LEIGHTON H. LIPPERT v. B & D REAL ESTATE PROPERTIES, LLC

CourtCourt of Appeals of Tennessee
DecidedMarch 30, 2026
DocketE2024-01676-COA-R3-CV
StatusPublished
AuthorJudge Jeffrey Usman

This text of LEIGHTON H. LIPPERT v. B & D REAL ESTATE PROPERTIES, LLC (LEIGHTON H. LIPPERT v. B & D REAL ESTATE PROPERTIES, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LEIGHTON H. LIPPERT v. B & D REAL ESTATE PROPERTIES, LLC, (Tenn. Ct. App. 2026).

Opinion

03/30/2026 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 17, 2025 Session

LEIGHTON H. LIPPERT ET AL. v. B&D REAL ESTATE PROPERTIES, LLC

Appeal from the Circuit Court for Bradley County No. V-20-146 Judge J. Michael Sharp ___________________________________

No. E2024-01676-COA-R3-CV ___________________________________

A developer failed to use proper erosion control measures, resulting in recurring sediment runoff into a pond owned by neighboring landowners and increasing accumulation of sediment therein. The trial court concluded that developer’s actions constituted a temporary, not permanent, nuisance and awarded injunctive relief and damages. Damages for emotional distress were included among the damages the trial court awarded. The developer appeals, challenging the trial court’s finding as to proximate causation and asserting that its actions, if a nuisance, were a permanent and not temporary nuisance, and accordingly the landowners’ suit was barred by the statute of limitations. The developer also asserts that the trial court erred as to the remedies awarded, challenging both the injunctive relief and emotional distress damages. We affirm the trial court’s findings as to proximate causation and its conclusion that the nuisance is temporary. We also affirm the trial court’s imposition of an injunction. However, we reverse the award of damages for emotional distress based upon deficient pleading.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court for Bradley County Affirmed in Part; Reversed in Part

JEFFREY USMAN, J., delivered the opinion of the Court, in which JOHN W. MCCLARTY, P.J., E.S., and MICHAEL SWINEY, J., joined.

Ellis A. Sharp and Annie S. Duncan, Knoxville, Tennessee, for the appellant, B&D Real Estate Properties, LLC.

H. Franklin Chancey, Cleveland, Tennessee, for the appellees, Leighton H. Lippert and Richard D. Lippert, Sr.

OPINION I.

This appeal arises from a dispute between neighboring property owners regarding improper and insufficient erosion control methods used in a development project, resulting in recurrent sediment runoff as well as accumulation of sediment in a nearby private pond. Appellees Leighton H. Lippert and Richard D. Lippert, Sr. (the Lipperts) own residential real property located in McDonald, Tennessee. The property includes a 0.8-acre pond, which the Lipperts described as “perfect” prior to the events at issue. Appellant B&D Real Estate Properties, LLC, (B&D) is the developer of a subdivision that is located at a higher elevation and is across from the Lipperts’ property.

In developing the subdivision, B&D subdivided the property into residential lots and performed grading and excavation work. The Lipperts alleged that, because of improper control of runoff in connection with B&D’s development of the subdivision, significant amounts of dirt, silt, and earth washed from B&D’s property into a natural stream that feeds the Lipperts’ pond. They asserted that, following rainfall events, muddy, brown water from the development flowed into their pond.

The problems with the runoff began shortly after development commenced on B&D’s property. Mr. Lippert filed his first complaint with the Tennessee Department of Environment and Conservation (TDEC) in December 2016. In response, B&D took effective remedial measures in 2016 and 2017 regarding road stabilization and pipe repairs that temporarily resolved the runoff issues to the Lipperts’ satisfaction. However, as the development project progressed, this initial success and responsiveness did not continue. Consequently, in March 2020, the Lipperts filed a complaint in the Circuit Court for Bradley County. They advanced a nuisance claim against B&D.

During the pendency of the litigation, TDEC issued multiple notices of violation to B&D regarding sediment control failures. In January 2021, March 2022, and June 2022, TDEC cited B&D for allowing sediment-laden water to leave its development site and for inadequate Erosion Prevention and Sediment Control (EPSC) measures. The TDEC reports documented specific failures in erosion control measures, including cracked pipes and a lack of maintenance. One TDEC inspection report noted: “Sediment laden water is being discharged, by-passing EPSC measures. Color contrast in receiving waters downhill from outfall point.”

A bench trial was conducted on February 14, 2024, and April 2, 2024. The trial judge also conducted a site visit to the properties to observe the condition of the pond and the surrounding terrain. At trial, the court heard testimony from Leighton Lippert, who testified that he treated the pond with chemical flocculants and installed riprap rock in an attempt to mitigate the damage. Mr. Lippert described the stress of his “pristine” pond turning into a “muddy eyesore.” He testified that he had contacted government officials over 300 times in order to try to save his pond. The Lipperts introduced a Solitude Lake

-2- Management report estimating the pond contained 1,091 cubic yards of sediment. The deepest accumulation was on the south side of the pond, away from the development; however, there was substantial buildup at the point of the pond nearest the development. During the trial, Mr. James Brown, who prepared the report, testified regarding the remediation, estimating that the cost of removal of sediment for the pond could range from $50,000 to “a couple hundred thousand dollars.”

