BJB ELECTRIC LP v. BRIDGELUX, INC.

District Court, N.D. California·Decided December 15, 2023·No. 3:22-cv-01886·Unknown

Opinion

1 2 3 4 5 6 9 BJB ELECTRIC LP, 10 Case No. 22-cv-01886-RS Plaintiff, 11 v. OPINION AND ORDER 12 BRIDGELUX, INC., 13 Defendant. 14

15 I. Introduction 16 Plaintiff BJB Electric LP (“BJB Electric”) and Defendant Bridgelux, Inc. (“Bridgelux”) 17 contracted in March 2016 hoping to sell tens of millions of units of their product: light-emitting 18 diodes (“LEDs”) made by Bridgelux encased in BJB Electric-provided holders (the “Holders”). 19 Their contract (the “Letter Agreement”) contemplated BJB Electric would obtain orders for 20 approximately 15 million Holders within a four-year Cost Sharing Period spanning from October 21 2016 to October 2020. This did not happen. 22 This case proceeded to a bench trial in August 2023. The parties presented testimony and 23 other evidence related to what the parties intended at the time of contracting and their subsequent 24 course of dealing. In particular, the parties focused on the meaning of the phrase “obtain orders” in 25 Article 2 of the Letter Agreement. BJB Electric’s breach of contract claim boils down to whether 26 it “obtained orders” for 15 million Holders during the Cost Sharing Period and, therefore, was 27 entitled to liquidated damages as specified in Article 2. This Opinion and Order comprises the 1 findings of fact and conclusions of law required by Federal Rule of Civil Procedure 52(a).1 It is 2 based on the evidence presented at trial, the oral arguments of counsel, and the parties’ pre- and 3 post-trial briefing. For the reasons explained below, BJB Electric prevails on its breach of contract 4 claim and is entitled to the liquidated damages provided for in the Letter Agreement. 5 II. Parties 6 Plaintiff BJB Electric is a company that sells products to lighting manufacturers, including 7 the Holders at issue in this case. BJB Electric is the American subsidiary of BJB Germany, where 8 BJB is headquartered. Defendant Bridgelux is a lighting company that produces LEDs. 9 III. The Letter Agreement and the Cost Sharing Period 10 BJB Electric and Bridgelux contracted on or around March 21, 2016, to engage in a joint 11 business endeavor where BJB Electric would provide Holders for Bridgelux’s Vero 2.0 product 12 series. The parties agreed BJB Electric would obtain orders for 15 million Holders within the four- 13 year Cost Sharing Period; if it did not, the parties agreed Bridgelux would pay $0.08 per unit of 14 the Shortfall Quantity to BJB Electric. The Cost Sharing Period lasted from October 2016 to 15 October 2020. BJB Germany was the manufacturing entity responsible for producing the Holders. 16 As of Summer 2020, Bridgelux had purchased only about 2.2 million Holders from BJB Electric 17 (significantly fewer than expected), and BJB Electric pointed this out to Bridgelux. BJB Electric 18 was far behind in obtaining the 15-million-unit Minimum Requirement for several potential 19 reasons, including “the migration of lighting manufacturing” away from Western Europe, the 20 imposition of a tariff on goods exchanged between the United States and China, and the COVID- 21 19 pandemic. Dkt. 123, at 6. On August 14, 2020, Bridgelux tendered P.O. 0801-01 to BJB 22 Electric. P.O. 0801-01 purported to order the remaining 13 million Holders from BJB Electric for 23 delivery to occur over the span of the next six years (until July 2026) in accordance with the 15- 24

