Brannan v. Lathrop Construction Associates, Inc.

206 Cal. App. 4th 1170, 142 Cal. Rptr. 3d 336, 2008 WL 8833510, 2012 Cal. App. LEXIS 680
CourtCalifornia Court of Appeal
DecidedMay 21, 2012
DocketNo. A129695
StatusPublished
Cited by13 cases

This text of 206 Cal. App. 4th 1170 (Brannan v. Lathrop Construction Associates, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brannan v. Lathrop Construction Associates, Inc., 206 Cal. App. 4th 1170, 142 Cal. Rptr. 3d 336, 2008 WL 8833510, 2012 Cal. App. LEXIS 680 (Cal. Ct. App. 2012).

Opinion

Opinion

MARGULIES, J.

While working for a masonry subcontractor at a school construction site, Brian Brannan slipped on wet scaffolding and injured his back. He sued the general contractor, Lathrop Construction Associates, Inc. (Lathrop), alleging his injuries were caused by Lathrop’s negligence in [1173]*1173sequencing and coordinating construction work at the site, and failing to call a “rain day” to protect workers from dangerous conditions caused by slippery surfaces. Lathrop moved successfully for summary judgment under the Privette-Toland doctrine. (Privette v. Superior Court (1993) 5 Cal.4th 689 [21 Cal.Rptr.2d 72, 854 R2d 721] (Privette); Toland v. Sunland Housing Group, Inc. (1998) 18 Cal.4th 253 [74 Cal.Rptr.2d 878, 955 P.2d 504] (Toland).) Brannan contends the trial court erred in finding there were no triable issues of material fact. We affirm.

I. INTRODUCTION

A. Pleadings

Brannan filed a complaint on October 29, 2008, alleging Lathrop was actively negligent in failing to carry out its duties of care as the general contractor on a construction project at El Cerrito High School. He alleged Lathrop’s negligence caused him to suffer personal injury when he slipped on wet scaffolding and injured his back while working at the site as a journeyman bricklayer employed by a masonry subcontractor.

Brannan pled causes of action for negligence and premises liability. His negligence cause of action alleged, among other things, Lathrop failed to coordinate and control the work being performed on the jobsite in a safe and proper manner, thereby creating a risk of injury to workers. Brannan alleged he was forced to work in and around scaffolding that prevented and blocked his access to his work, causing him to fall. Brannan’s premises liability claim was based on essentially the same facts.

B. Summary Judgment Motion

By motion for summary judgment, Lathrop asserted it was entitled to judgment as a matter of law under the Privette-Toland line of cases, based in substance on the following undisputed facts: Brannan was employed by Bratton Masonry (Bratton) as a journeyman bricklayer and was working at the El Cerrito High School construction site at the time of the accident. Lathrop was the general contractor. Lathrop hired Bratton as a subcontractor to perform masonry work at the site. Bratton’s subcontract required it to “comply with all State and Federal Health and Safety requirements,” as well as Bratton’s and Lathrop’s safety procedures and to “maintain a safety program” on the site. Lathrop also hired M. Perez Company, Inc., doing business as Henley & Company (Henley), as a subcontractor to perform plaster work. Henley’s subcontract required Henley to “comply with all State and Federal Health and Safety requirements,” as well as Bratton’s and Lathrop’s safety procedures, and to maintain a safety program at the site.

[1174]*1174Tom Kennon was Lathrop’s onsite project manager at the time of the accident, and was in charge of managing safety on the site for Lathrop. Lathrop had the final say on coordination of the work at the site and had authority to stop a subcontractor’s work for a safety issue. Before beginning the project, Kennon discussed sequencing with Bratton and Henley. It was discussed at the meeting Henley would do the plastering first, and remove the plaster scaffold before Bratton started the masonry work. There was agreement Bratton would not use Henley’s plaster scaffold. However, when Henley completed its plastering work, Henley left a section of plaster scaffolding up at the request of framer Advanced Interiors (AI) so AI could finish framing on a bridge between buildings C and D. Henley’s foreman believed he told Kennon that Henley was leaving the plaster scaffold for AI to use, and Kennon agreed to this. Bratton never requested Henley to remove the plaster scaffold.

