Zurn Industries, Inc. v. National Labor Relations Board

680 F.2d 683, 110 L.R.R.M. (BNA) 2944, 1982 U.S. App. LEXIS 17744
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 2, 1982
Docket81-7219, 81-7331
StatusPublished
Cited by18 cases

This text of 680 F.2d 683 (Zurn Industries, Inc. v. National Labor Relations Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zurn Industries, Inc. v. National Labor Relations Board, 680 F.2d 683, 110 L.R.R.M. (BNA) 2944, 1982 U.S. App. LEXIS 17744 (9th Cir. 1982).

Opinion

SCHWARZER, District Judge:

Petitioner, Zurn Industries, Inc. (Zurn), appeals from a decision of the National Labor Relations Board (Board) holding that Zurn’s discharge of six employees was an unfair labor practice in violation of Section 8(a)(1) of the National Labor Relations Act (the Act), 29 U.S.C. § 158(a)(1). 1 The Board cross-appeals for enforcement of the order.

Zurn contracted with the Washington Public Power Supply System to design and construct concrete cooling towers for a nuclear power plant near Satsop, Washington. The six employees in question were Zurn’s concrete placement crew (“mud crew”) for the jobsite. On August 15, 1979, these employees were among those attending one of Zurn’s regular weekly safety meetings. The main topic at the meeting was employee concern over Zurn’s newly acquired safety skip, a device used to move injured workers. Procurement of an adequate safety skip had been a source of controversy between the workers and management for several months. The meeting generated a heated discussion. Field Superintendent Buffington came from his adjacent office and interrupted the meeting, telling the group in an annoyed tone that he was “tired of hearing all this commotion about safety and especially about this safety skip,” that dissatisfied employees should “talk to the steward about it,” and that anyone who did not like that procedure could “pick up their checks.” 2 The meeting broke up when Buffington finished his remarks.

After the meeting, the mud crew reported for its concrete pour for the day. On arriving at the jobsite, the men discovered that the forms were not yet finished, lacking safety handrails and ladders and fully capped rebars. The crew refused to begin the pour because the forms appeared both incomplete and unsafe. They reported the problem to the safety officer and waited for the forms to be completed, ignoring instructions from Quality Control Supervisor Lewis that Buffington wanted them to start work. 3 The crew began the pour after lunch, but met with further difficulties when several pieces of equipment, the tre-mie chute carrying the concrete and two of the three vibrators used to prevent separation and air pocket formation, broke down.

The forms were removed two days later, on August 17, revealing serious deficiencies in the concrete structure including rock pockets and holes. The flaws in the pour were immediately reported to jobsite super *686 visors. That afternoon, the entire mud crew save the foreman received termination notices. Each notice stated that the worker to whom it was issued “does not work to our satisfaction.” 4 On receiving the notices, the crew members assembled at Buff-ington’s office to protest their discharges. Although admitting the poor quality of the August 15 vibration work, they argued that the flaws were not their fault but were largely due to machine deficiencies and breakdowns. Two of them also objected that four of the workers discharged had not been engaged in any work related to vibration at the August 15 pour. Buffington told the crew that the poor quality of the August 15 vibration work was the reason for their discharges. Three employees testified that when pressed Buffington said further that an additional reason for their discharges was their complaints about safety. 5

The crew members filed grievances with their union and unfair labor practice charges with the federal and state agencies. The Board issued a complaint against Zurn alleging violations of Section 8(a)(1) of the Act. An administrative law judge (ALJ) heard the evidence and concluded that the General Counsel had failed to prove that the crew had been discharged for engaging in the protected activity of expressing safety concerns. The Board reviewed the record de novo and found that Buffington’s remarks at the August 15 safety meeting threatened employees with discharge for engaging in protected activities relating to job safety, and that the General Counsel had made a prima facie showing that the motive for the crew’s discharge was its complaints about safety. The Board went on to find that the asserted reason for the discharge based on the unsatisfactory work of the crew was a pretext, and that a violation of Section 8(a)(1) had therefore been proved.

We must enforce the Board’s order if the Board correctly applied the law and if its findings are supported by substantial evidence on the record viewed as a whole. NLRB v. Nevis Industries Inc., 647 F.2d 905, 908 (9th Cir. 1981). Our review therefore entails a two-step process: did the Board apply a correct rule, and does substantial evidence support its order.

A. The Board’s Standard for Causation

This case again brings before the court the recurring problem of mixed, dual or pretextual motive discharges. 6 In its recent decision in Wright Line, a Division of Wright Line, Inc., 251 N.L.R.B. No. 150 (1980), the Board sought to end the confusion generated by the use of a variety of tests for gauging the lawfulness of such discharges. See Western Exterminator Co. v. NLRB, 565 F.2d 1114, 1118 (9th Cir. 1977). It rejected both the “in part” test, under which the General Counsel had only to show the presence of a prohibited motive, and the “dominant motive” test requiring proof that an unlawful motive was the motivating cause for discharge. Taking its lead from the Supreme Court’s decision in Mt. Healthy City School District Bd. of Education v. Doyle, 429 U.S. 274, 97 S.Ct. 568, 50 L.Ed.2d 471 (1977), 7 the Board devel *687 oped a two-part test. 8 Under that test, the General Counsel has the initial burden of proving that protected activity was a substantial factor in bringing about the discharge. Once the General Counsel has made this prima facie case, the burden shifts to the employer to prove, as an “affirmative defense,” that the decision would have been the same in the absence of the protected activity.

This court has previously approved the Wright Line standard in NLRB v. Nevis Industries, Inc., supra; see also Doug Hartley Inc. v. NLRB, 669 F.2d 579, 580-81 (9th Cir. 1982); and Lippincott Industries, Inc. v. NLRB, supra, 661 F.2d at 115. 9 Recent decisions by the First and Third Circuits raise a question, however, whether the test as formulated in Wright Line is entirely consistent with the Act. NLRB v. Wright

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
680 F.2d 683, 110 L.R.R.M. (BNA) 2944, 1982 U.S. App. LEXIS 17744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zurn-industries-inc-v-national-labor-relations-board-ca9-1982.