Caldwell v. Knox Concrete Products, Inc.

391 S.W.2d 5, 54 Tenn. App. 393, 1964 Tenn. App. LEXIS 159
CourtCourt of Appeals of Tennessee
DecidedAugust 5, 1964
StatusPublished
Cited by49 cases

This text of 391 S.W.2d 5 (Caldwell v. Knox Concrete Products, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caldwell v. Knox Concrete Products, Inc., 391 S.W.2d 5, 54 Tenn. App. 393, 1964 Tenn. App. LEXIS 159 (Tenn. Ct. App. 1964).

Opinion

COOPER, J.

This appeal is from the action of the trial judge in directing a verdict for the defendant, Knox Concrete Products, Inc., in an action brought by Ethel R. Caldwell to recover property damage allegedly resulting from the defendant's manufacturing operations.

The plaintiff is the owner and operator of the Colonial Tourist Court on Kingston Pike in Knoxville, Tennessee. The defendant owns and operates a concrete products plant on the property adjoining plaintiff’s motel. In June, 1957, the defendant expanded its operations and constructed facilities for the making of concrete beams near the property line between plaintiff’s and defendant’s properties.

In her declaration, the plaintiff averred that noise from the expanded operations was of such nature and intensity that it materially interfered with the use and enjoyment of her property as a home and a motel and constituted an actionable nuisance.

The defendant filed a plea of not guilty, and specially plead the three year statute of limitations as a bar to the plaintiff’s action.

It was conceded by the plaintiff during the trial that she could recover only if the noise complained of consti *398 tuted a temporary nuisance, and that her damages, if any, would be limited to those occurring after March 14, 1960, since suit was not filed until March 14, 1963.

On motion of the defendant made at the conclusion of all the evidence, the Court peremptorily instructed the jury to return a verdict in favor of the defendant on the ground that there was no evidence upon which a jury verdict in favor of the plaintiff could be predicated. In doing so, the trial judge stated, among other things, that:

“As a matter of law this is shown to be, if a nuisance at all, a permanent nuisance; and more than three years having elapsed since it began * * * [June, 1957] * * * this case is barred by the Statute of Limitations of three years, and that the plaintiff cannot recover.”

Plaintiff filed a motion for new trial and, when it was overruled, appealed assigning the court’s action as error.

The record shows that the motel, now owned by the plaintiff was constructed in the early 1930’s. Plaintiff bought the motel property in 1953 and operated the motel with increasing success through 1957, catering to the commercial trade and those tourists who sought inexpensive but clean accommodations. Thereafter, the receipts from the business showed a marked decrease yearly until 1963, when plaintiff closed the motel.

The defendant company began operations in 1943 on a nine acre tract of land adjacent to plaintiff’s motel. The tract was zoned for industrial uses, and was in the midst of commercial activity, viz., restaurants with drive-in service, liquor stores, and a miniature golf course, many of which operated late at night.

In 1957 defendant expanded its plant and constructed three beam beds and two prestress beam beds adjacent *399 to plaintiff’s motel. These beds are used to form concrete beams and they range in length from 140 feet to 200 feet.A bnilding was constructed at the northern end of, the beds to honse materials and a heater with a pump attachment to circulate hot oil through the beam beds to aid in curing the concrete.

There is considerable noise attendant to the beam and prestress operation. In the normal cycle of operations, which began at 7:00 A.M. prior to the filing of this suit, one of the beds is stripped and poured in the morning and the other in the afternoon, each such process requiring approximately three and one-half to four hours for completion. In stripping a bed, defendant’s employes are required to remove metal bulkheads from the ends of the completed beams. This is done by hammering — metal on metal — for approximately 20 minutes. The beams are then removed by use of mechanical carriers referred to as Karry Kranes. After the bed is stripped, reinforcing-steel is installed for the next pour. The Karry Kranes are then used to bring the cement to the forms- where vibrators (some of which are electric and some of which use a 2% horsepower gasoline motor) are used to compact the concrete intermittently during the pouring process that requires one to one and one-half hours. After the concrete has been allowed to set for two or three hours, a heater is turned on to circulate hot oil through the forms for the purpose of properly completing the curing process. The gas-fired heater and the pump attachment are located in an open building and operate intermittently through most of each night following the pouring of the concrete beams.

