively refer to all parts as the Administrative Record or “AR”. Citations to the documents provided in camera use the separately paginated bates-labeled page numbers, i.e., the page numbers following “CSI-IC”. 2 requirements for the contract. AR 89–132. The PWS laid out a set of 33 deliverables that GSA

and the Air Force expected contractors to provide following contract award, including items like

a Quality Management Plan due 30 days after contract start and a Monthly Status Report due no

later than the tenth day of each calendar month following commencement of the contract. See AR

114–16.

As relevant to this lawsuit, the Solicitation provided an estimate for staffing requirements,

indicating that the Agency expected staffing for approximately one year to require 12 full-time

equivalent positions supported by an estimated 45,120 labor hours. AR 68. In response to an

offeror’s question about the mismatch between the estimated number of full-time employees and

the estimated labor hours (45,120 labor hours suggests a total of 24 full-time positions in a year,

not 12), GSA later clarified—before the final due date for quotes—that the original Solicitation

was incorrect and the estimate for staffing levels should total 24 full-time positions. AR 228.

The Solicitation required offerors to “provide evidence (certificate) that key personnel

possess the required certifications in compliance with the PWS paragraph 7.5 Key Positions/Key

Personnel.” AR 71. That paragraph specified, in turn, that

[k]ey personnel are personnel proposed to perform in key positions. Key positions are those deemed essential for successful contractor accomplishment of the work to be performed. The contractor shall not divert key personnel to other projects or replace them without receiving prior authorization from the Contracting Officer (CO). All key positions require a bachelor’s degree and 3-5 years of experience. A minimum of 5 years of specialized experience relevant to the key position is required to substitute work experience or education.

AR 123. The PWS identified two positions that GSA considered to be key positions: a Project

Manager and a Lead Developer. AR 123–24. GSA required the Project Manager to “have

credentials that substantiate that he or she” has significant project experience, successful

management of project tasks, experience in managing teams on a Department of Defense contract,

3 and knowledge of Air Force management practices and program implementation. Id. GSA

required the Lead Developer to have expert knowledge in “Full Stack SDLC”; “SQL stored

queries, procedures, functions, views, and triggers”; “SQL database modeling, constraints,

indexes”; HTML; JavaScript; CSS; Java; Build Tools; and Configuration Management. AR 124.

Though cybersecurity certifications were not referenced directly in the Solicitation, GSA

included a section in the PWS noting that

[t]he contractor shall provide personnel who are fully qualified to perform the requirements in the PWS. All contractor personnel must possess and apply comprehensive knowledge on multiple complex tasks and high impact assessments. Tasks require personnel to have the knowledge, skills, and abilities to determine innovative solutions to complex requirements. All personnel in information technology positions must meet certification requirements identified in section 9.1.1 of this PWS.

AR 122. Section 9.1.1 required offerors to comply with Defense Acquisition Regulation

Supplement 252.239-7001, which in turn requires contractors to undergo training and possess

certification for information assurance functions applicable to Department of Defense contracts.

AR 129.

Free access — add to your briefcase to read the full text and ask questions with AI

Can Softtech, Inc v. United States, (uscfc 2025).

Can Softtech, Inc v. United States (Can Softtech, Inc v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burlington Truck Lines, Inc. v. United States
371 U.S. 156 (Supreme Court, 1962)
Powell v. McCormack
395 U.S. 486 (Supreme Court, 1969)
Camp v. Pitts
411 U.S. 138 (Supreme Court, 1973)
Rex Service Corp. v. United States
448 F.3d 1305 (Federal Circuit, 2006)
Timken U.S. Corp. v. United States
421 F.3d 1350 (Federal Circuit, 2005)
Aqua Marine Supply v. Aim Machining, Inc.
247 F.3d 1216 (Federal Circuit, 2001)
Skf Usa Inc. v. United States
254 F.3d 1022 (Federal Circuit, 2001)
R & W Flammann Gmbh v. United States
339 F.3d 1320 (Federal Circuit, 2003)
Bannum, Inc. v. United States
404 F.3d 1346 (Federal Circuit, 2005)
Professional Service Industries, Inc. v. United States
129 Fed. Cl. 190 (Federal Claims, 2016)
Dellew Corporation v. United States
855 F.3d 1375 (Federal Circuit, 2017)
Dell Federal Systems, L.P. v. United States
906 F.3d 982 (Federal Circuit, 2018)
Acetris Health, LLC v. United States
949 F.3d 719 (Federal Circuit, 2020)
Wellpoint Military Care Corp. v. United States
953 F.3d 1373 (Federal Circuit, 2020)