Buda v. State

198 Misc. 165, 97 N.Y.S.2d 37, 1950 N.Y. Misc. LEXIS 1612
CourtNew York Court of Claims
DecidedApril 28, 1950
DocketClaim No. 28688
StatusPublished
Cited by4 cases

This text of 198 Misc. 165 (Buda v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buda v. State, 198 Misc. 165, 97 N.Y.S.2d 37, 1950 N.Y. Misc. LEXIS 1612 (N.Y. Super. Ct. 1950).

Opinion

Sylvester, J.

Claimant seeks to recover damages for the flooding of his farm situated north of the village of Canastota, in the town of Lenox, Madison County. His property consisted of thirty-eight acres of so-called muck land, which were drained by eight lateral and two main ditches flowing into Colton Ditch and thence into Cowaselon Creek. It is asserted that the flooding of claimant’s land was caused by the negligent manner in which the State reconstructed the Cowaselon Creek Aqueduct which carries the waters of the Brie Canal over the Cowaselon Creek at a point four and one-half miles southeast of claimant’s property. Damages have been stipulated at $8,000.

The Cowaselon Creek flows from its headwaters in the town of Peterboro, southeast of Canastota, in a generally northerly and northwesterly direction through the village of Canastota, and empties into Oneida Lake on the north. The Brie Canal, whose waters are also claimed to have contributed to the flooding of claimant’s farm, flows in a generally westerly direction through the village of Canastota feeding into the Barge Canal at New London.

The Cowaselon Creek Aqueduct was, at the time in question, a wooden structure, with its trough or'flume resting upon two stone abutments at either side of the Cowaselon Creek and upon a stone pier in its center, the waters of the Cowaselon Creek being carried beneath the aqueduct through the two culverts thus formed.

For some time prior to 1947, the aqueduct had been in very poor condition, making it difficult to retain water in the flume. In compliance with its duty to maintain the canals in good condition (Canal Law, § 10), the State Department of Public Works awarded a contract on January 21, 1947, which, by its terms, required the wooden trough and walls of the old aqueduct to be [167]*167replaced by concrete structures. Work was begun on January 28, 1947, but was delayed from time to time thereafter as a result of severe storms and freezing conditions. In the course of the work, the contractor found it necessary to build a small cofferdam across the Erie Canal at a point 1.12 miles west of the aqueduct for the purpose of retaining the canal waters so that the reconstruction work could proceed. On May 22, 1947, when the initial flood occurred, the east floor of the aqueduct had been completed and the wall forms for the east half of the aqueduct were in place. However, the west opening of the aqueduct being entirely exposed, there was nothing to prevent the waters of the Erie Canal from flowing into the Cowaselon Creek.

Heavy rains fell in the Canastota area and in neighboring sections of the State on May 21, 1947, with the result that muck lands in Borne, New York, were flooded. There were five inches of water in the streets of Oneida, New York, with flood conditions prevailing in near-by areas. The proof shows that there was rain in the Canastota area every day between May 1st and May 9th; that it rained again on May 14th, with additional precipitation every day from May 17th to May 21st. In the early morning of May 22d, the Cowaselon Creek overflowed its banks in Canastota and flooded claimant’s property to a depth of approximately sixteen inches. Heavy rainfalls again occurred on June 2d and 3d, 1947, with the result that on June 3d the Cowaselon Creek once more overflowed and claimant’s property was again flooded.

The issue here is whether these floods were caused by the heavy rainfalls which have been described, as the State contends, or, as claimant insists, by the manner in which the aqueduct was reconstructed.

According to claimant, the walls of the aqueduct, which were approximately seven feet high, served as a retention dam for the waters of Cowaselon Creek as they intersected the Erie Canal. Thus, as the waters of the Cowaselon, swollen by the heavy rains, reached a point above the floor of the canal, approximately four feet above the channel bed, the flow of the creek would have been impeded by these aqueduct walls. It is said that the waters of the creek would then have been impounded and that the flooding of claimant’s property would have been prevented.

Contending, accordingly, that the aqueduct walls protected his property against floods, claimant urges that the aqueduct [168]*168should have been constructed in such a manner as to retain in place at all times either the south or the north wall of the aqueduct, and evidence was adduced tending to establish that the aqueduct could have been so constructed. Claimant also urges that the aqueduct could have been completed prior to May 22, 1947, had the proper materials been used.

The State, on the other hand, urges that the aqueduct was properly constructed and that it could not have been completed prior to May 22, 1947, by the exercise of reasonable diligence. It argues also that the completed construction, in any event, would not have protected claimant’s property against the flooding which, it says, was the sole result of the heavy rainfalls in the area, for which the State has no responsibility.

The factual issues to be resolved are twofold:

1. Was the aqueduct properly reconstructed?

2. Had the aqueduct been intact on May 22 and June 3, 1947, would claimant’s property have been flooded?

With respect to the construction of the aqueduct, the procedure actually followed was to remove the old aqueduct, including the floor and walls. The cement floor of the east half was then laid and the corresponding concrete walls erected. Upon the completion of the east half of the aqueduct, a similar procedure was followed in the reconstruction of the west half. Performance of the.work in this manner necessitated the complete removal of the old aqueduct prior to the commencement of the new construction. Claimant sought to establish by the testimony of an engineer, that the aqueduct could have been reconstructed in quarters, so that one of the aqueduct walls „ would be in place at all times. The procedure outlined by this witness would have enabled the removal of the west half of the north wall of the aqueduct together with the removal of half the floor on that side. This would permit the entire south wall and the east half of the north wall to remain intact. Upon completion of the construction of the new wall and half of the new floor, the same procedure would obtain with respect to the remaining half of the north side of the aqueduct. When that was accomplished, the same procedure would be followed in connection with the construction of the south wall of the aqueduct. Though this plan might have been feasible, there is no evidence of any instance where such a method was employed in aqueduct construction. The witness, in fact, admitted that he had never seen an aqueduct so constructed nor had he ever read of this method in any engineering text. It was, nevertheless, his [169]*169opinion that it was well adapted to afford maximum protection against flash floods.

The State, on the other hand, proffered the evidence of its experts to establish that the method actually adopted was in accord with sound engineering practice and generally followed in such cases. There was evidence that the type of construction suggested by claimant’s expert would have left a longitudinal seam in the flume of the canal, where leakage was likely, as contrasted with the more desirable horizontal joint over the central pier.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doundoulakis v. Town of Hempstead
51 A.D.2d 302 (Appellate Division of the Supreme Court of New York, 1976)
Waldo v. State
2 A.D.2d 730 (Appellate Division of the Supreme Court of New York, 1956)
Annin v. State
206 Misc. 24 (New York State Court of Claims, 1954)
Buda v. State
278 A.D. 424 (Appellate Division of the Supreme Court of New York, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
198 Misc. 165, 97 N.Y.S.2d 37, 1950 N.Y. Misc. LEXIS 1612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buda-v-state-nyclaimsct-1950.