Calloway v. Bovis Lend Lease, Inc.

2013 IL App (1st) 112746
CourtAppellate Court of Illinois
DecidedOctober 17, 2013
Docket1-11-2746
StatusPublished
Cited by31 cases

This text of 2013 IL App (1st) 112746 (Calloway v. Bovis Lend Lease, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calloway v. Bovis Lend Lease, Inc., 2013 IL App (1st) 112746 (Ill. Ct. App. 2013).

Opinion

ILLINOIS OFFICIAL REPORTS Appellate Court

Calloway v. Bovis Lend Lease, Inc., 2013 IL App (1st) 112746

Appellate Court HERMAN CALLOWAY, JR., and GWEN BROWN, Special Caption Administrator of the Estate of Herman Calloway, Sr., Deceased, Plaintiffs-Appellees, v. BOVIS LEND LEASE, INC., Defendant- Appellant.

District & No. First District, Fifth Division Docket No. 1-11-2746

Filed August 16, 2013 Rehearing denied October 3, 2013

Held In a consolidated action arising from an accident in which a father was (Note: This syllabus killed and his son was severely injured when a trench at a construction constitutes no part of site collapsed, the trial court properly denied the construction manager’s the opinion of the court motion for a judgment n.o.v. or a new trial, since no basis existed to but has been prepared disturb the jury’s finding that the construction manager owed a duty of by the Reporter of care to the deceased and his son, the accident was a foreseeable result of Decisions for the the failure of the construction manager’s superintendent to stop the convenience of the deceased and his son from working in the trench without protection, the reader.) jury’s disparate findings on contributory negligence were not against the manifest weight of the evidence, and the award of damages was not excessive.

Decision Under Appeal from the Circuit Court of Cook County, Nos. 05-L-8589, 06-L- Review 2005; the Hon. Clare E. McWilliams, Judge, presiding.

Judgment Affirmed. Counsel on Cremer, Spina, Shaughnessy, Jansen & Seigert, LLC, of Chicago (Francis Appeal A. Spina, Heather Kingery, and Patrick J. Giese, of counsel), for appellant.

Michael W. Rathsack, of Chicago (Allen N. Schwartz, Amanda L. Brasfield, Craig P. Mannarino, and Michael W. Rathsack, of counsel), for appellee Herman Calloway, Jr.

O’Connor & Nakos, Ltd., of Chicago (D. Jeffrey Comeau, of counsel), for appellee Gwen Brown.

Panel JUSTICE PALMER delivered the judgment of the court, with opinion. Presiding Justice McBride and Justice Howse concurred in the judgment and opinion.

OPINION

¶1 This appeal arises out of consolidated injury and wrongful death lawsuits. At all relevant times, the Community Unit School District 200 (the District) engaged various entities for a construction project located at Wheaton-Warrenville South High School (the project). The District hired defendant Bovis Lend Lease as the construction manager for the project. The District also contracted with DuPage Top Soil, which then subcontracted with Hamilton Construction (Hamilton) for the installation of underground sewer and storm pipes.1 On June 6, 2005, two of Hamilton’s employees, father and son Herman Calloway, Sr. (Senior), and Herman Calloway, Jr. (Junior), were working in a trench as part of Hamilton’s work on the project. The trench collapsed, killing Senior and injuring Junior. Plaintiffs, Junior and Gwen Brown, special administrator of Senior’s estate (the Estate), each brought a negligence action against Bovis and the cases were consolidated for trial. A jury returned a verdict in favor of Junior in the amount of $8,587,591.97, subject to a setoff of $406,915.85. The jury also returned a verdict in favor of the Estate, awarded it $1,020,000 subject to a $97,275 setoff and found that Senior was 49% contributorily negligent. The $1,020,000 represented the recoverable damages awarded after the Estate’s total damages of $2 million were reduced by the percentage of negligence attributed to Senior. ¶2 On appeal, Bovis contends that the trial court erred in denying its motion for judgment

