BJB ELECTRIC LP v. BRIDGELUX, INC.

CourtDistrict Court, N.D. California
DecidedJuly 28, 2023
Docket3:22-cv-01886
StatusUnknown

This text of BJB ELECTRIC LP v. BRIDGELUX, INC. (BJB ELECTRIC LP v. BRIDGELUX, INC.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BJB ELECTRIC LP v. BRIDGELUX, INC., (N.D. Cal. 2023).

Opinion

1 2 3 4 5 6 7 UNITED STATES DISTRICT COURT 8 NORTHERN DISTRICT OF CALIFORNIA 9 BJB ELECTRIC LP, 10 Case No. 22-cv-01886-RS Plaintiff, 11 v. ORDER DENYING MOTIONS FOR 12 PARTIAL SUMMARY JUDGMENT BRIDGELUX, INC., 13 Defendant. 14

15 BRIDGELUX, INC, 16 Counter-Claimant, 17 v.

18 BJB ELECTRIC LP,

19 Counter-Defendant. 20 Plaintiff BJB Electric LP filed this lawsuit alleging that Defendant Bridgelux, Inc. 21 breached a Letter Agreement requiring Defendant either to purchase a minimum number of LED 22 holders within four years of the product’s first availability (through October 2020) or to pay 23 liquidated damages. Defendant counterclaimed, alleging Plaintiff breached the Letter Agreement 24 beginning in April 2022 by changing the terms of the Agreement and refusing to deliver any 25 additional LED holders unless payment was made prior to delivery. Both parties have filed cross- 26 motions for partial summary judgment on Defendant’s liability for breach of the Letter 27 Agreement. For the reasons discussed below, both parties’ motions are denied. 1 I. BACKGROUND 2 Defendant Bridgelux, Inc. is a designer and manufacturer of LED lighting products. For its 3 new Vero 2.0 product series, Defendant needed LED holders—for which it approached Plaintiff, 4 BJB Electric LP, a supplier of components for lighting manufacturers. After negotiations, Plaintiff 5 agreed to produce the necessary holders for Defendant to purchase, and the parties executed a 6 Letter Agreement (the “Letter Agreement”) on March 21, 2016. Notably, the Letter Agreement 7 included a minimum purchase provision—the crux of the parties’ present dispute—which reads:

