BJB ELECTRIC LP v. BRIDGELUX, INC.

District Court, N.D. California·Decided December 15, 2023·No. 3:22-cv-01886·Unknown

Opinion

BJB ELECTRIC LP, Case No. 22-cv-01886-RS Plaintiff, v. OPINION AND ORDER BRIDGELUX, INC., Defendant.

I. Introduction Plaintiff BJB Electric LP (“BJB Electric”) and Defendant Bridgelux, Inc. (“Bridgelux”) contracted in March 2016 hoping to sell tens of millions of units of their product: light-emitting diodes (“LEDs”) made by Bridgelux encased in BJB Electric-provided holders (the “Holders”). Their contract (the “Letter Agreement”) contemplated BJB Electric would obtain orders for approximately 15 million Holders within a four-year Cost Sharing Period spanning from October 2016 to October 2020. This did not happen. This case proceeded to a bench trial in August 2023. The parties presented testimony and other evidence related to what the parties intended at the time of contracting and their subsequent course of dealing. In particular, the parties focused on the meaning of the phrase “obtain orders” in Article 2 of the Letter Agreement. BJB Electric’s breach of contract claim boils down to whether it “obtained orders” for 15 million Holders during the Cost Sharing Period and, therefore, was entitled to liquidated damages as specified in Article 2. This Opinion and Order comprises the findings of fact and conclusions of law required by Federal Rule of Civil Procedure 52(a).1 It is based on the evidence presented at trial, the oral arguments of counsel, and the parties’ pre- and post-trial briefing. For the reasons explained below, BJB Electric prevails on its breach of contract claim and is entitled to the liquidated damages provided for in the Letter Agreement. II. Parties Plaintiff BJB Electric is a company that sells products to lighting manufacturers, including the Holders at issue in this case. BJB Electric is the American subsidiary of BJB Germany, where BJB is headquartered. Defendant Bridgelux is a lighting company that produces LEDs. III. The Letter Agreement and the Cost Sharing Period BJB Electric and Bridgelux contracted on or around March 21, 2016, to engage in a joint business endeavor where BJB Electric would provide Holders for Bridgelux’s Vero 2.0 product series. The parties agreed BJB Electric would obtain orders for 15 million Holders within the four- year Cost Sharing Period; if it did not, the parties agreed Bridgelux would pay $0.08 per unit of the Shortfall Quantity to BJB Electric. The Cost Sharing Period lasted from October 2016 to October 2020. BJB Germany was the manufacturing entity responsible for producing the Holders. As of Summer 2020, Bridgelux had purchased only about 2.2 million Holders from BJB Electric (significantly fewer than expected), and BJB Electric pointed this out to Bridgelux. BJB Electric was far behind in obtaining the 15-million-unit Minimum Requirement for several potential reasons, including “the migration of lighting manufacturing” away from Western Europe, the imposition of a tariff on goods exchanged between the United States and China, and the COVID- 19 pandemic. Dkt. 123, at 6. On August 14, 2020, Bridgelux tendered P.O. 0801-01 to BJB Electric. P.O. 0801-01 purported to order the remaining 13 million Holders from BJB Electric for delivery to occur over the span of the next six years (until July 2026) in accordance with the 15-

1 To the extent any conclusions of law are inadvertently labeled as findings of fact (or vice versa), the findings and conclusions shall be considered “in [their] true light, regardless of the label that the . . . court may have placed on [them].” Tri–Tron Int’l v. Velto, 525 F.2d 432, 435–36 (9th Cir. 1975). million-unit Minimum Requirement. Under the terms of P.O. 0801-01, the majority of units were scheduled for delivery in the 2025 to 2026 period. Bridgelux’s prior orders did not contain similarly delayed delivery dates—indeed, Bridgelux did not have other vendors at the time to which it had submitted orders that extended six years into the future. BJB Electric did not immediately accept P.O. 0801-01. It viewed P.O. 0801-01 as a gesture that Bridgelux would continue selling the Holders despite falling behind on its original sales projections. BJB Electric asked Bridgelux to revise P.O. 0801-01 to condense the order to last four years instead of six and more evenly distribute the volumes of ordered Holders across time. Bridgelux replaced P.O. 0801-01 with P.O. 0831, but BJB Electric concluded this new purchase order was not substantially different than the purchase order it replaced. By the end of the Cost Sharing Period, BJB Electric had not accepted orders for 15 million Holders from Bridgelux. The parties continued negotiating until, a few months later (on December 24, 2020), Bridgelux submitted P.O. 1104-01.2 IV. BJB Electric’s Breach of Contract Claim Article 2 of the Letter Agreement executed by BJB Electric and Bridgelux provides as follows: If BJB is awarded the Holder Project (i.e. Bridgelux designates BJB as the supplier of the Holder), such units will be purchased by Bridgelux (or its designated contract manufacturer) under its purchase order at the pricing designated under Schedule A. However, if BJB fails to obtain orders for at least 15 million units (“Minimum Requirement”) of the Vero 2.0 Holder within 4 years after “First Availability” of the Vero 2.0 Holder (“Cost Sharing Period”), Bridgelux agrees that it or its contract manufacturer will purchase the “Shortfall Quantity” of such Vero 2.0 Holders at the pricing designated under Schedule A ($0.08 per unit) pursuant to a Bridgelux purchase order. Bridgelux (or its designated contract manufacturers) purchase order(s) will become mutually binding upon BJB’s written confirmation to Bridgelux of said purchase order(s). The “Shortfall Quantity” is the difference between the Minimum Requirement and the number of Vero 2.0 Holders ordered (“Ordered Holders”) during the Cost Sharing Period. “First Availability” is the date that “Shippable Holders” are available for sale and shipment by BJB (with such availability then indicated via written confirmation from BJB to Bridgelux). “Shippable Holders” are the

Free access — add to your briefcase to read the full text and ask questions with AI

BJB ELECTRIC LP v. BRIDGELUX, INC., (N.D. Cal. 2023).

BJB ELECTRIC LP v. BRIDGELUX, INC. (BJB ELECTRIC LP v. BRIDGELUX, INC.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brandwein v. Butler CA4/1
218 Cal. App. 4th 1485 (California Court of Appeal, 2013)
Pacific Gas & Electric Co. v. G. W. Thomas Drayage & Rigging Co.
442 P.2d 641 (California Supreme Court, 1968)
Garrett v. Coast & Southern Federal Savings & Loan Ass'n
511 P.2d 1197 (California Supreme Court, 1973)
Ridgley v. Topa Thrift & Loan Assn.
953 P.2d 484 (California Supreme Court, 1998)
Applied Elastomerics, Inc. v. Z-Man Fishing Products, Inc.
521 F. Supp. 2d 1031 (N.D. California, 2007)
Nystrom v. First Nat. Bank of Fresno
81 Cal. App. 3d 759 (California Court of Appeal, 1978)
Lortz v. Connell
273 Cal. App. 2d 286 (California Court of Appeal, 1969)
Republic Bank v. Marine National Bank
45 Cal. App. 4th 919 (California Court of Appeal, 1996)
Weber, Lipshie & Co. v. Christian
52 Cal. App. 4th 645 (California Court of Appeal, 1997)
Mountain Air Enters., LLC v. Sundowner Towers, LLC
398 P.3d 556 (California Supreme Court, 2017)
People v. Lundquist
24 P. 153 (California Supreme Court, 1890)
East West Bank v. Altadena Lincoln Crossing, LLC
598 B.R. 633 (C.D. California, 2019)
Dollar Tree Stores Inc. v. Toyama Partners LLC
875 F. Supp. 2d 1058 (N.D. California, 2012)