Ruiz v. Herman Weissker, Inc.

29 Cal. Rptr. 3d 641, 130 Cal. App. 4th 52, 2005 Daily Journal DAR 6773, 70 Cal. Comp. Cases 826, 2005 Cal. Daily Op. Serv. 4989, 2005 Cal. App. LEXIS 930
CourtCalifornia Court of Appeal
DecidedJune 9, 2005
DocketD044733
StatusPublished
Cited by23 cases

This text of 29 Cal. Rptr. 3d 641 (Ruiz v. Herman Weissker, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruiz v. Herman Weissker, Inc., 29 Cal. Rptr. 3d 641, 130 Cal. App. 4th 52, 2005 Daily Journal DAR 6773, 70 Cal. Comp. Cases 826, 2005 Cal. Daily Op. Serv. 4989, 2005 Cal. App. LEXIS 930 (Cal. Ct. App. 2005).

Opinion

Opinion

McINTYRE, J.

The fundamental question presented in this case is whether the California Supreme Court’s analyses in Privette v. Superior Court (1993) 5 Cal.4th 689 [21 Cal.Rptr.2d 72, 854 P.2d 721] (Privette) and Hooker v. Department of Transportation (2002) 27 Cal.4th 198 [115 Cal.Rptr.2d 853, 38 P.3d 1081] (Hooker), which hold that a hirer of a subcontractor whose employee is injured on the job as a result of the subcontractor’s negligence is not vicariously liable under the peculiar risk doctrine for the employee’s injuries, also bars similar claims against the hirer’s agent. We conclude that the policy considerations relied on in Privette and Hooker are equally applicable to claims against the hirer’s agent and thus affirm the judgment entered in favor of the agent.

*56 FACTUAL AND PROCEDURAL BACKGROUND

In October 2001, San Diego Gas & Electric Company (SDG&E) hired Herman Weissker, Inc. (HWI) as a contract administrator for its distribution line construction projects. Pursuant to its contract with SDG&E, HWI was responsible for reviewing plans to ensure proper planning and feasibility and for monitoring the construction work for safety and contract compliance.

In August 2002, SDG&E requested bids to replace old insulators on two of their 230kv transmission lines (also known as tie-lines) (TL 23002 and TL 23006, respectively) on a steel tower. Although both circuits on the tower had a history of “flashovers” (insulation failures that allowed electrical energy to flow from the lines to the tower structure), SDG&E limited the job to replacing only the insulators on TL 23002, so that TL 23006 could remain energized and in use during the project. Bidders were required to submit a work plan, including personnel safety methods, for SDG&E’s consideration. SDG&E accepted a bid by Henkels & McCoy, Inc. (Henkels) to do the work.

In accordance with its master contract with SDG&E, Henkels was required to provide its own equipment for the job and to perform its work in accordance with applicable professional standards, including SDG&E’s standards. The agreement also required that Henkels “take all necessary precautions for the safety of its employees ... on the jobsite and prevent accidents or injury to individuals on, about, or adjacent to the jobsite” and fully comply with all laws, rules, regulations and standards relating to occupational health and safety. Henkels was “solely responsible for . . . construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work” and represented that it and its suppliers and agents were “properly licensed, fully experienced and qualified to perform the class and type of Work as specified ... in addition to being properly insured, equipped, organized, staffed and financed to handle such Work.”

Timothy Ruiz was a member of the Henkels crew that was assigned to do the replacement work. Prior to the commencement of the job, the crew met at the Henkels yard with Henkels foreman Don Snyder and HWI representative Donald Richards to discuss the equipment needed for the project. The project involved changing the insulators on TL 23002’s three tiers of power lines, one on each of the lower, middle and upper portions of the tower. The 32-ton crane that the crew planned to use was unavailable, as was their second-choice lift, which had been red-tagged by a Henkels mechanic. Although Snyder initially indicated his intent to delay the start of the job, he changed his mind after talking with Richards and Henkels general foreman Bill Kibbe.

*57 The Henkels crew ultimately decided to use a 95-foot bucket truck for the job; because the truck was not tall enough to reach the upper tier of the tower, the men also brought an insulated ladder so that they could reach the insulators on that tier. After the crew went to the jobsite, they explained to Richards their plans for carrying out the job, including the plan to use the ladder to reach the upper tier and their plans for protecting the men working on the tower by using personal grounding devices. Richards indicated that the crew’s plans were fine with him.