*400 Plaintiff testified that the noises from these operations prevented her from renting her motel rooms, and caused her to lose patrons of many years standing.

Several of these patrons testified that their rest was disturbed by the noises, particularly those in the -early morning hours, and that they sought accommodations elsewhere.

The general manager of the defendant’s plant described the manufacturing operation in detail, and testified that the methods used were those generally used in the trade, and that while noise, of necessity, accompanied the manufacturing operations, it was not excessive. On cross-examination, the general manager testified that the noise could be reduced.

(1) by using a steel bar to loosen cargo in the railroad cars rather than by vibrating the car or by beating the side of the car with a sledge hammer;

(2) by cleaning concrete from the beam bed area by hand rather than by use of bulldozers;

(3) by locating the heater and pump away from the curing beds and plaintiff’s motel;

(4) by freeing the bulkheads used in the beam beds by the use of a steel bar rather than by hammering;

(5) by unloading the steel used in the beam beds at a location away from plaintiff’s motel; and

(6) by using electric vibrators in place of the gasoline propelled vibrators on the beam beds.

The general manager insisted, however, that the reduction of the noise would not be economical, and would impair the defendant’s position in a highly competitive market.

*401 The general manager farther testified that after the present snit was filed, the time of commencement of work in the concrete beam area was changed from 7:00 A.M. to 8:00 A.M.

Other employes of the defendant company were called to testify concerning the methods nsed by defendant in its mannfactnring operations, and to testify that the plaintiff had not complained of the noise prior to filing snit, except as to the noise from a warning whistle on the oil pnmp attachment, and that this had been corrected by the snhstitntion of a warning light.

The defendant also introduced in evidence the testimony of Mr. K. J. Coker, an industrial sound engineer, and Mr. J. W. Barnes. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DEAN SALEM v. NICK GALBRAITH
Court of Appeals of Tennessee, 2025
Noah Ryan v. Laverna Soucie
Court of Appeals of Tennessee, 2019
KMI Group, Inc. v. Wade Acres, LLC
Court of Appeals of Tennessee, 2019
Brent Ray v. Thomas Neff
Court of Appeals of Tennessee, 2018
Betsy Stibler v. The Country Club, Inc.
Court of Appeals of Tennessee, 2015
Velda J. Shore v. Maple Lane Farms, LLC
411 S.W.3d 405 (Tennessee Supreme Court, 2013)
Chandra Pearson v. Victor Ross
Court of Appeals of Tennessee, 2011
In Re Tennessee Valley Authority Ash Spill Litigation
805 F. Supp. 2d 468 (E.D. Tennessee, 2011)
1704 FARMINGTON, LLC v. City of Memphis
667 F. Supp. 2d 797 (W.D. Tennessee, 2009)
Sue Leggett v. Paul Allen Dorris
Court of Appeals of Tennessee, 2009
North Carolina Ex Rel. Cooper v. Tennessee Valley Authority
593 F. Supp. 2d 812 (W.D. North Carolina, 2009)
Robert W. Fink v. Fred M. Crean
Court of Appeals of Tennessee, 2006
David Manis, et ux. v. Kenneth Gibson, et ux.
Court of Appeals of Tennessee, 2006
George R. Caldwell, Jr., et ux v. PBM Properties
Court of Appeals of Tennessee, 2005
Anderson v. American Limestone Co., Inc.
168 S.W.3d 757 (Court of Appeals of Tennessee, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
391 S.W.2d 5, 54 Tenn. App. 393, 1964 Tenn. App. LEXIS 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caldwell-v-knox-concrete-products-inc-tennctapp-1964.