Bolt Electric, Inc. v. The City of New York

223 F.3d 146, 2000 U.S. App. LEXIS 18672
CourtCourt of Appeals for the Second Circuit
DecidedAugust 3, 2000
Docket1999
StatusPublished
Cited by22 cases

This text of 223 F.3d 146 (Bolt Electric, Inc. v. The City of New York) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolt Electric, Inc. v. The City of New York, 223 F.3d 146, 2000 U.S. App. LEXIS 18672 (2d Cir. 2000).

Opinion

MORDUE, District Judge

Background

Plaintiff-appellant Bolt Electric, Inc. (“Bolt”) appeals from a judgment entered December 10, 1998, in the United States District Court for the Southern District of New York, Deborah A. Batts, Judge. The district court granted the motion of defendant-appellee City of New York (“City”) for summary judgment dismissing Bolt’s complaint in its entirety pursuant to Fed. R.Civ.P. 56(c), holding that there was no genuine issue as to any material fact. See Bolt Elec., Inc. v. City of New York, 1998 WL 851603 (S.D.N.Y. 1998). District Court jurisdiction is based on 28 U.S.C. § 1331(a)(1). Appellate jurisdiction is based on 28 U.S.C. § 1291. New York law applies. We reverse the award of summary judgment to the City and remand.

Facts

In March 1987, the City awarded Na-clerio Contracting Co., Inc. (“Naclerio”) a $58.7 million contract for a reconstruction project on the Eastern Parkway in Brooklyn, New York (“project”). In July 1987, L.K. Comstock, Co. (“Comstock”), the electrical subcontractor on the project, issued a purchase order to Bolt to supply lighting and related electrical materials on the project for a total price of $2,118,774. Naclerio ordered nonelectrical materials for the project directly from Bolt pursuant *148 to a separate purchase order reflected in a letter dated February 22,1988.

In 1990, Naclerio filed a petition for Chapter 11 bankruptcy protection while continuing to perform on the project. In the summer of 1991, Comstock withdrew from the project. Bolt declined to accept additional orders from Naclerio or to continue work under the February 1988 purchase order without the City’s assurance of payment.

Thus, the City wrote Bolt a letter dated September 25, 1991, bearing the signature of Tom Jelliffe, an Assistant Commissioner for the City Department of Transportation (“DOT”), over the typed signature line of Bernard McCoy, Deputy Commissioner of the DOT (“McCoy letter”). The McCoy letter stated:

I have been requested by Naclerio Contracting Co., Inc. to communicate with you regarding payment for materials supplied by your firm, to be incorporated into the above-captioned project.
All conforming material ordered by Na-elerio on their Purchase Order with you will be paid to Naclerio by the City of New York.
In the event Naclerio Contracting Co., Inc. defaults in its contract with the New York City Department of Transportation, the Department will purchase from Bolt Electric, Inc. all materials ordered specifically for the Eastern Parkway contract.

On September 30, 1991, Bolt and Com-stock entered into a settlement agreement pursuant to which Bolt received $119,110 from Comstock as payment in full for all materials delivered under the Comstock purchase order. Bolt also 'received full payment by Naclerio for all materials already delivered pursuant to the February 1988 purchase order. Bolt admits that it has been fully paid for all materials it delivered to Comstock and Naclerio for the project.

On October 1, 1991, Naclerio issued a purchase order to Bolt in the amount of $2,126,746.20 for lighting fixtures not yet delivered under the Comstock purchase order. On October 1, 1992, the City declared Naclerio in default of the project contract. Bolt claims that both before and after that date, City representatives directed Bolt to continue performing on the project and that, in reliance thereon, Bolt continued to work with its vendors and the City in planning, developing prototypes and securing architectural approval of lighting fixtures for the project. It is undisputed that, subsequent to the date of the McCoy letter, Bolt neither provided further materials to the project nor contracted with any vendor to do so.

Pursuant to a performance bond issued on April 7, 1987, Aetna Casualty and Surety Co. (“Aetna”) assumed responsibility for completing the project and named Tully Construction, Inc. as completion contractor. Welsbach Electric, Inc., the new electrical subcontractor selected by Tully Construction, Inc., notified Bolt on February 12, 1993, that it had selected Spring City Electrical Manufacturing Co. instead of Bolt as lighting supplier for completion of the project. The City and Aetna thereafter refused Bolt’s demands that the City purchase from Bolt the materials specified in the February 1988 and October 1991 purchase orders.

Procedural History

On May 27, 1993, Bolt filed the Amended Complaint herein, setting forth a breach of contract claim against the City. Bolt claims that in reliance on the McCoy letter and the October 1991 purchase order it “expended substantial sums and incurred potential liabilities in its efforts to execute that purchase order” and that it continued to perform under the February 1988 purchase order. Bolt further claims that the City refused “to take delivery of and pay for the materials ordered by Na-clerio,” and seeks approximately $2,500,000 in damages. Bolt’s claims against defendant Spring City Electrical Manufacturing Co., the electrical supplier on the project *149 selected by Welsbach Electric, Inc., have been settled and are not involved in this appeal.

By judgment entered March 31, 1994, the United States District Court for the Southern District of New York, Sonia So-tomayor, Judge, granted the City’s motion to dismiss the complaint pursuant to Fed.R.Civ.P. 12(b)(6). The district court held that Bolt could not recover against the City under the alleged guaranty created by the McCoy letter because it had not been filed with and endorsed by the City Comptroller in compliance with section 6-101 of the New York City Administrative Code. On appeal, another panel of this Court disagreed, reversed the district court’s judgment and remanded the case for further proceedings. See Bolt Elec. Inc. v. City of New York, 53 F.3d 465, 470 (2d Cir.1995).

The City thereafter moved for summary judgment pursuant to Fed.R.Civ.P. 56(c) on the ground that there was no genuine issue as to any material fact. The United States District Court for the Southern District of New York, Deborah A. Batts, Judge, determined, based on the “plain language” of the McCoy letter that it was a guaranty by the City to pay for materials “ordered specifically” by Bolt, which the Court read as referring to materials supplied by Bolt or ordered by Bolt from its vendors. The Court noted that after the date of the McCoy letter, Bolt never supplied any materials or entered into'any contracts to provide any materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melville v. Hop Energy, LLC
S.D. New York, 2023
Verso Corporation v.
Third Circuit, 2020
UMB Bank, National Ass'n v. Airplanes Ltd.
260 F. Supp. 3d 384 (S.D. New York, 2017)
Powers v. Stanley Black & Decker, Inc.
137 F. Supp. 3d 358 (S.D. New York, 2015)
Wells Fargo Bank, N.A. v. Wrights Mill Holdings, LLC
127 F. Supp. 3d 156 (S.D. New York, 2015)
In re the Trusteeships Created by Tropic CDO I Ltd.
92 F. Supp. 3d 163 (S.D. New York, 2015)
British Telecommunications PLC v. Coxcom, Inc.
9 F. Supp. 3d 423 (D. Delaware, 2014)
CSI Investment Partners II, L.P. v. Cendant Corp.
507 F. Supp. 2d 384 (S.D. New York, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
223 F.3d 146, 2000 U.S. App. LEXIS 18672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolt-electric-inc-v-the-city-of-new-york-ca2-2000.