Reed v. . the State

15 N.E. 735, 108 N.Y. 407, 13 N.Y. St. Rep. 815, 63 Sickels 407, 1888 N.Y. LEXIS 597
CourtNew York Court of Appeals
DecidedFebruary 28, 1888
StatusPublished
Cited by30 cases

This text of 15 N.E. 735 (Reed v. . the State) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed v. . the State, 15 N.E. 735, 108 N.Y. 407, 13 N.Y. St. Rep. 815, 63 Sickels 407, 1888 N.Y. LEXIS 597 (N.Y. 1888).

Opinion

Rugeb, Oh. J.

Prior to the year 1873 the state became the owner of about 160 acres of land in the town of Lafayette, Onondaga county, lying in a valley on both sides of Butternut creek. For the purpose of providing a feeder for the Erie canal it proceeded, through its own agents, without the intervention of contractors, to construct a dam across the valley, by which means a large body of water, covering about sixty or seventy acres of land to a depth of thirty feet or less, was. collected in a reservoir, and there retained and used, as occasion required, for the canal. In the course of the construction of the reservoir a large bed of coarse gravel, lying on the westerly side of the dam and extending over four or five acres of land, was uncovered and denuded of soil and earth and left exposed directly to the action of the water upon it. This bed of gravel lay about four or five feet below the level of the spill-way of the dam, and when that was filled, large quantities, of water flowed through the gravel, by subterraneous channels and discharged itself upon the lands of the claimant and others lying below the dam, and inflicted serious damage thereto. The water was first let into the dam in 1874 or 1875, and immediately thereafter appeared upon the premises described, and has so continued to appear and to injure the claimant’s land each year since. This claim was filed with the Board of Appraisers in 1879, and was transferred, together with other claims, to the Board of Claims, when that body was created by statute in 1883. Upon the trial the Board of Claims, besides finding the facts above stated also found that the reservoir, dam and embankment were constructed, maintained and operated with great care and diligence on the part of the state, its officers, agents and servants, and that it does not appear that *411 the damage to lands of claimant is permanent, nor does the amount of any temporary damage he may have sustained appear. As a conclusion of law it found that the state was not bound to assume that a deposit of gravel extended beneath the surface, from the land inside of said reservón1, across other lands, and at a distance of over one hundred rods, to the land of claimant, and to provide absolutely against the percolation of the water from the reservoir through the same,” and,, therefore, they awarded the claimant, nothing.

We are of the opinion that the undisputed evidence in the case shows that the board erred in exempting the state from the imputation of negligence in the construction of the reservoir and its embankments.

The liability assumed by the state under chapter 321 of the Laws of 1810, embraces all cases of damage occurring to-corporations and individuals from the use or management of the canals of the state, or resulting or arising from the negligence or conduct of any officer of the state having charge thereof, or from any accident or other matter or thing connected with the canals in a case where the facts proved would create a legal liability against the state, were the same established in evidence in a court of justice against an individual or corporation, and providing that it is not a case of damages arising from the navigation of the canals. In cases arising under this statute the state-is therefore to be regarded as occupying the same position as an individual, and the inquiry is solely whether the facts proved would render an individual liable if established against him. The situation of the gravel bank skirting the western embankment of the reservoir was plainly visible to every one, and was known to the agents of the state while prosecuting the work of construction. Instead of taking-precautions to avoid leakage at this point they continued the work of denudation until many acres were exposed to the action of the water. That water, however situated, will seek its level through any channel open to it is a natural law, with which every one is familiar and could not ha've been unknown to the' officers having charge of this work. The attempt to collect a- *412 large body of water into a limited space surrounded with a porous and gravelly soil, without taking adequate precaution to confine it to the receptacle prepared fan it, was, upon the face of it, an inexcusable act of negligence in those having charge of such work, and cannot be justified under the known laws governing the motion of fluids. (Pixley v. Clark, 35 N. Y. 520; Jutte v. Hughes, 67 id. 267; Mairs v. Manhattan R. E. Assn., 89 id. 506.)

