East Tennessee Natural Gas Co. v. Peltz

270 S.W.2d 591, 38 Tenn. App. 100, 1954 Tenn. App. LEXIS 106
CourtCourt of Appeals of Tennessee
DecidedMarch 18, 1954
StatusPublished
Cited by33 cases

This text of 270 S.W.2d 591 (East Tennessee Natural Gas Co. v. Peltz) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Tennessee Natural Gas Co. v. Peltz, 270 S.W.2d 591, 38 Tenn. App. 100, 1954 Tenn. App. LEXIS 106 (Tenn. Ct. App. 1954).

Opinion

HOWARD, J.

Referring to the parties as they appeared below, the plaintiffs, Peter Peltz and wife, Bridget Peltz, filed this action against the defendants, East Tennessee Natural Gras Company, hereinafter referred to as Gas Company, and John Oman III and Stirton Oman, *107 co-partners doing business as tbe Oman Construotion Company, for damages for tbe alleged destruction of a concrete dam caused by tbe blasting operations conducted by tbe defendant, Oman Construotion Company, upon tbe right-of-way of tbe Gas Company, wbile laying a 22 inch natural gas transmission line referred to as tbe Green-brier-Oak Ridge line, and for tbe casting of debris, rocks, etc., upon tbe property of tbe plaintiffs adjacent to tbe right-of-way.

At tbe time tbe matters herein arose tbe Gas Company, a corporation organized and existing under tbe laws of tbe State of Tennessee with its principal office at Knoxville, was engaged in supplying and tbe distribution of natural gas throughout East Tennessee. The Oman Construction Company maintained its office at Nashville, Tennessee, and at the time was under a contract with tbe Gas Company to construct the gas line in question.

Plaintiffs are residents of Morgan County, Tennessee, where they have lived for more than 33 years, having moved into said County in 1919 from tbe State of Pennsylvania, where Peltz bad worked previously for 8 years as a coal miner. They are of Polish descent, self educated, frugal and ambitious, and by their efforts have acquired ownership of several hundred acres of farm and timber lands located in tbe 7th Civil District of Morgan County, near tbe Village of Deer Lodge about 14 miles west of Wart-burg, tbe County Seat. Plaintiffs acquired their land by tbe purchase of 8 separate tracts purchased at different times, but only 4 are mentioned in tbe record. They are (1) tbe 100 acre tract on which tbe family residence was located; (2) a 50 acre tract about % mile away upon which the dam involved herein was erected; (3) a 40 acre tract and (4) a 50 acre tract adjacent to each other, and abut *108 ting the 50 aere “dam tract” on the northeast. The tracts 2, 3 and 4 were unfenced, uncultivated and had no improvements on them except the dam, which was erected by the plaintiffs in 1948,1949. The Gas Company’s pipe line right-of-way passed through tracts 3 and 4, and at its nearest point was about 1500 feet from the dam and approximately 700 feet from the water line of the lake.

In 1945, before Peltz decided to erect the dam, he contacted M. P. Gowder, State Engineer with the Agriculture Extension Service at the University of Tennessee Farm in Knoxville, whose duties were to assist farmers in the solution of their problems. At Peltz’s request Gowder visited the dam site, where, assisted by Peltz and Charlie Edwards, the then County Agent of Morgan County, he made a survey and preliminary estimate of the cost. Later, Gower prepared plans and specifications for the dam. The plans, completed in 1946, called for a masonry and concrete dam with expansion and contraction joints at 4 points. These joints were between the spillways and wing-walls and the spillways and the center pier. The plans specified wingwalls 24 inches thick with footings at the base of the dam 16 inches thick, in solid rock to prevent seepage. The specifications for the concrete called for a mixture or formula of 1-2-4, meaning 1 bag of cement, 2 bags of sand and 4 bags of aggregate or gravel, reinforced by steel of % inch or larger. After studying the plans Peltz abandoned the idea of using masonry and decided to build the dam of solid concrete.

Before starting construction of the dam Peltz, assisted by the members of his family, his neighbors and hired labor, removed all the trees and cleared the basin for the lake, and with a bulldozer removed the surface dirt and everything down to solid rock on which the dam was to be *109 constructed. Three branches assured an ample supply of water, and it was admitted that the sité selected was an ideal location for the dam. Plaintiffs started construction of the dam in February, 1948 and completed it in May, 1949, the basin filling completely by the following June.

