Boise Cascade Corporation, Composite Can Division v. Secretary of Labor and Occupational Safety and Health Review Commission

694 F.2d 584, 11 BNA OSHC 1010, 11 OSHC (BNA) 1010, 1982 U.S. App. LEXIS 23410
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 10, 1982
Docket77-2201
StatusPublished
Cited by4 cases

This text of 694 F.2d 584 (Boise Cascade Corporation, Composite Can Division v. Secretary of Labor and Occupational Safety and Health Review Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boise Cascade Corporation, Composite Can Division v. Secretary of Labor and Occupational Safety and Health Review Commission, 694 F.2d 584, 11 BNA OSHC 1010, 11 OSHC (BNA) 1010, 1982 U.S. App. LEXIS 23410 (9th Cir. 1982).

Opinion

HUG, Circuit Judge:

Boise Cascade Corporation petitions for review of a decision of the Occupational Safety and Health Review Commission enforcing a citation for violation of occupational noise standards. The Secretary of Labor cited the company for failure to install engineering and administrative controls to abate noise levels and failure to implement a hearing conservation program. We affirm the determination that Boise Cascade violated the standard and the requirement that it institute an effective hearing conservation program. Because the Secretary failed to prove that feasible engineering controls exist, we vacate the portions of the citation requiring implementation of such controls.

Boise Cascade Corporation operates a plant in Turner, Kansas, 1 at which composite cans are formed. 2 Approximately 125 persons are employed at the plant.

In February, 1972, an Occupational Safety and Health Administration (“OSHA”) industrial hygienist inspected the plant to determine the employees’ noise exposure. He recorded noise levels in excess of the 90 dBA level permitted under the applicable OSHA standard, 29 C.F.R. § 1910.95 (1981). Based on the hygienist’s observations, the Secretary issued a citation on March 6, 1972, alleging a violation of 29 C.F.R. § 1910.95. The citation noted violations in two different work areas. The first was the area where punch presses were located. The second area contained automatic seamers, hand seamers, and winders. 3

Boise Cascade contested the citation. At a hearing before an Administrative Law Judge (“ALJ”), the company conceded that the punch presses produced noise in excess of permissible levels, but argued that punch press workers were adequately protected by the requirement that they wear earplugs. As evidence of its good faith, the company presented testimony as to its efforts to develop prototype engineering controls for the punch presses. Boise Cascade denied that the remaining equipment produced noise in excess of permissible levels, and challenged the technique by which the hygienist had made his observations. It presented expert witnesses who described appropriate sound measurement techniques.

The ALJ found that the hygienist’s testimony was sufficient evidence to support the citation. He determined that noise levels in all pertinent plant areas had exceeded 90 dBA during approximately seven hours of the regular workday. He concluded Boise *587 Cascade had not implemented an effective hearing conservation program to protect its workers, and that protection through administrative controls was not feasible. Finally, the ALJ concluded that Boise Cascade’s efforts to design engineering controls for the punch presses had confronted the company with “enormous problems.” In view of the developmental difficulties and the company’s apparent good faith, the ALJ expanded the schedule for implementation of engineering controls. He did order, however, that “Respondent shall, by June 1, 1975, complete feasible equipment and/or facility modifications to attenuate those areas wherein excessive noise was found.”

Boise Cascade sought review by the Commission under 29 U.S.C. § 661(i). The following issues were specified for Commission review:

(1) Whether the evidence adduced in this case establishes a violation of the Act for noncompliance with 29 C.F.R. § 1910.95.
(2) Whether 29 C.F.R. § 1910.95(b)(1) requires the employer to utilize feasible engineering or administrative controls if personal protective equipment used by the employees reduces the sound levels to that required by Table G-16.
(3) Whether 29 C.F.R. § 1910.95(b) is so vague as to be unenforceable.

The Commission affirmed the ALJ’s conclusion that the OSHA hygienist’s testimony provided sufficient credible evidence that noise levels exceeded permissible standards. 4 The second issue — whether personal protective equipment could be used in lieu of administrative or engineering eontrols — was not reached, because the Commission determined that Boise Cascade had not implemented and enforced a protective equipment program. 5 Finally, the Commission held that the standard outlined in 29 C.F.R. § 1910.95 is not unenforceably vague. It pointed to Boise Cascade’s efforts at compliance as evidence that the standard is understandable. 6

Following the Commission’s decision, Boise Cascade removed the punch presses from the plant. The parties agree that only the portions of the citation concerning the winders and seamers are at issue in this appeal.

In this enforcement action, our jurisdiction to review the Commission’s decision is provided by 29 U.S.C. § 660(a) and by 5 U.S.C. § 706. Titanium Metals Corp. of America v. Usery, 579 F.2d 536, 540 & n. 2 (9th Cir.1978); Brennan v. OSHRC, 511 F.2d 1139, 1141 (9th Cir.1975). We must affirm the Commission’s finding that Boise Cascade violated 29 C.F.R. § 1910.95 if that finding is “supported by substantial evidence on the record considered as a whole.” 29 U.S.C. § 660(a).

Boise Cascade first challenges the finding of the ALJ, affirmed by the Commission, that its equipment produced noise in excess of permissible levels as set out in Table G-16 of 29 C.F.R. § 1910.95. At the administrative hearing, the Secretary bore the burden of proof on this issue; he was required to prove the violation by a preponderance of the evidence. See 29 C.F.R. § 2200.73(a) (1981); B & B Insulation, Inc. v. OSHRC, 583 F.2d 1364, 1372 (5th Cir. 1978); Marshall v. Knutson Constr. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
694 F.2d 584, 11 BNA OSHC 1010, 11 OSHC (BNA) 1010, 1982 U.S. App. LEXIS 23410, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boise-cascade-corporation-composite-can-division-v-secretary-of-labor-and-ca9-1982.