Braithwaite v. Town of Wallingford, No. 262168 (Oct. 30, 1991)

1991 Conn. Super. Ct. 8784, 6 Conn. Super. Ct. 1088
CourtConnecticut Superior Court
DecidedOctober 30, 1991
DocketNo. 262168 262169
StatusUnpublished

This text of 1991 Conn. Super. Ct. 8784 (Braithwaite v. Town of Wallingford, No. 262168 (Oct. 30, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Braithwaite v. Town of Wallingford, No. 262168 (Oct. 30, 1991), 1991 Conn. Super. Ct. 8784, 6 Conn. Super. Ct. 1088 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION ON PLAINTIFF'S MOTION FOR ENTITLEMENT TO PREJUDGMENT AND POSTJUDGMENT INTEREST This court entered a judgment on June 28, 1991,1 in the above two class action suits in favor of the plaintiffs in the amount of $2,798,594.00.2 This damage or figure includes (1) $2,588,616.00 for damages computed prospectively from June 1, 1990 through the remainder of the terms of the 99 year covenants on the properties of class members and (2) $209,978.00 for "actual lost savings" computed from February 3, 1987 through June 1, 1990.

The plaintiffs in these cases have now moved that they be CT Page 8785 paid prejudgment interest in the statutory amount of ten percent (10%) covering the period February 3, 1987 through June 28, 1991. They also seek post judgment interest in the statutory amount of ten percent (10%) not only on the principal debt found set out in the June 28, 1991 judgment but on the amount of that judgment plus the prejudgment interest requested in their present motion.

I.

The court turns first to the claim for prejudgment interest. Although that portion of these cases leading up to the award of $2,798,594.00, was thoroughly tried and exhaustively briefed and "interest" was prayed for in the relief sought by the plaintiffs their briefs did not mention prejudgment interest. In its June 28, 1991 judgment this court did not consider and/or award prejudgment interest. No appeal was taken by the plaintiffs from that judgment. While it is not offered as precise, plaintiffs' counsel, during argument on September 27, 1991 for pre-judgment interest, indicated that amount was about $1,200,000.00.

Pointing to the total damage figure of $2,798,594.00, the plaintiffs claim that they are entitled to prejudgment interest on this "liquidated compensatory award of damages in the statutory amount of ten percent (10%), which, they claim would entitle each class member to an annual interest award of $835.40, with interest accruing at $69.62 per month and $2.29 per diem, resulting in a total award of prejudgment interest per class member in the amount of $3,677.33, covering the period February 3, 1987 through June 28, 1991." They also maintain that equitable considerations require the award of prejudgment interest in these class actions, and that this award is supported by precedent in both Connecticut case law and basic contract law. After referring to certain Connecticut cases, the plaintiffs contend that "if the defendants had dealt fairly and equitably with the plaintiffs, they would have awarded the plaintiffs in February 1987, the fair value of the Agreements for [the breached covenants] in question." They continue and maintain that "not only have the plaintiffs not had the use of the monies due them representing the fair value of the Agreements since February 3, 1987, they have been required to pay the increased burden in terms of increased sewer use fees to the town since the date [February 3, 1987] of the voiding of the Agreements." The Town,3 they argue "should not be able to reap the fruits of obtaining increased sewer use fee payments over the last four and one-half years, and at the same time, escape its fair obligation to the plaintiffs, interest for four and one-half years."