25 1 To the extent any conclusions of law are inadvertently labeled as findings of fact (or vice versa), 26 the findings and conclusions shall be considered “in [their] true light, regardless of the label that the . . . court may have placed on [them].” Tri–Tron Int’l v. Velto, 525 F.2d 432, 435–36 (9th Cir. 27 1975). 1 million-unit Minimum Requirement. Under the terms of P.O. 0801-01, the majority of units were 2 scheduled for delivery in the 2025 to 2026 period. Bridgelux’s prior orders did not contain 3 similarly delayed delivery dates—indeed, Bridgelux did not have other vendors at the time to 4 which it had submitted orders that extended six years into the future. 5 BJB Electric did not immediately accept P.O. 0801-01. It viewed P.O. 0801-01 as a gesture 6 that Bridgelux would continue selling the Holders despite falling behind on its original sales 7 projections. BJB Electric asked Bridgelux to revise P.O. 0801-01 to condense the order to last four 8 years instead of six and more evenly distribute the volumes of ordered Holders across time. 9 Bridgelux replaced P.O. 0801-01 with P.O. 0831, but BJB Electric concluded this new purchase 10 order was not substantially different than the purchase order it replaced. By the end of the Cost 11 Sharing Period, BJB Electric had not accepted orders for 15 million Holders from Bridgelux. The 12 parties continued negotiating until, a few months later (on December 24, 2020), Bridgelux 13 submitted P.O. 1104-01.2 14 IV. BJB Electric’s Breach of Contract Claim 15 Article 2 of the Letter Agreement executed by BJB Electric and Bridgelux provides as 16 follows: 17 If BJB is awarded the Holder Project (i.e. Bridgelux designates BJB as the supplier of the Holder), such units will be purchased by Bridgelux (or its designated contract manufacturer) 18 under its purchase order at the pricing designated under Schedule A. However, if BJB fails to obtain orders for at least 15 million units (“Minimum Requirement”) of the Vero 2.0 19 Holder within 4 years after “First Availability” of the Vero 2.0 Holder (“Cost Sharing Period”), Bridgelux agrees that it or its contract manufacturer will purchase the “Shortfall 20 Quantity” of such Vero 2.0 Holders at the pricing designated under Schedule A ($0.08 per 21 unit) pursuant to a Bridgelux purchase order. Bridgelux (or its designated contract manufacturers) purchase order(s) will become mutually binding upon BJB’s written 22 confirmation to Bridgelux of said purchase order(s). The “Shortfall Quantity” is the difference between the Minimum Requirement and the number of Vero 2.0 Holders ordered 23 (“Ordered Holders”) during the Cost Sharing Period. “First Availability” is the date that 24 “Shippable Holders” are available for sale and shipment by BJB (with such availability then indicated via written confirmation from BJB to Bridgelux). “Shippable Holders” are the 25

26 2 It is somewhat unclear whether BJB Electric ever accepted P.O. 1104-01. BJB Electric claims 27 any such acceptance was explicitly conditioned on delivery dates and quantities remaining firm. production version of Vero 2.0 Holders which are then available for sale and shipment. 1 The crux of this dispute requires interpreting the 15-million-unit Minimum Requirement in 2 the context of the four-year Cost Sharing Period. BJB Electric claims Bridgelux breached the 3 Letter Agreement because (1) BJB Electric did not “obtain orders for at least 15 million units” 4 within the Cost Sharing Period and (2) BJB Electric is entitled to, but has not received, liquidated 5 damages for the Shortfall Quantity amounting to $1,022,368.16.3 Bridgelux disputes that it 6 breached the Letter Agreement and claims it submitted orders for 15 million Holders. The parties 7 also dispute whether the liquidated damages sum constitutes an unenforceable penalty provision. 8 See Cal. Civ. Code § 1671 (contractual damages provisions unenforceable where they were 9 “unreasonable under the circumstances existing at the time the contract was made”). 10 V. Summary of Evidence 11 In this bench trial, the parties presented evidence regarding the meaning of key terms 12 contained in Article 2 and the scope of the parties’ dealings with one another.

Free access — add to your briefcase to read the full text and ask questions with AI

BJB ELECTRIC LP v. BRIDGELUX, INC., (N.D. Cal. 2023).

BJB ELECTRIC LP v. BRIDGELUX, INC. (BJB ELECTRIC LP v. BRIDGELUX, INC.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brandwein v. Butler CA4/1
218 Cal. App. 4th 1485 (California Court of Appeal, 2013)
Pacific Gas & Electric Co. v. G. W. Thomas Drayage & Rigging Co.
442 P.2d 641 (California Supreme Court, 1968)
Garrett v. Coast & Southern Federal Savings & Loan Ass'n
511 P.2d 1197 (California Supreme Court, 1973)
Ridgley v. Topa Thrift & Loan Assn.
953 P.2d 484 (California Supreme Court, 1998)
Applied Elastomerics, Inc. v. Z-Man Fishing Products, Inc.
521 F. Supp. 2d 1031 (N.D. California, 2007)
Nystrom v. First Nat. Bank of Fresno
81 Cal. App. 3d 759 (California Court of Appeal, 1978)
Lortz v. Connell
273 Cal. App. 2d 286 (California Court of Appeal, 1969)
Republic Bank v. Marine National Bank
45 Cal. App. 4th 919 (California Court of Appeal, 1996)
Weber, Lipshie & Co. v. Christian
52 Cal. App. 4th 645 (California Court of Appeal, 1997)
Mountain Air Enters., LLC v. Sundowner Towers, LLC
398 P.3d 556 (California Supreme Court, 2017)
People v. Lundquist
24 P. 153 (California Supreme Court, 1890)
East West Bank v. Altadena Lincoln Crossing, LLC
598 B.R. 633 (C.D. California, 2019)
Dollar Tree Stores Inc. v. Toyama Partners LLC
875 F. Supp. 2d 1058 (N.D. California, 2012)