B&D presented the testimony of Alan Ogle, a civil engineer and private consultant hired by B&D to perform erosion analysis and inspections. Mr. Ogle admitted that turbidity in the Lipperts’ pond was caused, at least partially, by runoff from B&D’s development. He also noted that “the discoloration following a rain entering Mr. Lippert’s pond was primarily coming from runoff from this development.” He acknowledged that during his inspections, he observed deficiencies in B&D’s erosion controls, such as unstabilized dirt piles and silt fences needing maintenance. Mr. Ogle identified specific, reasonable measures B&D could take to mitigate or eliminate the sediment runoff, including modifying the existing sediment basin, installing baffles to reduce sediment discharge, installing a retention basin below the sediment pond, and utilizing flocculants. While acknowledging that runoff from the development caused the discoloration, Mr. Ogle contended that leaf debris from surrounding hillsides was another major contributor to the sediment accumulation.

In August 2024, the trial court entered an order finding that B&D created a temporary nuisance due to ineffective EPSC measures resulting in the accumulation of sediment in the Lipperts’ pond. The court found that the nuisance was “created by the defendant . . . due to the defendant’s negligent operation . . . on their property.” The court determined that the nuisance was a temporary rather than a permanent nuisance, which was a matter of consequence in terms of whether the Lipperts had filed within the statute of limitations. As to abating the nuisance, the trial court required B&D to “take erosion control measures on its property that should be outlined by the defendant’s expert, and approved by the appropriate governmental agency.” The trial court specifically noted failures regarding B&D’s sediment control basin. In accordance therewith, the trial court required employment of

an appropriate engineer to perform the necessary studies, and ultimately to make the necessary design to address the impact not only of the existing drainage but needed drainage in the future. This should include what impact, if any, future development will have on the existing watershed affecting the plaintiffs’ pond. The defendant shall implement the recommendations of the appropriate engineer’s study and/or governmental requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ronald and Sherry Windrow v. Middle Tennessee Electric Membership Corporation
376 S.W.3d 733 (Court of Appeals of Tennessee, 2012)
Newcomb v. Kohler Co.
222 S.W.3d 368 (Court of Appeals of Tennessee, 2006)
Anderson v. American Limestone Co., Inc.
168 S.W.3d 757 (Court of Appeals of Tennessee, 2004)
Hardcastle v. Harris
170 S.W.3d 67 (Court of Appeals of Tennessee, 2004)
Sneed v. Board of Professional Responsibility
301 S.W.3d 603 (Tennessee Supreme Court, 2010)
Lane v. WJ. Curry & Sons
92 S.W.3d 355 (Tennessee Supreme Court, 2002)
Pryor v. Willoughby
36 S.W.3d 829 (Court of Appeals of Tennessee, 2000)
Brown v. Erachem Comilog, Inc.
231 S.W.3d 918 (Tennessee Supreme Court, 2007)
Lacy v. Cox
152 S.W.3d 480 (Tennessee Supreme Court, 2004)
Clabo v. Great American Resorts, Inc.
121 S.W.3d 668 (Court of Appeals of Tennessee, 2003)
Pate v. City of Martin
614 S.W.2d 46 (Tennessee Supreme Court, 1981)
Lance Productions, Inc. v. Commerce Union Bank
764 S.W.2d 207 (Court of Appeals of Tennessee, 1988)
Caldwell v. Knox Concrete Products, Inc.
391 S.W.2d 5 (Court of Appeals of Tennessee, 1964)
Mitchell v. Mitchell
876 S.W.2d 830 (Tennessee Supreme Court, 1994)
Kenneth E. King v. Anderson County, Tennessee
419 S.W.3d 232 (Tennessee Supreme Court, 2013)
Lasater Lumber Co. v. Harding
189 S.W.2d 583 (Court of Appeals of Tennessee, 1944)
Regions Bank v. Thomas D. Thomas
532 S.W.3d 330 (Tennessee Supreme Court, 2017)
Blackard v. Hercules, Inc.
17 F. Supp. 3d 576 (S.D. Mississippi, 2014)
Burson v. Cox
65 Tenn. 360 (Tennessee Supreme Court, 1873)

Cite This Page — Counsel Stack

Bluebook (online)
LEIGHTON H. LIPPERT v. B & D REAL ESTATE PROPERTIES, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leighton-h-lippert-v-b-d-real-estate-properties-llc-tennctapp-2026.