Bouton v. Manson Construction Co

CourtDistrict Court, W.D. Louisiana
DecidedDecember 7, 2023
Docket6:22-cv-05535
StatusUnknown

This text of Bouton v. Manson Construction Co (Bouton v. Manson Construction Co) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bouton v. Manson Construction Co, (W.D. La. 2023).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAFAYETTE DIVISION

CHRISTOPHER BOUTON CIVIL DOCKET NO. 6:22-cv-05535

VERSUS JUDGE DAVID C. JOSEPH

MANSON CONSTRUCTION CO. MAGISTRATE JUDGE CAROL B. WHITEHURST

MEMORANDUM RULING Before the Court is a MOTION FOR SUMMARY JUDGMENT (the “Motion”) [Doc. 37] filed by Defendant Manson Construction Co. (hereinafter, “Manson”). Manson seeks summary judgment with respect to all claims asserted by Plaintiff Christopher Bouton (“Plaintiff” or “Bouton”) on grounds the Plaintiff is not a seaman under the Jones Act, 46 U.S.C. § 30104, et seq. For the reasons that follow, Manson’s Motion is GRANTED. FACTUAL BACKGROUND This lawsuit arises out of a workplace accident that occurred on or around April 10, 2021,1 on a spudded down or tied off barge located on the St. Johns River in Jacksonville, Florida. At the time of the incident, Plaintiff was an employee of

1 The date of the subject accident is uncertain. In his responses to interrogatories, the Plaintiff indicated that the accident occurred on April 10, 2021; however, the Plaintiff acknowledged in his deposition that he did not report the accident to Manson or seek medical attention on the date the alleged injury occurred and cannot remember the date it happened. (See Deposition of Christopher Bouton, attached as Exhibit 2 to Plaintiff’s Motion for Summary Judgment, [Doc. 37-2] at pp. 68-69). The Plaintiff testified that Manson “came up with the date.” (Id. at p. 69).

Although only selected portions of the Plaintiff’s deposition were initially filed, Manson produced the entirety of the deposition at the Court’s request. A complete copy of the deposition will be filed in the record. Manson, a marine construction company that specializes, among other things, in the building of wharves, piers, and bridges. (See Declaration of Ray Givan,2 attached as Exhibit 1 to Manson’s Motion for Summary Judgment, [Doc. 37-1] at ¶ 3). Manson

hired Plaintiff on January 6, 2021, as a carpenter3 to perform various discrete tasks in connection with the demolition of an existing dock and the construction of a new dock located at the Blount Island Marine Terminal in Jacksonville, Florida (the “BIMT Project”). (See Givan Declaration at ¶ 5; see also “New Employee Orientation Checklist,” attached to Givan Declaration as Exhibit 1-A). Plaintiff was injured when a 70-pound shackle fell on his left foot while he was working on a barge that held the

materials pulled from the water in connection with demolition of the existing dock (the “material barge”). (See Complaint, Doc. 1 at ¶ 7). Manson argues that Plaintiff was a general laborer at all relevant times, not a Jones Act seaman. In support thereof, Manson points to a sworn Declaration of Ray Givan, in which Mr. Givan discusses the nature of the BIMT Project and the Plaintiff’s work in connection therewith. According to Mr. Givan, the BIMT Project, which was shore-based and related solely to dock demolition and construction,

consisted of several distinct phases: (i) Phase I – driving piles and the complete demolition of the wharf while working on the land side of the BIMT dock, which lasted

2 In his Declaration, Mr. Givan states that he is Manson’s General Superintendent for the Gulf of Mexico and East Coast, has been employed by Manson since 2009, and is familiar with Manson’s business operations and business records. [Doc. 37-1 at ¶ 1].

3 In his deposition, the Plaintiff testified that he was told to “fill in the application as general … laborer, and that’s what I did.” See Deposition of Christopher Bouton, [Doc. 37-3, pp. 29-30]. until approximately March 2021 (Givan Declaration, ¶ 14); (ii) Phase II – demolition and removal of the piles and other materials that comprised the existing dock on the water side of the BIMT dock, which lasted from approximately March of 2021 to June

of 2021 (Id. at ¶ 15); and (iii) Phase III – construction of the new dock by driving new piles in place of those that were removed. The project was completed in March of 2022 (Id. at ¶ 7). According to Mr. Givan, all of Plaintiff’s work was located at the BIMT Project site or at an area nearby where Manson was offloading the old dock pilings. (Id. at ¶ 11). The Plaintiff was employed by Manson only during Phases I and II of the

project. It is undisputed that from his date of hire on January 6, 2021, through March 8, 2021, Plaintiff’s work consisted of pouring concrete and other discrete tasks in connection with the removal of the old piles and other materials that comprised the existing dock. Mr. Givan attests that all of the work performed by Plaintiff during this time period took place on land. (Id. at ¶ 14). And Bouton acknowledges that when he first started working for Manson, he was working on a pile driving crew on the “land side” of the Project. (See Affidavit of Christopher Bouton, attached as

