Bridges v. Lanham

14 Neb. 369
CourtNebraska Supreme Court
DecidedJanuary 15, 1883
StatusPublished
Cited by8 cases

This text of 14 Neb. 369 (Bridges v. Lanham) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bridges v. Lanham, 14 Neb. 369 (Neb. 1883).

Opinion

Cobb, J.

This action was commenced in the court below by the defendant in error against the plaintiffs in error for the agreed price of a stone flume furnished and built by him for them under a contract.

The defendants answered and set up as a defense and counter-claim that it was a part of the said contract for the [370]*370building of the said flume, that the same should be erected and built in a good and workmanlike manner, and to the satisfaction of the said plaintiffs in error, and fully completed on or before the first day of December, 1880. That said plaintiff (defendant in error) did not perform the work and labor on said flume in a good and workmanlike manner, nor did he complete the flume on or before the first day of December, 1880, by reason of which non-completion of said flume, the defendants (plaintiffs in error) were damaged in the sum of $4,160.

2. That by reason of the said plaintiff’s non-completion of said flume on or before the first day of December, 1880, as agreed, the said defendants were on the fifteenth day of December, 1880, compelled to do a great deal of work and labor in and about digging frozen ground, to protect the unfinished wall of said flume, to their damage in the sum of $75.00.

3. That by reason of the non-completion of said flume at said specified time, defendants were, on the 8th day of May, 1881, compelled to use and throw 10,000 bricks into the water above the flume to protect the flume, and to prevent the water from washing it away, to their damage in the sum of $80.00.

4. That during the erection of the said flume, stones were thrown down the embankment by the said defendant against the green and unfinished wall so being built, whereby said wall became crooked and out of shape, and in such a condition that it would not hold water, to the damage of defendants in the sum of $500.

5. That said flume was not built in a good and workmanlike manner, but on the contrary the same was very poor work, to the damage of defendants $400.

6. That by reason of the said flume not being completed at the time agreed, the said defendants were damaged in the sum of $500 by water running through the wall and washing away the embankment.

[371]*3717. That defendants have laid out and expended large suras of money, to-wit: forty dollars for labor and cement in and about protecting the unfinished wall of said flume, which became necessary on account of the incompletion of said flume on or before the first day of December, 1880.

8. That by reason of the incompletion of said flume on or before the first day of December, 1880, the head gates ■of said defendants, near which said flume was being built, were washed out in the spring of 1881, whereby defendants' were compelled to expend large sums of money and labor in replacing said head gates, to their damage of $500.

With a prayer for judgment for $5,315.00.

To which the plaintiff replied by a general denial.

There was a verdict and judgment for the plaintiff. Defendants bring the cause to this court on error.

There are a great number of errors complained of in the petition in error. There is, however, but one important question involved, and to which our attention will be chiefly, if not exclusively, confined in this opinion.

Upon the trial the court on its own motion, among •others, gave to the jury the following instruction:

“5. In the opinion of the court the claim for damages for the want of the use of the mill, and the building of which is claimed to have been delayed, is too remote, and you will allow nothing for this claim.”

The same point also arises upon the refusal of the court to give in charge to the jury the third, fifth, sixth, seventh, eighth, and ninth prayers of the defendants, by which a contrary opinion was sought.

In their brief and by argument at the bar, plaintiffs in error claim that their case comes within the rule laid down in Hadley v. Baxendale, 9 Exch. R., 341. Booth v. Spuyten Duyvil Rolling Mill Co., 60 N. Y., 487. Griffin v. Culrer, 16 N. Y., 489, and many other cases all following the case first named.

We had occasion to examine and cite the leading case of [372]*372Hadley v. Baxendale while writing the opinion in the case of The Sycamore Marsh Harvester Co. v. Sturm, 13 Neb., 210. The plaintiffs were the owners of a steam, grist mill, and contracted with the defendant, a carrier of goods by railway, to carry for hire two pieces of iron, constituting the broken shaft of a mill, and deliver the same to an artificer who lived at a considerable distance, in order to serve as a model for a new shaft to be made for them by him. The defendant having violated his agreement by not delivering these pieces of iron within a reasonable time, a delay necessarily arose in supplying the new shaft. A shaft being indispensable to the working of the mill, and the plaintiff not having any other, the mill remained idle until the delivery of the new one; but although there was evidence that the defendant knew the mill was standing still, he was not aware that this was for the want of the shaft for which the iron delivered to him was to serve as a model. In this case the decision turned upon the want of knowledge on the part of the defendant, or of notice to him that the mill was lying idle solely for the want of the shaft, the necessary model for which he was failing to deliver to the mechanic who was depended upon to furnish it; and the want of evidence from which the court and jury could find that it was within the contemplation of the parties, the defendant as well as the plaintiffs, at the time of the making of the contract, that the mill would necessarily be idle to the plaintiff's damage until a shaft should be manufactured and furnished from the model, the carrying and delivery of which was the subject of the contract. The distinction between the above case and the case at bar consists chiefly in this: There the mill had been completed, had been in operation, and was probably a well-known manufacturing establishment of the neighborhood. Capital ■ was actually invested in' it. Probably a number of persons were employed in and about the mill; it had established customers, as well those who furnished the raw [373]*373material as those who purchased and used the manufactured product. Thus it is obvious that a continued suspension of its operations would be substantial and far-reaching in its effects. But here, while there was evidence tending to prove that it was the intention of the defendants below to erect a corn mill for temporary use, to be propelled by water supplied by the flume which the plaintiff contracted to erect, and that such intention was known to him, yet it is an undisputed fact that this mill had not been built; that it only existed in the intention and potential ability of the defendants to build it.

The case of Griffin v. Colver et al., 16 N. Y., 489, was where the plaintiff agreed to build a steam engine with boilers, etc., for defendants, and deliver it to them on a day certain. He failed to do so, and a delay of one week occurred, during which time defendants lost the use of certain machinery for the sawing and planing of lumber, which the steam engine was intended to drive, and which the plaintiff knew it was intended to drive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stubblefield v. Montgomery Ward & Co.
98 P.2d 14 (Oregon Supreme Court, 1940)
Southern Railway Co. v. Pardue
123 Tenn. 376 (Tennessee Supreme Court, 1910)
Maclay v. United States
43 Ct. Cl. 90 (Court of Claims, 1908)
Choctaw, Oklahoma & Gulf Railroad v. Jacobs
1905 OK 43 (Supreme Court of Oklahoma, 1905)
Atchison, Topeka & Santa Fe Railway Co. v. Thomas
78 P. 861 (Supreme Court of Kansas, 1904)
Paola Gas Co. v. Paola Glass Co.
44 P. 621 (Supreme Court of Kansas, 1896)
Denver, T. & G. R. v. Hutchins & Hyatt
48 N.W. 398 (Nebraska Supreme Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
14 Neb. 369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bridges-v-lanham-neb-1883.