Stoecklein v. Fayette Farms

CourtColorado Court of Appeals
DecidedDecember 12, 2024
Docket24CA0678
StatusUnpublished

This text of Stoecklein v. Fayette Farms (Stoecklein v. Fayette Farms) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stoecklein v. Fayette Farms, (Colo. Ct. App. 2024).

Opinion

24CA0678 Stoecklein v Fayette Farms 12-12-2024

COLORADO COURT OF APPEALS

Court of Appeals No. 24CA0678 Elbert County District Court No. 20CV30009 Honorable Theresa Slade, Judge

Lindsey Stoecklein and Chance Stoecklein,

Plaintiffs-Appellants,

v.

Fayette Farms, LLC,

Defendant-Appellee.

JUDGMENT AFFIRMED

Division II Opinion by JUDGE JOHNSON Fox and Schock, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced December 12, 2024

Todd Collins & Associates, LLC, Todd Collins, Marc Tull, Stephanie Williams, Elizabeth, Colorado, for Plaintiffs-Appellants

Lasater & Martin, P.C., Janet B. Martin, Max S. Gad, Greenwood Village, Colorado, for Defendant-Appellee ¶1 Plaintiffs, Lindsey and Chance Stoecklein (collectively, the

Stoeckleins),1 appeal the district court’s order granting summary

judgment in favor of defendant, Fayette Farms, LLC (Fayette

Farms). The Stoeckleins contend that in granting summary

judgment, the district court erred by (1) applying the wrong statute

of limitations, thus time barring their fifth claim for relief and

(2) concluding there were no genuine issues of material fact as to

when they were aware or should have been aware of the physical

manifestation of defects to their home as a result of Fayette Farms’

alleged negligent actions, thus time barring their fifth and sixth

claims. We affirm.

I. Background

¶2 The Stoeckleins entered into an agreement with Redline

Construction Corporation (Redline) to construct a manufactured

home.2 Redline transferred its duties and responsibilities under the

contract to High Country Construction & Development, LLC (High

Country). High Country served as the general contractor for the

1 We later refer to the Stoeckleins by their first names because they

share the same last name. We intend no disrespect by doing so. 2 The contract was between the Stoeckleins and Eric Markowski,

who conducted business as Redline Construction Corporation.

1 Stoeckleins’ manufactured home. But High Country subcontracted

with Fayette Farms to install the manufactured home on the

Stoeckleins’ lot.

¶3 The Stoeckleins moved into the home on June 14, 2019, and

immediately discovered extensive damage and defects. The next

day, the Stoeckleins notified High Country about the defective work,

which included foundation cracks and cracking throughout the

home, the inability to open and close doors and windows, problems

with the floor, stairwell cracks, warped and cracked ceilings, and

sagging throughout the structure. They requested that High

Country repair the identified issues.

¶4 The Stoeckleins hired Steel Rhino Property (Steel Rhino) to

inspect their home. Steel Rhino issued a report (the Steel Report)

on June 29 that identified a general list of defects and

recommendations to follow up with qualified professionals for

further evaluation of the problems and for repairs. The Stoeckleins

retained attorneys from Messner Reeves, LLP and later Todd Collins

(Collins) to represent them in potential and then-filed construction

defect claims. On July 25, Collins sent a letter to High Country

2 notifying them of the various defects observed in June 2019 and

identified in the Steel Report.

¶5 On February 24, 2020, the Stoeckleins filed a lawsuit against

High Country. As part of the lawsuit, the Stoeckleins hired an

engineering expert, Edward Fronapfel (Fronapfel), who issued a

report (the Fronapfel Report) on September 30, 2021. Through the

Fronapfel Report, the Stoeckleins learned of additional defects to

their home attributable to Fayette Farms. Fayette Farms’ work on

the Stoeckleins’ home included setting the home, raising the roof,

and installing lap siding on the end walls. The Fronapfel Report

identified that Fayette Farms had caused damage to the

Stoeckleins’ foundation by parking a crane too close to the

basement wall, causing the basement wall to bow and crack.

¶6 As a result of Fayette Farms’ alleged negligent work, the

Stoeckleins filed their fifth amended complaint on May 16, 2022.

Their fifth and sixth claims alleged that Fayette Farms failed to

(1) strictly comply with the manufacturer’s instructions when it

installed the home, a violation of section 24-32-3316(1), C.R.S.