After completing the work on the lower and middle phases of the circuit, the crew replaced the 95-foot bucket truck (which had started to leak hydraulic fluid) with an 85-foot bucket truck. At 2:20 p.m., the crew began the work on the top phase of the circuit. Because the 85-foot bucket truck was not tall enough to reach the top portion of the circuit, Ruiz climbed up to the top tier of the tower and secured the insulated ladder there. He and apprentice lineman Justin Fairbaim replaced the top phase insulators and, as Fairbaim was attempting to reposition the track bucket to assist in getting Ruiz and the equipment down from the tower, Ruiz was electrocuted. (The evidence in the record does not clearly establish how the circuit became reenergized, but suggests several different possible causes.)

Fairbaim looked up and saw Ruiz hanging upside down with his legs caught in the ladder; he shouted at Ruiz, but got no response. Fairbaim climbed back onto the tower and began yelling to the crew to call 911 and help him get Ruiz down. Fairbaim gave Ruiz mouth-to-mouth resuscitation, periodically checking Ruiz’s pulse, and continued to call for help for more than a half hour. Bystanders outside a nearby office heard Fairbaim’s pleas and called 911 at 3:45 p.m. A bit later, Snyder and Henkels’s superintendent Joe Malin came up in a bucket to assist in getting Ruiz down.

Paramedics arrived on the scene at 3:57 p.m., but, in accordance with fire department policies, could not assist with the rescue until the second circuit on the tower was deenergized. While the paramedics were waiting for SDG&E to shut off the power to TL 23006, Snyder and two other linemen succeeded in freeing Ruiz from the ladder and lowering him to the ground. At 4:45 p.m., paramedics took Ruiz by ambulance to the emergency room at Sharp Memorial Hospital; Ruiz died shortly thereafter. An autopsy showed that Ruiz suffered electrical bums on his right lower leg and right forearm and identified electrocution as the cause of death. The California Occupational Safety and Health Administration (Cal-OSHA) investigated the accident and cited Henkels for violating rales relating to personal grounding and approach distance practices and the adequacy of the tools used.

*58 In March 2003, Ruiz’s wife, personally and as the representative of Ruiz’s estate (hereinafter collectively referred to as the Estate), filed this action against SDG&E and certain Does for negligence and wrongful death. The complaint alleged that Henkels’s crew was unfamiliar with high voltage transmission line work, was inadequately trained and staffed to do such work and engaged in unsafe practices in carrying out the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramirez v. PK I Plaza 580 SC LP
California Court of Appeal, 2022
Torres v. Design Group Facility Solutions CA2/3
California Court of Appeal, 2021
Gonzalez v. Mathis
493 P.3d 212 (California Supreme Court, 2021)
Mohsen v. Wells Fargo Shareowner Services CA6
California Court of Appeal, 2021
City of L.A. v. Super. Ct.
California Court of Appeal, 2021
Gordon v. ARC Manufacturing, Inc.
California Court of Appeal, 2019
Strouse v. Webcor Construction
California Court of Appeal, 2019
Strouse v. Webcor Constr., L.P.
246 Cal. Rptr. 3d 419 (California Court of Appeals, 5th District, 2019)
Peredia v. HR Mobile Services, Inc.
California Court of Appeal, 2018
Peredia v. HR Mobile Servs., Inc.
236 Cal. Rptr. 3d 157 (California Court of Appeals, 5th District, 2018)
Delgadillo v. Television Center, Inc.
California Court of Appeal, 2018
Delgadillo v. Television Ctr., Inc.
229 Cal. Rptr. 3d 594 (California Court of Appeals, 5th District, 2018)
Alvarez v. Seaside Transportation
California Court of Appeal, 2017
Alvarez v. Seaside Transp. Servs. LLC
221 Cal. Rptr. 3d 119 (California Court of Appeals, 5th District, 2017)
Kolodzik v. Advanced Cargo Services CA2/5
California Court of Appeal, 2016
Gietzen v. Goveia CA2/6
California Court of Appeal, 2015
Brannan v. Lathrop Construction Associates, Inc.
206 Cal. App. 4th 1170 (California Court of Appeal, 2012)
Tverberg v. Fillner Construction, Inc.
202 Cal. App. 4th 1439 (California Court of Appeal, 2012)
Nasrawi v. Buck Consultants, LLC
713 F. Supp. 2d 1080 (E.D. California, 2010)
Hoffman v. May
313 F. App'x 955 (Ninth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
29 Cal. Rptr. 3d 641, 130 Cal. App. 4th 52, 2005 Daily Journal DAR 6773, 70 Cal. Comp. Cases 826, 2005 Cal. Daily Op. Serv. 4989, 2005 Cal. App. LEXIS 930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruiz-v-herman-weissker-inc-calctapp-2005.