1 DuPage Top Soil is not a party to this appeal, having been dismissed from the case prior to trial.

-2- notwithstanding the verdict and in failing to grant Bovis a new trial. For the reasons that follow, we affirm. ¶3 In its capacity as construction manager, Bovis was responsible for coordinating day-to- day activities on the project, including the work of all contractors and subcontractors. On the day of the accident, Hamilton was digging a trench to install a sewer line. The process typically involved a backhoe digging a trench and then a hole in the trench in which a trench box was to be placed. A trench box is a wooden or metal box that is placed in the trench in order to provide protection for workers against a trench collapse. The trench box is put in the trench and then a stone base is placed in the bottom of the trench. A backhoe is used to place the sewer pipes on top of the stone base. Workers are required to be in the trench to level or hand-grade the stone base, to detach the sewer pipes from the backhoe and to connect the segments of sewer pipe together inside the trench. On the day of the accident, the trench being dug had intersected with markings indicating a buried electric line. Work had stopped while the Hamilton crew attempted to locate the cable. It was at some point during this process that Junior and Senior were in the trench without a trench box when the trench collapsed. With this background in mind, we set forth the evidence presented at trial. ¶4 Jim Blowers was the senior superintendent for Bovis at the time of the accident. He testified that Bovis was the construction manager and that in that role it coordinated the day- to-day activities at the construction site. As the senior superintendent, Blowers was assigned to coordinate activities on the project and was at the site daily. Blowers was responsible for “the whole site” and walked the site daily to check on the progress of the contractors and subcontractors. He typically did not have the authority to direct the manner, method or means of a subcontractor’s work and left those decisions to the subcontractor. However, Blowers had the authority to stop unsafe work that he observed. If he saw a subcontractor not following proper procedure or doing something unsafe, he would stop the activity and have a discussion with the foreman about his concerns and how the task could be done differently. ¶5 Blowers testified that Bovis provided a safety orientation to all subcontractors and contractors who worked on the project. The orientation involved reading through documentation, talking about specific things related to the project, reviewing a general list of “basic common sense rules” appropriate for the project and then watching a 15-minute safety video. Part of the documentation distributed to all workers on the project was a 34- page site-specific “Safety Plan” that Bovis expected all contractors and subcontractors to follow. Bovis superintendents were responsible for ensuring that all contractors and subcontractors followed that safety plan. Bovis also distributed a project orientation to all subcontractors and contractors. The orientation contained, among other things, a “trenching” section that Bovis expected all subcontractors to follow. That section stated that when working in a trench over five feet deep, all workers were required to use a “trench box” or to “slope” the side of the trench to avoid injury resulting from a trench collapse. Enforcement of the provisions in the orientation was within the scope of Blowers’ job duties. ¶6 Blowers also testified that all of his contact with Hamilton was through Senior. Blowers and Senior met each morning to discuss the tasks Hamilton was going to perform and to ensure that Blowers and Senior were “on the same page.” When Blowers arrived at site on the morning of the accident, he spoke with Senior about Hamilton’s plan to dig a north-south

-3- trench that day in order to lay sewer lines. Blowers told Senior to use proper trenching equipment because of the importance of safety. Senior did not mention that he planned to work without a trench box that day. Blowers left to check on work being done inside the school but returned later that morning and saw that work had begun on the north-south trench.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Layko Properties v. M-OK Distribution, Inc.
2026 IL App (3d) 220269-U (Appellate Court of Illinois, 2026)
Cohoon v. Crowe
2024 IL App (5th) 240100-U (Appellate Court of Illinois, 2024)
Wilson v. University of Chicago Medical Center
2023 IL App (1st) 230078 (Appellate Court of Illinois, 2023)
In re Commonwealth Edison Co. Illinois Consumer Fraud Litigation
2023 IL App (1st) 220105 (Appellate Court of Illinois, 2023)
In re Estate of Rao
Appellate Court of Illinois, 2023
Prosise v. Bank of America, N.A.
2022 IL App (2d) 210109-U (Appellate Court of Illinois, 2022)
Dayton v. Pledge
2019 IL App (3d) 170698 (Appellate Court of Illinois, 2019)
Munoz v. Menard, Inc.
N.D. Illinois, 2019
Dahlstrand v. FCA US LLC
N.D. Illinois, 2019
Jefferson v. Mercy Hospital & Medical Center
2018 IL App (1st) 162219 (Appellate Court of Illinois, 2018)
Racky v. Belfor USA Group, Inc.
2017 IL App (1st) 153446 (Appellate Court of Illinois, 2017)
Cabrera v. ESI Consultants, Ltd.
2015 IL App (1st) 140933 (Appellate Court of Illinois, 2015)
McHale v. W.D. Trucking, Inc.
2015 IL App (1st) 132625 (Appellate Court of Illinois, 2015)
O'Gorman v. F.H. Paschen, S.N. Nielsen, Inc.
2015 IL App (1st) 133472 (Appellate Court of Illinois, 2015)
City of Des Plaines v. Metropolitan Alliance of Police Chapter No. 240
2015 IL App (1st) 140957 (Appellate Court of Illinois, 2015)
O'Gorman v. F.H. Paschen
2015 IL App (1st) 133472 (Appellate Court of Illinois, 2015)
In re Estate of Mankowski
2014 IL App (2d) 140154 (Appellate Court of Illinois, 2014)
Davis v. The City of Chicago
2014 IL App (1st) 122427 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2013 IL App (1st) 112746, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calloway-v-bovis-lend-lease-inc-illappct-2013.