The dam was described as having an upstream wall about 206 feet in length and a downstream wall about 156 feet in length. At the north end of the structure there were two parallel walls each 26 inches in thickness, and these walls extended south to a spillway section, at which point the walls were approximately 20 feet high. The spillway section consisted of two solid monolithic blocks of concrete, each 10 feet wide and 18 feet high. They were 10 feet in thickness at the base and tapered to about 4 feet in thickness at the top. One of these was on each side of a center pier which was approximately 4 feet wide. At the south end of the south spillway section two parallel walls of concrete, each 26 inches in thickness, extended for a distance of 81 feet to the south hank of the ravine. The space between these two walls was supposed to have been filled in with crushed stone, but had been only partially filled at the time of the failure. That part of the dam which failed consisted of 25% feet of the 81 foot south.section of the darn, and on the night of October 31,1949, this portion washed out.

On July 11,1949, the plaintiffs executed a deed granting the Gas Company a 50 foot right-of-way across tracts 3 and 4, for the purpose of extending the Greenbrier-Oak Ridge gas line then under construction, and subsequently, in preparation for the laying of the gas line, the defendant, Oman Construction Company, dug a trench approximately 40 inches wide down to the rock along the center of the Gas Company’s 50 foot right-of-way at a point about *110 1500 feet east of plaintiffs ’ dam where it crossed one of the branches that flowed into the lake. By the nse of wagon drills with bits 2% inches in diameter, two lines of holes were then drilled into the exposed rock in the trench. These holes were staggered and were about 3 feet apart and ranged in depth from 6 to 8 feet, and the lines extended for a considerable distance beyond the branch on each side. The holes were then packed with 40% dynamite, using 5 or 6 sticks to the foot, for a distance estimated at from 700' to 800 feet, and by the use of a battery the complete charge, ranging from one and one-half to two tons, was set off in one blasting on the morning of September 21st.

Plaintiffs ’ declaration was in 4 Counts, the first Count alleging in substance that the plaintiffs had constructed a concrete dam at great expense, that the defendants used excessive charges of dynamite in their blasting operations, which were negligently done, and that the defendants failed to exercise the necessary care to protect plaintiff s ’ property. The second Count alleged that the defendants did not confine their operations and blasting activities to the 50 foot right-of-way, but unnecessarily encroached upon plaintiffs’ property. The third Count alleged that the defendants, in causing the damage to the dam, committed a trespass upon plaintiffs ’ property, and the fourth Count charged that the defendants, in using high explosives, were insurers for damages resulting therefrom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks Monypeny v. Chamroeun Kheiv
Court of Appeals of Tennessee, 2015
State of Tennessee v. Raymond Buford
Court of Criminal Appeals of Tennessee, 2012
Dale Anthony Scott v. Marion Yarbro
Court of Appeals of Tennessee, 2005
Stroud v. Seaton
Court of Appeals of Tennessee, 1998
City of Little Rock v. McIntosh
892 S.W.2d 462 (Supreme Court of Arkansas, 1995)
State v. Anderson
880 S.W.2d 720 (Court of Criminal Appeals of Tennessee, 1994)
Betty v. Metropolitan Government of Nashville
835 S.W.2d 1 (Court of Appeals of Tennessee, 1992)
Blevins v. Johnson County
746 S.W.2d 678 (Tennessee Supreme Court, 1988)
Miller v. Alman Construction Co.
666 S.W.2d 466 (Court of Appeals of Tennessee, 1983)
Edwards v. State
540 S.W.2d 641 (Tennessee Supreme Court, 1976)
Speight v. Gibbs
486 S.W.2d 922 (Court of Appeals of Tennessee, 1972)
Sparkman v. State
469 S.W.2d 692 (Court of Criminal Appeals of Tennessee, 1970)
Johnson v. King
426 S.W.2d 196 (Tennessee Supreme Court, 1968)
First American National Bank v. Tennessee Gas Transmission Co.
428 S.W.2d 35 (Court of Appeals of Tennessee, 1967)
Williams v. Southern Railway Co.
417 S.W.2d 573 (Court of Appeals of Tennessee, 1966)
Scott v. Columbia Gulf Transmission Co.
405 S.W.2d 784 (Court of Appeals of Tennessee, 1965)
Caldwell v. Knox Concrete Products, Inc.
391 S.W.2d 5 (Court of Appeals of Tennessee, 1964)
Chambers v. Bradley County
384 S.W.2d 43 (Court of Appeals of Tennessee, 1964)
Tapoco, Inc. v. Peterson
373 S.W.2d 605 (Tennessee Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
270 S.W.2d 591, 38 Tenn. App. 100, 1954 Tenn. App. LEXIS 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-tennessee-natural-gas-co-v-peltz-tennctapp-1954.