Indeed one of the state engineers upon the work testified that when they were uncovering the bank on the western side of the reservoir, he observed they were getting into a bed of •coarse gravel, and that it might leak if they went deeper. Another engineer employed in superintending the construction •stated that he observed what was going on in regard to this gravel bed, and told the canal commissioner in charge of the work, that he didn’t think they would be able to keep any water •in the reservoir above this point. He further testified that the effect of removing the soil and earth from the gravel was to open a channel where all of the water from the reservoir might run out, but that if it had been “ suitably lined with •clay a large body of which was found within the limits of the reservoir, it would not leak.”

The only excuse suggested by the engineers for not lining it was the large expense which the state would incur by doing so. 'The officers of the state seem to have proceeded with their work, well knowing that they had exposed sub-surface channels of vast extent through which the collected waters of the reservoir must flow off and discharge at some point, when its level was reached. That they did not know it would flood the land of the claimant was entirely immaterial, since they must have known that it would discharge upon somebody’s land and was hable to inflict damage thereto.

There was no evidence that conflicted in any way with the facts stated, and the only attempt to palliate its force was made by calling one of the engineers of the canal department to testify to his opinion that the work of building the dam •and reservoir was done according to the plans and specifica *413 tians ]Sio plans and specifications were produced on the trial, and the witness does not state that he ever saw them. One of the engineers testified that there were no specifications relating to the exposed gravel. The witness was permitted, under such circumstances, to state that the work was performed by the officers of the state with great care, and the dam was constructed in a good, safe and workman-like manner. Such testimony does not produce a conflict of evidence upon the point in dispute, within the meaning of the rule precluding this court from reviewing a question of fact; on the contrary it leaves the facts unanswered and undisputed, and the legal conclusion to be predicated thereon a question of law alone. In a case quite analogous to this, which came to this court from the Board of Claims, its conclusion of fact in regard to the liability of the state for damages occasioned by percolations of water through the banks of the canal, from defective precautions to restrain such waters, was just the reverse of that arrived at in this case.

In Clements v. The State (105 N. Y.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capruso v. Village of Kings Point
16 N.E.3d 527 (New York Court of Appeals, 2014)
Amax, Inc. v. Sohio Industrial Products Co.
121 Misc. 2d 814 (New York Supreme Court, 1983)
Dimovitch v. State
33 A.D.2d 146 (Appellate Division of the Supreme Court of New York, 1969)
Buda v. State
198 Misc. 165 (New York State Court of Claims, 1950)
Salvi v. John A. Manning Paper Co.
168 Misc. 661 (New York Supreme Court, 1938)
Hartzell v. Village of Hamburg
155 Misc. 345 (New York Supreme Court, 1935)
Cashin v. City of New Rochelle
176 N.E. 138 (New York Court of Appeals, 1931)
MacKay v. Breeze
269 P. 1026 (Utah Supreme Court, 1928)
Calvert v. Anderson
236 P. 847 (Montana Supreme Court, 1925)
Healey v. Citizens Gas & Electric Co.
201 N.W. 118 (Supreme Court of Iowa, 1924)
Harrison v. State
121 Misc. 861 (New York State Court of Claims, 1923)
Kall v. Carruthers
211 P. 43 (California Court of Appeal, 1922)
Dufel v. State
198 A.D. 97 (Appellate Division of the Supreme Court of New York, 1921)
Burt Olney Canning Co. v. . State
130 N.E. 574 (New York Court of Appeals, 1921)
Longmire v. Yelm Irrigation District
195 P. 1014 (Washington Supreme Court, 1921)
Meruk v. . City of New York
119 N.E. 571 (New York Court of Appeals, 1918)
Sundstrom v. . State of New York
106 N.E. 924 (New York Court of Appeals, 1914)
North Sterling Irrigation District v. Dickman
59 Colo. 169 (Supreme Court of Colorado, 1914)
Wheeler v. Town of St. Johnsbury
87 A. 349 (Supreme Court of Vermont, 1913)
Kimberly-Clark Co. v. Patten Paper Co.
140 N.W. 1066 (Wisconsin Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
15 N.E. 735, 108 N.Y. 407, 13 N.Y. St. Rep. 815, 63 Sickels 407, 1888 N.Y. LEXIS 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-v-the-state-ny-1888.