On the other hand, the defendants argues that "an award of prejudgment interest is not justified under the circumstances nor is it on the interests of justice." They maintain that they "acted in good faith and relied on legal advice in deciding to declare the plaintiffs' sewer covenants null and void." Urging CT Page 8786 that their actions were for the benefit of the entire Town, they contend that "their actions did not amount to a wrongful detention of money and that, therefore, this court should not award prejudgment interest to the plaintiffs." The defendants go on and argue that even if this court decides to award prejudgment interest, the plaintiffs' proposed method of calculating such an award is incorrect and excessive. In that regard they refer to evidence at the trial demonstrating "that some of the class members of the class actions never paid the increased sewer bill as it became due but instead paid only $15.00 (this was the annual rate that property owners in the areas covered by the Agreements were required to pay in sewer use fees)." Asserting that because the purpose of prejudgment interest is for the loss of use of money, they claim that it would be "particularly inappropriate" to award such interest to plaintiffs who had not in fact lost the use of their money. The plaintiffs were "more than fully compensated", they go on, because they have been given an award for "actual lost savings" (this refers to the $209,978.00 component of the June 28, 1991 award of $2,798,954.00) "even though some [class] members never experienced such lost savings." Here the defendants also claim that although "actual lost savings" were calculated from February 3, 1987 through June, 1990, not all sewer bills were due and owing on February 3, 1987, but rather became due successively on an annual basis. They, accordingly, take issue with the plaintiffs claim of entitlement to prejudgment interest at the statutory rate of 10% on the "liquidated compensatory award" of the total figure of $2,798,954.00. There they claim that this figure includes (1) the "actual lost savings" amount of $209,987.00 for all class members even though some never paid the increased billing and that all sewer bills for the period from February 3, 1987 to June 1, 1990 were not due and owing on February 3, 1987 and (2) $2,588,616.00 (computed by deducting $209,978.00 from $2,798,954.00) for future lost savings from June 1, 1990 prospectively for the balance [in terms of years] of the 99 year covenants "that were breached. Neither of these components of the June 21, 1991 award represent, they contend "damages for the detention of money after it becomes payable" citing Connecticut General Statutes 37-3a which provides in part that ". . . interest at the rate of ten percent per year . . . may be recovered and allowed in civil actions . . . after it becomes payable as" prejudgment interest, which they contend is not payable for prospective damages but rather when performance is due.

The defendants also urge that an award of prejudgment interest should not be made since they did not "wrongfully detain plaintiffs' money." Saying that the plaintiffs have been compensated "more than adequately" the defendants contend that "in it would not be in the best interests of justice to increase their [the plaintiffs'] judgment with a $1,231,095.55 award of CT Page 8787 prejudgment interest."4 Finally, they claim that the plaintiffs have not timely raised their request for prejudgment interest.

At the juncture certain legal principles may be appropriately set out. "The allowance of prejudgment interest as an element of damages is an equitable determination and a matter lying within the discretion of the court. H. B. Toms Tree Surgery, Inc. v. Brant, 187 Conn. 343, 348, 446 A.2d (1982); Cecio Bros. Inc. v. Feldman, 161 Conn. 265, 275, 287 A.2d 374 (1971)." West Haven Sound Development Corporation v. West Haven, 207 Conn. 308, 321

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Comm'rs of Jackson Cty. v. United States
308 U.S. 343 (Supreme Court, 1939)
Blau v. Lehman
368 U.S. 403 (Supreme Court, 1962)
Lar-Rob Bus Corp. v. Town of Fairfield
365 A.2d 1086 (Supreme Court of Connecticut, 1976)
State v. Battle
365 A.2d 1100 (Supreme Court of Connecticut, 1976)
Buckley v. Warden, Connecticut Correctional Institution
435 A.2d 348 (Supreme Court of Connecticut, 1980)
Cecio Bros., Inc. v. Feldmann
287 A.2d 374 (Supreme Court of Connecticut, 1971)
State v. Onofrio
425 A.2d 560 (Supreme Court of Connecticut, 1979)
Bertozzi v. McCarthy
323 A.2d 553 (Supreme Court of Connecticut, 1973)
H. B. Toms Tree Surgery, Inc. v. Brant
446 A.2d 1 (Supreme Court of Connecticut, 1982)
Bernhard v. Rochester German Insurance
65 A. 134 (Supreme Court of Connecticut, 1906)
Hammerberg v. Leinert
46 A.2d 420 (Supreme Court of Connecticut, 1946)
State Ex Inf. McKittrick v. Wallach
182 S.W.2d 313 (Supreme Court of Missouri, 1944)
State v. Stengel
472 A.2d 350 (Supreme Court of Connecticut, 1984)
Town of Newington v. General Sanitation Service Co.
491 A.2d 363 (Supreme Court of Connecticut, 1985)
State v. Corchado
512 A.2d 183 (Supreme Court of Connecticut, 1986)
King v. Board of Education
524 A.2d 1131 (Supreme Court of Connecticut, 1987)
West Haven Sound Development Corp. v. City of West Haven
541 A.2d 858 (Supreme Court of Connecticut, 1988)
Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Associated Catalog Merchandisers, Inc. v. Chagnon
557 A.2d 525 (Supreme Court of Connecticut, 1989)
Harris Calorific Sales Co. v. Manifold Systems, Inc.
559 A.2d 241 (Connecticut Appellate Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 8784, 6 Conn. Super. Ct. 1088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/braithwaite-v-town-of-wallingford-no-262168-oct-30-1991-connsuperct-1991.