Stiff v. Bilden Homes, Inc.

88 P.3d 639, 2003 WL 22019865
CourtColorado Court of Appeals
DecidedOctober 9, 2003
Docket02CA1838
StatusPublished
Cited by6 cases

This text of 88 P.3d 639 (Stiff v. Bilden Homes, Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stiff v. Bilden Homes, Inc., 88 P.3d 639, 2003 WL 22019865 (Colo. Ct. App. 2003).

Opinion

Opinion by

Judge NEY.

Plaintiff, Jacqueline E. Stiff, appeals the summary judgment entered in favor of defendant, BilDen Homes, Inc., on her claims for negligence, breach of implied warranty, negligent misrepresentation, false representation, concealment and nondisclosure, breach of contract and express warranty, and consumer protection. We affirm in part, re *640 verse in part, and remand for farther proceedings.

Plaintiff purchased a new home from defendant in November 1994. Prior to construction, a soils report prepared for defendant recommended the use of structural floors rather than slab-on-grade floors because expanding soils on the lot would cause the slab-on-grade floors to move. The report, however, provided alternative specifications for the construction of slab-on-grade flooring if the owner was willing to accept the risk of slab movement. It cautioned that the alternative specifications “will not prevent movement, but would reduce damage if movement occurred.” The home was constructed with slab-on-grade basement and garage floors with the alternative specifications. Plaintiff was aware at closing of the soils report, the engineering recommendations, and the use of the slab-on-grade flooring.

In October 1995 and May 1996, plaintiffs husband notified defendant of construction problems, including cracks in the basement drywall, which he claimed were construction defects and were covered under the warranty. Defendant responded that it was financially unable to address these claims. The cracking of the drywall was later determined to be solely attributable to another contractor, who remedied the situation.

In September 1996, plaintiff hired a consultant engineer to inspect the property and received a written report concluding that the movement of the floor was “to be expected.” In November 1998, the same engineer rein-speeted the house and concluded that the floor movement was “not excessive.”

In September 1999, plaintiffs husband noticed that the walls in the basement were moving away from each other, and in June 2000, he noticed that the furniture in the basement rooms was tilting. In February 2001, plaintiff filed this action.

The trial court granted summary judgment for defendant on the ground that plaintiffs claims were barred by the statute of limitations and that plaintiffs negligence and negligent misrepresentation claims were barred based on the economic loss rule. This appeal followed.

I.

Plaintiff contends that the trial court erred in granting summary judgment on her negligence claim based on the expiration of the statute of limitations. She asserts that there is a disputed issue of fact as to when the damage occurred to begin the running of the statute of limitations. We agree.

Review of a summary judgment is de novo. Aspen Wilderness Workshop, Inc. v. Colo. Water Conservation Bd., 901 P.2d 1251 (Colo.1995).

Summary judgment is appropriate when the moving party can demonstrate that there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Burman v. Richmond Homes Ltd., 821 P.2d 913 (Colo.App.1991). We, like the trial court, must view the evidence in the light most favorable to the nonmoving party. Cissell Mfg. Co. v. Park, 36 P.3d 85 (Colo.App.2001).

Plaintiff bases her claim of negligence on defendant’s failure to follow the recommendation in the soils report to use structural flooring instead of slab-on-grade flooring.

A.

Plaintiff first contends that the applicable statute of limitations is contained in §§ 13-80-102 & 13-80-108, C.R.S.2002, and not § 13-80-104, C.R.S.2002, concerning actions against builders. We decline to address this issue.

In reviewing the granting of summary judgment, we need only determine whether the trial court erred in concluding that there were no material facts in dispute. Because we conclude that a disputed issue of material fact remains as to the date that damage occurred and began the running of the statute of limitations, and because evidence in the record indicates that the damage may not have occurred until September 1999, which is within the limitations period of both statutes, we need not determine now which statute applies.

*641 B.

We conclude that summary judgment based on the statutes of limitation was not proper to bar plaintiffs negligence claim, because the record reflects a question of fact regarding the date on which plaintiff knew or should have known of the damage and its cause.

Although the statutes use slightly different language, as relevant here under both statutes, the limitations period begins when the plaintiff knew or should have known of the damage and its cause. Compare § 13-80-108(1), C.R.S.2002 (“a cause of action for injury to person, property, reputation, possession, relationship, or status shall be considered to accrue on the date both the injury and its cause are known or should have been known by the exercise of reasonable diligence”), with § 13—80—104(1)(b)(I), C.R.S. 2002 (“a claim for relief arises under this section at the time the claimant or the claimant’s predecessor in interest discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect in the improvement which ultimately causes the injury”).

However, not all damage is sufficient to begin the limitations period. The limitations period only begins when the plaintiff discovers or should have discovered damage that would entitle her to maintain a cause of action based on that damage. See Daugherty v. Allstate Ins. Co., 55 P.3d 224, 226 (Colo.App.2002)(eause of action accrues when litigation could first have been successfully maintained); Tucker v. Claimants in re Death of Gonzales, 37 Colo.App. 252, 546 P.2d 1271 (1975).

Here, the builder installed slab-on-grade flooring and took action to accommodate a certain amount of movement. As a result, a certain amount of movement of the slab-on-grade floor was to be expected. It was not until the movement became greater than expected that any damage that was caused by the allegedly negligent act would permit plaintiff to maintain a cause of action. Accordingly, under the facts here, damage would arise to permit a successful cause of action only when the movement of the slab-on-grade flooring became excessive and the accommodations were no longer sufficient to control the damage.

Here, the evidence in the record indicates a dispute about when the movement of the floor became excessive. Viewing the evidence in the light most favorable to plaintiff, we conclude that the evidence of plaintiffs knowledge of the movement of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stoecklein v. Fayette Farms
Colorado Court of Appeals, 2024
Colorado Pool Systems, Inc. v. Scottsdale Insurance Co.
2012 COA 178 (Colorado Court of Appeals, 2012)
People v. Wartena
2012 COA 12 (Colorado Court of Appeals, 2012)
United Fire Group v. Powers Electric, Inc.
240 P.3d 569 (Colorado Court of Appeals, 2010)
Andrews v. Picard
199 P.3d 6 (Colorado Court of Appeals, 2007)
A.C. Excavating v. Yacht Club II Homeowners Ass'n
114 P.3d 862 (Supreme Court of Colorado, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
88 P.3d 639, 2003 WL 22019865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stiff-v-bilden-homes-inc-coloctapp-2003.