2024, which in turn constituted a deceptive trade practice in

violation of section 6-1-105, C.R.S. 2024, of the Colorado Consumer

3 Protection Act (CCPA); and (2) install the home in accordance with

industry standards and, thus, engaged in negligent conduct.3

¶7 Fayette Farms moved for summary judgment contending that

the Stoeckleins’ claims were time barred because they were not

brought within the two year statute of limitations for construction

defect claims under the Construction Defect Actions Reform Act

(CDARA), section 13-80-104(1)(a), C.R.S. 2024. In response, the

Stoeckleins argued that the CCPA’s three year statute of limitations

applied to its fifth claim and that, because facts were disputed as to

when they were or should have been aware of the defects caused by

Fayette Farms, summary judgment should have been denied on the

fifth and sixth claims. The district court agreed with Fayette

Farms, concluding that CDARA time barred those claims, as the

statute of limitations began to accrue no later than August 2019.

II. Standard of Review and Applicable Law

¶8 We review de novo a district court’s order granting summary

judgment. Rocky Mountain Planned Parenthood, Inc. v. Wagner,

2020 CO 51, ¶ 19.

3 Although the Stoeckleins sued other companies and individuals,

this appeal only concerns Fayette Farms.

4 ¶9 Summary judgment is a drastic remedy and, therefore, is only

appropriate where there are no disputed issues of material fact, and

the moving party is entitled to judgment as a matter of law.

C.R.C.P. 56(c); Sanchez v. Moosburger, 187 P.3d 1185, 1187 (Colo.

App. 2008). The party moving for summary judgment bears the

initial burden of showing the nonexistence of any genuine issue of

material fact, “and all doubts as to the existence of such an issue

must be resolved against the moving party.” Stanczyk v. Poudre

Sch. Dist. R-1, 2020 COA 27M, ¶ 51 (quoting Churchey v. Adolph

Coors Co., 759 P.2d 1336, 1340 (Colo. 1988)), aff’d on other

grounds, 2021 CO 57.

¶ 10 The interpretation of when a claim accrues under a statute of

limitations is an issue of law that we review de novo. Rider v. State

Farm Mut. Auto. Ins. Co., 205 P.3d 519, 521 (Colo. App. 2009). But

whether the statute of limitations bars a particular claim because a

court finds certain circumstances exist is generally a question of

fact. Sulca v. Allstate Ins. Co., 77 P.3d 897, 899 (Colo. App. 2003).

A court may grant summary judgment if the plaintiff’s claim is

barred by the governing statute of limitations, but it “cannot grant

summary judgment on this basis if there are disputed issues of fact

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Theodore Roosevelt Agency, Inc. v. General Motors Acceptance Corp.
398 P.2d 965 (Supreme Court of Colorado, 1965)
Churchey v. Adolph Coors Co.
759 P.2d 1336 (Supreme Court of Colorado, 1988)
United Fire Group v. Powers Electric, Inc.
240 P.3d 569 (Colorado Court of Appeals, 2010)
Stiff v. Bilden Homes, Inc.
88 P.3d 639 (Colorado Court of Appeals, 2003)
Sulca v. Allstate Insurance Co.
77 P.3d 897 (Colorado Court of Appeals, 2003)
Sanchez v. MOOSBURGER
187 P.3d 1185 (Colorado Court of Appeals, 2008)
Rider v. State Farm Mutual Automobile Insurance Co.
205 P.3d 519 (Colorado Court of Appeals, 2009)
Two Denver Highlands Ltd. Partnership v. Dillingham Construction N.A.
932 P.2d 827 (Colorado Court of Appeals, 1996)
Fischbach v. Holzberlein
215 P.3d 407 (Colorado Court of Appeals, 2009)
People v. Delgado
2016 COA 174 (Colorado Court of Appeals, 2016)
In re Goodman v. Heritage Builders
2017 CO 13 (Supreme Court of Colorado, 2017)
Broomfield Senior Living Owner, LLC v. R.G. Brinkmann Co
2017 COA 31 (Colorado Court of Appeals, 2017)
v. Zag Built LLC —
2018 COA 66 (Colorado Court of Appeals, 2018)
v. Delgado
2019 CO 82 (Supreme Court of Colorado, 2019)
Mountain Planned Parenthood, Inc. v. Wagner
2020 CO 51 (Supreme Court of Colorado, 2020)
Seaman v. Colorado Manufactured Housing Licensing Board
832 P.2d 1041 (Colorado Court of Appeals, 1991)
State v. Nieto
993 P.2d 493 (Supreme Court of Colorado, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Stoecklein v. Fayette Farms, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stoecklein-v-fayette-farms-coloctapp-2024.