Broomfield Senior Living Owner, LLC v. R.G. Brinkmann Co

2017 COA 31, 413 P.3d 219
Colorado Court of Appeals·Decided March 9, 2017·No. 16CA0101·Published·Cited by 21 cases

Opinion

COLORADO COURT OF APPEALS 2017COA31

Court of Appeals No. 16CA0101 City and County of Broomfield District Court No. 14CV30139 Honorable C. Scott Crabtree, Judge

Broomfield Senior Living Owner, LLC, a Delaware limited liability company; and Sunrise Development, Inc., LLC, a Virginia corporation,

Plaintiffs-Appellants, v.

R.G. Brinkmann Company, d/b/a Brinkmann Constructors, a Missouri corporation,

Defendant-Appellee.

JUDGMENT REVERSED AND CASE REMANDED WITH DIRECTIONS

Division V

Opinion by JUDGE FREYRE

Ashby, J., concurs

Davidson*, J., specially concurs

Announced March 9, 2017

Fox Rothschild LLP, Patrick J. Casey, Spencer L. Sears, Risa B. Brown, Denver, Colorado, for Plaintiffs-Appellants

Markusson, Green, and Jarvis, Gregg S. Rich, Daniel R. Coombe, Wyatt M. Cox, Denver, Colorado, for Defendant-Appellee

*Sitting by assignment of the Chief Justice under provisions of Colo. Const. art. VI, § 5(3), and § 24-51-1105, C.R.S. 2016.

¶1 In this construction defect case involving a senior assisted and independent living facility (senior facility), we must decide whether the parties’ contract or relevant Colorado statutes govern the accrual of defect claims. To do so, we must decide a matter of first impression — whether a senior facility constitutes “residential property” that is protected by a provision of the Construction Defect Action Reform Act (CDARA) entitled the “Homeowner Protection Act of 2007” (HPA).1 The HPA renders a contract’s limitation or waiver of CDARA’s rights and remedies void as against public policy in cases involving claims arising from residential property.

¶2 Plaintiffs, Broomfield Senior Living Owner, LLC and Sunrise Development, Inc., LLC (collectively Broomfield), appeal the trial court’s order granting summary judgment for defendant, R.G. Brinkmann Company d/b/a Brinkmann Constructors (Brinkmann). Broomfield brought claims against Brinkmann for breach of contract, negligence, negligence per se, negligent

1 The title “Homeowner Protection Act of 2007” does not appear anywhere in the current statutes; however, the text of the session law enacting the HPA included a short title that indicated “[t]his act shall be known and may be cited as the ‘Homeowner Protection Act of 2007.’” Ch. 164, sec. 1, 2007 Colo. Sess. Laws 610.

misrepresentation,2 and breach of express warranties. Brinkmann raised both contractual limitations and statutory limitations defenses to all of Broomfield’s claims. Because we conclude that the term “residential property” in the HPA unambiguously includes senior facilities, we find the contract’s accrual provisions void as against public policy. Therefore, the relevant statutory accrual provisions apply here. We further conclude that genuine issues of material fact remain regarding (1) when the defects were discovered and any claims accrued; (2) whether Brinkmann engaged in impermissible design services outside of the contract; (3) whether Brinkmann was given an adequate opportunity to correct the defects; and (4) whether the defects alleged are latent or patent. Accordingly, we reverse and remand for further proceedings.

I. Background

¶3 In 2007, Sunrise Development and a former owner entered into an American Institute of Architects Standard Form of Agreement contract (the contract) for the construction of a senior

2The trial court did not address this claim and neither did the parties in their briefs. Therefore, we do not consider it.

living community (the building) in Broomfield, Colorado.3 The contract contains a general warranty provision, § 3.5, which guarantees that the materials and equipment used will “be of good quality” and that the work will be “free from defects not inherent in the quality required or permitted, and that the work will conform to the requirements of the Contract Documents.” In addition to the general warranty provision, the contract includes an additional warranty (§ 12.2.2) for latent defects discovered after the date of final completion. See infra Appendix 1. In relevant part, this additional warranty extends the warranty period by one year following discovery of the latent defect. It requires the owner to promptly notify the contractor of any defect and provides that an owner who fails to provide prompt notice of a defect waives the right to require its correction or to make a claim for breach of warranty.