Exhibit B to Plaintiff’s Opposition Brief, [Doc. 39-3] at p. 1). From March 9, 2021, through April 17, 2021, Plaintiff worked on Phase II of the Project. It is during this Phase that the parties dispute the nature of Plaintiff’s work. According to Manson, Bouton’s work during this period consisted almost exclusively of helping remove the piles of the existing dock using a crane working from the “spudded down” crane barge, MB1704. (Givan Declaration, ¶ 18). During this process, the crane operator removed the existing piles from the water and placed them on a separate spudded down “material barge,” located immediately next to MB1704. (Id.). Once the crane operator placed the piles on the material barge,

Bouton and other Manson laborers would remove the chain and shackle that connected the pile to the crane’s hook and lay the removed pile onto the material barge. (Id. at ¶ 19). Thus, Plaintiff’s primary job responsibilities consisted of unshackling the piles once the crane operator placed them on the material barge. (Id. at ¶ 20). It is undisputed that both the material barge and the crane barge were either spudded down or tied off when they were being used as work platforms at or

near the Blount Island Marine Terminal dock. (Id. at ¶ 17; see also Bouton Depo., p. 111). The record shows that MB1704 and the material barge were located approximately 20-30 feet from the shore, (Bouton Depo., pp. 205-206; Givan Declaration, ¶ 21), and they were situated side-by-side such that the Plaintiff could step back and forth between them. (Bouton Depo., p. 203). Plaintiff began each day’s work by boarding the MB1704 crane barge by a gangway or a short ride on a tugboat.

(Id. at pp. 203-209). While the Plaintiff estimates that his use of a gangway and tugboat was equal (“half and half”) (Id. at pp. 205-206), Manson argues that the Plaintiff accessed the MB1704 crane barge primarily via a gangway, and that a small “fleet boat” was only used when it was not feasible to use the gangway.4 (Givan Declaration, ¶ 23).

4 The Plaintiff testified that sometimes a gangway could not be used because piles were in the way. (Bouton Depo., p. 206). Plaintiff’s description of his job duties during Phase II is different. Plaintiff argues that, once Phase II started, his job switched from being exclusively “land side” work to “water side” work. That is, from early March until he was injured in April,

Plaintiff alleges that he worked aboard a group of vessels that were owned or leased by Manson and worked primarily on a “very large deck barge” with a crawler crane affixed to it. (See Plaintiff’s Opposition Brief, [Doc. 39] at p. 1). Plaintiff argues that “[i]f he was not on that barge pulling piles out of the St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oliver v. Scott
276 F.3d 736 (Fifth Circuit, 2002)
Condrey v. Suntrust Bank of GA
431 F.3d 191 (Fifth Circuit, 2005)
Lozano v. Ocwen Federal Bank, FSB
489 F.3d 636 (Fifth Circuit, 2007)
McLaurin v. Noble Drilling (U.S.), Inc.
529 F.3d 285 (Fifth Circuit, 2008)
Kirksey v. Tonghai Maritime
535 F.3d 388 (Fifth Circuit, 2008)
Duffie v. United States
600 F.3d 362 (Fifth Circuit, 2010)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
McDermott International, Inc. v. Wilander
498 U.S. 337 (Supreme Court, 1991)
Chandris, Inc. v. Latsis
515 U.S. 347 (Supreme Court, 1995)
Norfolk Shipbuilding & Drydock Corp. v. Garris
532 U.S. 811 (Supreme Court, 2001)
Kirksey v. P & O Ports Texas, Inc.
488 F. Supp. 2d 579 (S.D. Texas, 2007)
James Hefren v. Murphy Expl & Prodn Co., USA, et a
820 F.3d 767 (Fifth Circuit, 2016)
Amanda Riggio v. Wal-Mart Stores, Incorporated
850 F.3d 742 (Fifth Circuit, 2017)
Lonny Acker v. General Motors, L.L.C.
853 F.3d 784 (Fifth Circuit, 2017)
Sanchez v. Smart Fabricators of TX
997 F.3d 564 (Fifth Circuit, 2021)
Molina v. Home Depot
20 F.4th 166 (Fifth Circuit, 2021)
Endeavor Marine, Inc. v. Crane Operators, Inc.
234 F.3d 287 (Fifth Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Bouton v. Manson Construction Co, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bouton-v-manson-construction-co-lawd-2023.