Bratton employees were working at ground level laying brick veneer in the area of the bridge between buildings C and D on the day of the accident. Peter Garcia was the Bratton foreman that day. Part of his job was to make sure the site was safe for Bratton employees. Garcia did not need authority from Lathrop to call off work if he saw something was unsafe. He was aware of the plaster scaffolding in the area where Bratton employees were working. They were not using the scaffolding on the day of the accident, but were working around it. Garcia did not have safety concerns about his workers working around the scaffolding, but he did feel the scaffolding would slow down their work. He asked Lathrop before the accident when the plaster scaffold would be removed. Garcia had the authority to call work off if he believed rain (or any other condition) made conditions unsafe, but had no concerns about the rain or wetness on the day of the accident other than that it slowed down the work. Garcia believed his crews could work around the plaster scaffold, and had no safety concerns about them stepping onto the scaffold rungs to get to the other side. Lathrop did not direct Garcia or Brannan on how the masonry was to be laid.

At the time of the accident, Brannan was trying to cross over the plaster scaffold to gain access so he could lay masonry in an area underneath it. Brannan alleges he stepped up onto the second rung of the scaffold believing there was no other way to access the area in which he was working. No one told Brannan to gain access the way he did. Brannan alleges he slipped off the rung because it was wet and his feet were muddy. He filed a workers’ compensation claim shortly after the accident.

The trial court granted summary judgment to Lathrop, and this appeal followed.

[1175]*1175II. DISCUSSION

A. Standard of Review

On appeal after a trial court has granted summary judgment, we review the record de novo to determine whether the evidence submitted for and against the motion discloses material factual issues warranting a trial. (Merrill v. Navegar, Inc. (2001) 26 Cal.4th 465, 476 [110 Cal.Rptr.2d 370, 28 P.3d 116]; Guz v. Bechtel National, Inc. (2000) 24 Cal.4th 317, 334-335 & fn. 7 [100 Cal.Rptr.2d 352, 8 P.3d 1089].)

Summary judgment is properly granted when no triable issue of material fact exists and the moving party is entitled to judgment as a matter of law. (Code Civ. Proc., § 437c, subd. (c).) A defendant moving for summary judgment bears the initial burden of showing a cause of action has no merit by showing one or more of its elements cannot be established or there is a complete defense. (Code Civ. Proc., § 437c, subds. (a), (o).) Once the defendant has met that burden, the burden shifts to the plaintiff “to show that a triable issue of one or more material facts exists as to that cause of action or a defense thereto.” (Code Civ. Proc., § 437c, subd. (p)(2).) “There is a triable issue of material fact if, and only if, the evidence would allow a reasonable trier of fact to find the underlying fact in favor of the party opposing the motion in accordance with the applicable standard of proof.” (Aguilar v. Atlantic Richfield Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cordero v. Ghilotti Construction Co., Inc.
California Court of Appeal, 2026
Cordero v. Ghilotti Construction Co. CA1/1
California Court of Appeal, 2026
Bowen v. Burns & McDonnell Engineering Co., Inc.
California Court of Appeal, 2024
Smith v. Skanska USA CA1/3
California Court of Appeal, 2023
Marin v. Department of Transportation
California Court of Appeal, 2023
Marin v. Department of Transportation CA1/5
California Court of Appeal, 2023
Brown v. Beach House Design & Development
California Court of Appeal, 2022
Torres v. Design Group Facility Solutions CA2/3
California Court of Appeal, 2021
Gonzalez v. Mathis
493 P.3d 212 (California Supreme Court, 2021)
Horne v. Ahern Rentals, Inc.
California Court of Appeal, 2020
Strouse v. Webcor Construction
California Court of Appeal, 2019
Hodges v. Hertz Corp.
351 F. Supp. 3d 1227 (N.D. California, 2018)
Regalado v. Callaghan
California Court of Appeal, 2016
Regalado v. Callaghan CA
3 Cal. App. 5th 582 (California Court of Appeal, 2016)
Batton v. Alten Construction, Inc. CA1/5
California Court of Appeal, 2013

Cite This Page — Counsel Stack

Bluebook (online)
206 Cal. App. 4th 1170, 142 Cal. Rptr. 3d 336, 2008 WL 8833510, 2012 Cal. App. LEXIS 680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brannan-v-lathrop-construction-associates-inc-calctapp-2012.