3 Broomfield Senior Living is the current owner of the building and assumed ownership through a transfer of title from the original owner. The parties agree that specific contract language (§ 13.2.1), giving successive owners rights and obligations under the contract, gives Broomfield standing to bring a breach of contract claim, despite its status as a subsequent owner. Therefore, our breach of contract analysis is limited to subsequent owners who have contractual standing.

A contractor’s failure to correct the defect in a reasonable period of time permits the owner to make the correction.

¶4 The contract also includes a clause (§ 13.7) limiting Brinkmann’s liability in the event the work was defective. See infra Appendix 2. This clause contains three separate accrual provisions. It provides that claims arising from acts or failures to act (1) occurring before substantial completion accrue no later than the date of substantial completion; (2) occurring between substantial completion and final payment certificate accrue no later than the final payment certificate issuance date; and (3) occurring after final payment accrue no later than the time provided in the warranty (§ 3.5) or the additional warranty (§ 12.2), whichever is later.

¶5 A certificate of substantial completion was issued on March 16, 2009. The project was completed on May 15, 2009, when a certificate of occupancy was issued. At that time, neither Broomfield nor Brinkmann noted any defects in the construction of the building.

¶6 In the fall of 2012, Broomfield discovered sewer flies and hired a general contractor to investigate their cause. The contractor determined that the sewer flies resulted from broken sewer pipes.

Because the pipes were located beneath concrete slabs, they could not be readily accessed or repaired. Thus, on November 27, 2012, Broomfield began excavation beneath the building to inspect and repair the broken pipes. The contractor eventually advised Broomfield that the breaks resulted from soil expansion and recommended further investigation of other potential pipe breaks.

¶7 On April 26, 2013, Broomfield hired SBSA, Inc. (SBSA) to conduct this further investigation. SBSA began its investigation on May 3, 2013, and continued investigating through March 2015. During that two-year period, SBSA identified numerous building defects that it attributed to improper construction. See infra Appendix 3.

¶8 On November 21, 2013, SBSA issued a notice of latent defects to Broomfield identifying the defects discovered. On January 28, 2014, Broomfield issued a notice of claim informing Brinkmann of the latent defects. On March 13, 2014, Brinkmann conducted a site visit. In a letter dated May 12, 2014, Brinkmann rejected the notice of claim, stating that the “primary problem affecting this site is the soils.” It noted that the building itself had not moved and credited the proper design and construction of the void space to this

non-movement. After comparing the list of defects provided by Broomfield to the construction documents, Brinkmann concluded that it had performed its work in accordance with the documents, that there was no defective construction, and that there was no “work requiring repair.”

Free access — add to your briefcase to read the full text and ask questions with AI

Broomfield Senior Living Owner, LLC v. R.G. Brinkmann Co, 2017 COA 31, 413 P.3d 219 (Colo. Ct. App. 2017).

2017 COA 31 (Broomfield Senior Living Owner, LLC v. R.G. Brinkmann Co) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Peo in Interest of DRS
Colorado Court of Appeals, 2026
Carroll Partners LLC v. Bd. of Comm'rs
Colorado Court of Appeals, 2026
V&H v. Beardsley
Colorado Court of Appeals, 2025
Peo in Interest of AC
Colorado Court of Appeals, 2025
Stoecklein v. Fayette Farms
Colorado Court of Appeals, 2024
& 23CA0663 Duran v. Montoya
Colorado Court of Appeals, 2024
Matthew K Hobbs v. City of Salida
550 P.3d 193 (Colorado Court of Appeals, 2024)
Thomas Seaman v. Heather Gardens Association
Colorado Court of Appeals, 2023
v. Center for Excellence
2021 COA 117 (Colorado Court of Appeals, 2021)
Hardy v. Flood
D. Colorado, 2019