8 If BJB is awarded the Holder Project (i.e., Bridgelux designates BJB as the supplier of the Holder), such units will be purchased by Bridgelux (or its designated 9 contract manufacturer) under its purchase order at the pricing designated under Schedule A. However, if BJB fails to obtain orders for at least 15 million units 10 (“Minimum Requirement”) of the Vero 2.0 Holder within 4 years after “First Availability” of the Vero 2.0 Holder (“Cost Sharing Period”), Bridgelux agrees that 11 it or its contract manufacturer will purchase the “Shortfall Quantity” of such Vero 2.0 Holders at the pricing designated under Schedule A ($0.08 per unit) pursuant to 12 a Bridgelux purchase order. Bridgelux (or its designated contract manufacturers) purchase order(s) will become mutually binding upon BJB’s written confirmation 13 to Bridgelux of said purchase order(s). The “Shortfall Quantity” is the difference between the Minimum Requirement and the number of Vero 2.0 Holders ordered 14 (“Ordered Holders”) during the Cost Sharing Period. “First Availability” is the date that “Shippable Holders” are available for sale and shipment by BJB (with such 15 availability then indicated via written confirmation from BJB to Bridgelux). “Shippable Holders” are the production version of Vero 2.0 Holders which are then 16 available for sale and shipment. 17 Dkt. 65-1, Ex. 4 (“Letter Agreement”), art. 2. According to this provision, if Plaintiff “fail[ed] to 18 obtain orders for at least 15 million units” within four years of the product’s first availability 19 (known as the “Cost Sharing Period”), Defendant would pay liquidated damages. Id. As the First 20 Availability of the Vero 2.0 Holder occurred in October of 2016, the Cost Sharing Period expired 21 in October of 2020. 22 By the summer of 2020, Defendant had ordered only about 2.2 million holders. On August 23 14, 2020, Defendant submitted a purchase order (P.O. 0801-01) for approximately 13 million 24 holders. Rather than requesting delivery a short while after purchase, P.O. 0801-01 set forth a 25 delivery schedule stretching over the following 68 months. 26 After noting that 53% of the sales volume in P.O. 0801-01 would occur in 2025 and 2026, 27 Plaintiff asked Defendant to revise the purchase order on August 18, 2020. Defendant submitted a 1 revised purchase order (P.O. 0831) ten days later, on August 28, 2020, which contemplated a 2 delivery schedule of 66 months. When submitting P.O. 0831, Defendant noted that Plaintiff had 3 not accepted P.O. 0801-01. Though Plaintiff acknowledged receipt of P.O. 0831 on September 3, 4 2020, it told Defendant that it did not see any significant differences between the two purchase 5 orders. Plaintiff told Defendant that it would work with its German counterpart to determine how 6 to proceed, but ultimately never seemed to accept the order. The parties negotiated, but were 7 unable to reach an agreement before the end of the Cost Sharing Period. Believing that Defendant 8 breached the Letter Agreement by failing to order at least 15 million units during the Cost Sharing 9 Period, Plaintiff filed the instant suit. 10 II. LEGAL STANDARD 11 Summary judgment is proper “if the movant shows that there is no genuine dispute as to 12 any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). 13 The purpose of summary judgment “is to isolate and dispose of factually unsupported claims or 14 defenses.” Celotex v. Catrett, 477 U.S. 317, 323–24 (1986). The moving party “always bears the 15 initial responsibility of informing the district court of the basis for its motion, and identifying 16 those portions of the pleadings, depositions, answers to interrogatories, and admissions on file, 17 together with the affidavits, if any, which it believes demonstrate the absence of a genuine issue of 18 material fact.” Id. at 323 (internal quotation marks omitted). If it meets this burden, the moving 19 party is then entitled to judgment as a matter of law when the non-moving party fails to make a 20 sufficient showing on an essential element of the case with respect to which it bears the burden of 21 proof at trial. Id. at 322–23. 22 To preclude the entry of summary judgment, the non-moving party must bring forth 23 material facts—that is, “facts that might affect the outcome of the suit under the governing law[.]” 24 Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The opposing party “must do more 25 than simply show that there is some metaphysical doubt as to the material facts.” Matsushita Elec. 26 Indus. Co. v. Zenith Radio, 475 U.S. 574, 586 (1986). The trial court must “draw all justifiable 27 inferences in favor of the nonmoving party, including questions of credibility and of the weight to 1 be accorded particular evidence.” Masson v. New Yorker Mag., Inc., 501 U.S. 496, 520 (1991) 2 (citing Anderson, 477 U.S. at 255). “Where the record taken as a whole could not lead a rational 3 trier of fact to find for the non-moving party,” however, “there is no ‘genuine issue for trial.’” 4 Matsushita, 475 U.S. at 587. 5 Contract interpretation is a question of law, and thereby amenable to summary judgment, if 6 (1) the contract is not ambiguous; or (2) the contract is ambiguous but no parol evidence is 7 admitted or the parol evidence is not in conflict. Walter E. Heller W., Inc. v. Tecrim Corp., 196 8 Cal. App. 3d 149, 158 (1987). A contract is ambiguous when “on its face it is capable of two 9 different reasonable interpretations.” Republic Bank v. Marine Nat’l Bank, 45 Cal. App. 4th 919, 10 924 (1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Masson v. New Yorker Magazine, Inc.
501 U.S. 496 (Supreme Court, 1991)
People v. Gamble
8 Cal. App. 3d 142 (California Court of Appeal, 1970)
Republic Bank v. Marine National Bank
45 Cal. App. 4th 919 (California Court of Appeal, 1996)
City of Hope National Medical Center v. Genentech, Inc.
181 P.3d 142 (California Supreme Court, 2008)
Essex Walnut Owner L.P. v. Aspen Specialty Ins. Co.
335 F. Supp. 3d 1146 (N.D. California, 2018)
Best Buy Stores, L.P. v. Manteca Lifestyle Center, LLC
859 F. Supp. 2d 1138 (E.D. California, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
BJB ELECTRIC LP v. BRIDGELUX, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bjb-electric-lp-v-bridgelux-inc-cand-2023.